The invention provides a construction method of a pedestrian suspension bridge. The construction method comprises the following steps: S1, cable saddle construction; s2, construction of a traction system; s3, guide rope construction; s4, bearing cable construction; s5, main cable construction; and S6, cable clamp sling construction. And S7, auxiliary construction. According to the scheme, the pilot cable, the transition cable and the traction cable are pulled in a reciprocating mode through the winches on the two banks of the river channel, finally the bearing cable is erected on the tops of the two banks through the traction cable, the main cable is rapidly installed on the tops of the two banks of the river channel through the bearing cable under the synchronous winding and unwinding effect of the winches on the two banks, and manual auxiliary tugboat and other equipment are not needed; and deep valleys and river channels can be quickly spanned, a large amount of engineering time is saved, meanwhile, control over the channel is not needed, and the equipment renting cost is also reduced.
本发明提供了一种人行悬索桥的施工方法,包括如下步骤:S1,索鞍施工;S2,牵引系统施工;S3,导索施工;S4,承重索施工;S5,主缆施工;S6,索夹吊索施工。S7,附属施工。本方案通过河道两岸的卷扬机往复的牵引先导索、过渡索、牵引索,最后通过牵引索的作用将承重索架设在两岸塔顶,且承重索在两岸卷扬机同步收放的作用下快速的将主缆安装在河道两岸的塔顶,不需要依靠人工辅助拖船等设备,可以快速跨越深谷及河道,节约了大量的工程时间,同时无需对航道进行管制,也降低了设备租用成本。
Construction method of pedestrian suspension bridge
The invention provides a construction method of a pedestrian suspension bridge. The construction method comprises the following steps: S1, cable saddle construction; s2, construction of a traction system; s3, guide rope construction; s4, bearing cable construction; s5, main cable construction; and S6, cable clamp sling construction. And S7, auxiliary construction. According to the scheme, the pilot cable, the transition cable and the traction cable are pulled in a reciprocating mode through the winches on the two banks of the river channel, finally the bearing cable is erected on the tops of the two banks through the traction cable, the main cable is rapidly installed on the tops of the two banks of the river channel through the bearing cable under the synchronous winding and unwinding effect of the winches on the two banks, and manual auxiliary tugboat and other equipment are not needed; and deep valleys and river channels can be quickly spanned, a large amount of engineering time is saved, meanwhile, control over the channel is not needed, and the equipment renting cost is also reduced.
本发明提供了一种人行悬索桥的施工方法,包括如下步骤:S1,索鞍施工;S2,牵引系统施工;S3,导索施工;S4,承重索施工;S5,主缆施工;S6,索夹吊索施工。S7,附属施工。本方案通过河道两岸的卷扬机往复的牵引先导索、过渡索、牵引索,最后通过牵引索的作用将承重索架设在两岸塔顶,且承重索在两岸卷扬机同步收放的作用下快速的将主缆安装在河道两岸的塔顶,不需要依靠人工辅助拖船等设备,可以快速跨越深谷及河道,节约了大量的工程时间,同时无需对航道进行管制,也降低了设备租用成本。
Construction method of pedestrian suspension bridge
一种人行悬索桥的施工方法
WEN ZHONGXING (author) / DIAO NAIHAO (author) / LIU GUICHUN (author) / HUANG GAOBIN (author) / ZHANG LIN (author) / GUO ZIHENG (author) / CAO HAIQING (author) / ZENG YINYONG (author)
2024-08-13
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
Suspension bridge for pedestrian and construction method thereof
European Patent Office | 2018
|European Patent Office | 2021
|Pedestrian suspension bridge reinforcing structure and construction process thereof
European Patent Office | 2021
|Austria's Longest Pedestrian Suspension Bridge
Online Contents | 1997
|Austria's Longest Pedestrian Suspension Bridge
British Library Online Contents | 1997
|