Hydraulic creeping formwork construction method for multi-hole wall
The invention discloses a hydraulic creeping formwork construction method for a multi-hole wall and relates to the technical field of hydraulic creeping formwork construction. The hydraulic creeping formwork construction method comprises the steps that the fixed position and the floating position of a bearing triangular support are obtained according to construction parameters of a building; the mounting position corresponds to the fixed position or the floating position; in the formwork climbing process, according to the position of the hole, the bearing triangular support at the fixed position and/or the floating position is selected as the climbing position, and meanwhile the position of the guide rail is adjusted according to the climbing position; when a multi-hole wall is constructed, a fixed position and a floating position can be set according to the position of a hole so as to avoid a hole area as much as possible, it is guaranteed that the multi-hole wall can be normally used when the hydraulic climbing formwork system is adopted for construction, and the construction efficiency of the multi-hole wall is improved.
一种多洞口墙体的液压爬模施工方法涉及液压爬模施工技术领域,包括根据建筑物的施工参数得承重三角支架的固定位置以及浮动位置;以及与固定位置或浮动位置对应的附墙座的安装位置;在爬模过程中,根据洞口的位置,选择使用固定位置和/或浮动位置的承重三角支架作为爬升位置,同时根据爬升位置调整导轨的位置;利用上述设置的爬模结构对建筑进行爬模施工,本发明在对多洞口墙体进行施工时,能根据洞口的位置设置固定位置和浮动位置以尽可能避开洞口区域,保障多洞口墙体采用液压爬模系统施工中能正常使用,提升多洞口墙体的施工效率。
Hydraulic creeping formwork construction method for multi-hole wall
The invention discloses a hydraulic creeping formwork construction method for a multi-hole wall and relates to the technical field of hydraulic creeping formwork construction. The hydraulic creeping formwork construction method comprises the steps that the fixed position and the floating position of a bearing triangular support are obtained according to construction parameters of a building; the mounting position corresponds to the fixed position or the floating position; in the formwork climbing process, according to the position of the hole, the bearing triangular support at the fixed position and/or the floating position is selected as the climbing position, and meanwhile the position of the guide rail is adjusted according to the climbing position; when a multi-hole wall is constructed, a fixed position and a floating position can be set according to the position of a hole so as to avoid a hole area as much as possible, it is guaranteed that the multi-hole wall can be normally used when the hydraulic climbing formwork system is adopted for construction, and the construction efficiency of the multi-hole wall is improved.
一种多洞口墙体的液压爬模施工方法涉及液压爬模施工技术领域,包括根据建筑物的施工参数得承重三角支架的固定位置以及浮动位置;以及与固定位置或浮动位置对应的附墙座的安装位置;在爬模过程中,根据洞口的位置,选择使用固定位置和/或浮动位置的承重三角支架作为爬升位置,同时根据爬升位置调整导轨的位置;利用上述设置的爬模结构对建筑进行爬模施工,本发明在对多洞口墙体进行施工时,能根据洞口的位置设置固定位置和浮动位置以尽可能避开洞口区域,保障多洞口墙体采用液压爬模系统施工中能正常使用,提升多洞口墙体的施工效率。
Hydraulic creeping formwork construction method for multi-hole wall
一种多洞口墙体的液压爬模施工方法
LI TAO (author) / BAI JIAN (author) / XU MINGWEI (author) / DING WENLING (author) / WANG BIN (author) / LI BO (author)
2024-06-28
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
European Patent Office | 2023
|Thin-wall pier hydraulic creeping formwork system and construction method thereof
European Patent Office | 2021
|Steam curing method for hydraulic creeping formwork construction
European Patent Office | 2023
|