Underwater cast-in-place pile dismantling process
The invention relates to an underwater cast-in-place pile dismantling technology, and belongs to the technical field of cast-in-place pile dismantling, and the underwater cast-in-place pile dismantling technology comprises the following steps: installing a guide tool on the whole cast-in-place pile, enabling a first rope saw to bypass the guide tool, and installing the first rope saw on a first sliding rail; the first sliding rails are located on the two sides of the top beam in the arrangement direction of the underwater cast-in-place piles. Rope penetrating holes allowing a second rope saw to penetrate through are drilled in the multiple underwater cast-in-place piles correspondingly, and the second rope saw sequentially penetrates through the multiple rope penetrating holes formed in the different underwater cast-in-place piles; the second rope saw is installed on the second sliding rail which is located on the crane ship. The whole cast-in-place piles are pre-hoisted through a crane on a crane ship, so that the crane can hoist the multiple underwater cast-in-place piles to be dismantled at the same time; a first wire saw is used for cutting the multiple underwater cast-in-place piles to be dismantled in the first direction at the same time for one time; a second wire saw is used for conducting secondary cutting on the multiple underwater cast-in-place piles to be dismantled at the same time in the second direction; when the first rope saw and/or the second rope saw cut the underwater cast-in-place pile, the crane provides supporting force for the underwater cast-in-place pile to be dismantled, and the underwater cast-in-place pile is prevented from toppling over.
本发明涉及一种水下灌注桩拆除工艺,属于灌注桩拆除技术领域,其中水下灌注桩拆除工艺包括以下步骤:在灌注桩整体安装导向工装,使第一绳锯绕过导向工装设置,第一绳锯安装于第一滑轨,第一滑轨位于冠梁沿水下灌注桩的排布方向的两侧;在多个水下灌注桩分别钻设供第二绳锯穿过的穿绳孔,将第二绳锯依次穿过设于不同水下灌注桩的多个穿绳孔;第二绳锯安装于第二滑轨,第二滑轨位于起重船;使用起重船上的起重机对灌注桩整体进行预吊装,以使起重机可以同时吊装多个待拆除的水下灌注桩;使用第一绳锯沿第一方向同时对多个待拆除的水下灌注桩进行一次切割;使用第二绳锯沿第二方向同时对多个待拆除的水下灌注桩进行二次切割;其中,第一绳锯和/或第二绳锯切割水下灌注桩时,起重机对待拆除的水下灌注桩提供支持力,防止水下灌注桩倾倒。
Underwater cast-in-place pile dismantling process
The invention relates to an underwater cast-in-place pile dismantling technology, and belongs to the technical field of cast-in-place pile dismantling, and the underwater cast-in-place pile dismantling technology comprises the following steps: installing a guide tool on the whole cast-in-place pile, enabling a first rope saw to bypass the guide tool, and installing the first rope saw on a first sliding rail; the first sliding rails are located on the two sides of the top beam in the arrangement direction of the underwater cast-in-place piles. Rope penetrating holes allowing a second rope saw to penetrate through are drilled in the multiple underwater cast-in-place piles correspondingly, and the second rope saw sequentially penetrates through the multiple rope penetrating holes formed in the different underwater cast-in-place piles; the second rope saw is installed on the second sliding rail which is located on the crane ship. The whole cast-in-place piles are pre-hoisted through a crane on a crane ship, so that the crane can hoist the multiple underwater cast-in-place piles to be dismantled at the same time; a first wire saw is used for cutting the multiple underwater cast-in-place piles to be dismantled in the first direction at the same time for one time; a second wire saw is used for conducting secondary cutting on the multiple underwater cast-in-place piles to be dismantled at the same time in the second direction; when the first rope saw and/or the second rope saw cut the underwater cast-in-place pile, the crane provides supporting force for the underwater cast-in-place pile to be dismantled, and the underwater cast-in-place pile is prevented from toppling over.
本发明涉及一种水下灌注桩拆除工艺,属于灌注桩拆除技术领域,其中水下灌注桩拆除工艺包括以下步骤:在灌注桩整体安装导向工装,使第一绳锯绕过导向工装设置,第一绳锯安装于第一滑轨,第一滑轨位于冠梁沿水下灌注桩的排布方向的两侧;在多个水下灌注桩分别钻设供第二绳锯穿过的穿绳孔,将第二绳锯依次穿过设于不同水下灌注桩的多个穿绳孔;第二绳锯安装于第二滑轨,第二滑轨位于起重船;使用起重船上的起重机对灌注桩整体进行预吊装,以使起重机可以同时吊装多个待拆除的水下灌注桩;使用第一绳锯沿第一方向同时对多个待拆除的水下灌注桩进行一次切割;使用第二绳锯沿第二方向同时对多个待拆除的水下灌注桩进行二次切割;其中,第一绳锯和/或第二绳锯切割水下灌注桩时,起重机对待拆除的水下灌注桩提供支持力,防止水下灌注桩倾倒。
Underwater cast-in-place pile dismantling process
水下灌注桩拆除工艺
HE YAFENG (author) / LIU DEJIN (author) / KUANG LEI (author) / SONG RONGGUANG (author) / JU PENG (author) / WANG DIANWEN (author) / SHANG QIANKUN (author) / SONG JIANGWEI (author) / DONG LIYE (author) / NIU YINSHENG (author)
2024-06-25
Patent
Electronic Resource
Chinese
Construction method of cast-in-place bridge steel pipe pile underwater support dismantling system
European Patent Office | 2022
|Construction technology for dismantling reinforced concrete cast-in-place pile
European Patent Office | 2021
|Quick dismantling method for cast-in-place beam steel pipe pile support
European Patent Office | 2021
|Construction method for dismantling tool column in concrete pouring process of cast-in-place pile
European Patent Office | 2023
|Steel support and cast-in-place pile connecting structure and dismantling method thereof
European Patent Office | 2023
|