Full-depth foamed asphalt cold recycling construction method
The invention provides a full-depth foamed asphalt cold recycling construction method. The method comprises the following steps: S1, determining mechanical configuration; s2, determining the mix proportion design of the regenerated material; s3, test section construction; s4, in-situ cold recycling construction of the foamed asphalt; the milling hob II is far away from the milling hob I, so that the working depth of the milling hob II and the working depth of the milling hob II are different after adjustment, and the requirement of milling a deeper road surface is met; the adjustable screening mechanism can adjust the size of screen holes according to needs, so that the requirements of different sizes during sampling are met, and the convenience during use is also improved; the invention relates to the technical field of road engineering, in particular to a full-depth foamed asphalt cold recycling construction method. Aiming at the defects in the prior art, the invention develops a full-depth foamed asphalt cold recycling construction method which is convenient to realize asphalt pavement repair.
本发明提供了一种全深式泡沫沥青冷再生施工方法,包括以下步骤:S1:确定机械配置;S2:确定再生材料配合比设计;S3:试验段施工;S4:泡沫沥青就地冷再生施工;本发明中由于铣刨滚刀二远离铣刨滚刀一,从而确保了调节后铣刨滚刀二和铣刨滚刀二的工作深度不一样,也就满足了较深路面铣刨的需要;本发明中设置的可调筛选机构能够根据需要对筛孔的大小进行调节,从而满足了取样时不同大小的需要,也就提高了使用时候的便利性;本发明涉及道路工程技术领域,尤其涉及一种全深式泡沫沥青冷再生施工方法;本发明针对现有技术的不足,研制一种全深式泡沫沥青冷再生施工方法,该发明方便实现沥青路面修复。
Full-depth foamed asphalt cold recycling construction method
The invention provides a full-depth foamed asphalt cold recycling construction method. The method comprises the following steps: S1, determining mechanical configuration; s2, determining the mix proportion design of the regenerated material; s3, test section construction; s4, in-situ cold recycling construction of the foamed asphalt; the milling hob II is far away from the milling hob I, so that the working depth of the milling hob II and the working depth of the milling hob II are different after adjustment, and the requirement of milling a deeper road surface is met; the adjustable screening mechanism can adjust the size of screen holes according to needs, so that the requirements of different sizes during sampling are met, and the convenience during use is also improved; the invention relates to the technical field of road engineering, in particular to a full-depth foamed asphalt cold recycling construction method. Aiming at the defects in the prior art, the invention develops a full-depth foamed asphalt cold recycling construction method which is convenient to realize asphalt pavement repair.
本发明提供了一种全深式泡沫沥青冷再生施工方法,包括以下步骤:S1:确定机械配置;S2:确定再生材料配合比设计;S3:试验段施工;S4:泡沫沥青就地冷再生施工;本发明中由于铣刨滚刀二远离铣刨滚刀一,从而确保了调节后铣刨滚刀二和铣刨滚刀二的工作深度不一样,也就满足了较深路面铣刨的需要;本发明中设置的可调筛选机构能够根据需要对筛孔的大小进行调节,从而满足了取样时不同大小的需要,也就提高了使用时候的便利性;本发明涉及道路工程技术领域,尤其涉及一种全深式泡沫沥青冷再生施工方法;本发明针对现有技术的不足,研制一种全深式泡沫沥青冷再生施工方法,该发明方便实现沥青路面修复。
Full-depth foamed asphalt cold recycling construction method
一种全深式泡沫沥青冷再生施工方法
XIE YANBO (author) / GAO WENCHENG (author) / YUAN LIANWANG (author) / LI YUANYI (author) / ZHANG RUI (author) / SUN TINGSHUAI (author)
2024-07-02
Patent
Electronic Resource
Chinese
IPC:
E01C
Bau von Straßen, Sportplätzen oder dgl., Decken dafür
,
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE
Practical Experience with Cold In-Place Asphalt Recycling and Foamed Asphalt Full Depth Reclamation
British Library Conference Proceedings | 2006
|Foamed asphalt cold recycling construction method of pavement
European Patent Office | 2020
|Foamed asphalt integrated foaming beam for foamed asphalt cold-recycling plant mixing equipment
European Patent Office | 2020
|Laboratory Study on Cold Recycling with Foamed Asphalt
Trans Tech Publications | 2011
|Laboratory Study on Cold Recycling with Foamed Asphalt
British Library Conference Proceedings | 2011
|