Shipborne lead hole construction process
The invention discloses a shipborne hole guiding construction technology, and relates to the field of shipborne hole guiding, the shipborne hole guiding construction technology comprises a 600t ship, an 800t ship and broken stones, the upper ends of the 600t ship and the 800t ship are provided with lifting structures, the upper ends of the lifting structures are provided with connecting frames, the connecting frames can also serve as moving channels and are formed by welding profile steel, and the connecting frames can also serve as percussion drill platforms. According to the shipborne hole guiding construction technology, the two ships are connected into a whole to form a shipborne construction platform, hole guiding operation can be directly conducted in a river without being affected by the trestle construction progress, meanwhile, under the condition that steel pipes need to be anchored under the complex construction conditions of bare rock strata, deep water, long flood periods and the like, the steel platform can be constructed synchronously with the trestle, and the construction efficiency is improved. And even the steel platform can be constructed in advance of the trestle, so that the steel platform construction is prevented from lagging behind the steel trestle, and the construction time is saved.
本发明公开了一种船载引孔施工工艺,涉及船载引孔领域,包括600t船、800t船和碎石,所述600t船和800t船的上端设置有升降结构,且升降结构的上端安装有连接架,所述连接架可兼作移动通道,采用型钢焊接而成,所述连接架可同时作为冲击钻平台使用。该船载引孔施工工艺,通过将两艘船连接成一个整体,形成一个船载施工平台,可以不受栈桥施工进度影响,直接在河中进行引孔作业,同时对于裸露岩层、深水、洪水期长等复杂施工条件下需要锚固钢管情况下,可以与栈桥同步施工钢平台,甚至可以提前于栈桥施工钢平台,避免了钢平台施工滞后于钢栈桥,节省了施工时间。
Shipborne lead hole construction process
The invention discloses a shipborne hole guiding construction technology, and relates to the field of shipborne hole guiding, the shipborne hole guiding construction technology comprises a 600t ship, an 800t ship and broken stones, the upper ends of the 600t ship and the 800t ship are provided with lifting structures, the upper ends of the lifting structures are provided with connecting frames, the connecting frames can also serve as moving channels and are formed by welding profile steel, and the connecting frames can also serve as percussion drill platforms. According to the shipborne hole guiding construction technology, the two ships are connected into a whole to form a shipborne construction platform, hole guiding operation can be directly conducted in a river without being affected by the trestle construction progress, meanwhile, under the condition that steel pipes need to be anchored under the complex construction conditions of bare rock strata, deep water, long flood periods and the like, the steel platform can be constructed synchronously with the trestle, and the construction efficiency is improved. And even the steel platform can be constructed in advance of the trestle, so that the steel platform construction is prevented from lagging behind the steel trestle, and the construction time is saved.
本发明公开了一种船载引孔施工工艺,涉及船载引孔领域,包括600t船、800t船和碎石,所述600t船和800t船的上端设置有升降结构,且升降结构的上端安装有连接架,所述连接架可兼作移动通道,采用型钢焊接而成,所述连接架可同时作为冲击钻平台使用。该船载引孔施工工艺,通过将两艘船连接成一个整体,形成一个船载施工平台,可以不受栈桥施工进度影响,直接在河中进行引孔作业,同时对于裸露岩层、深水、洪水期长等复杂施工条件下需要锚固钢管情况下,可以与栈桥同步施工钢平台,甚至可以提前于栈桥施工钢平台,避免了钢平台施工滞后于钢栈桥,节省了施工时间。
Shipborne lead hole construction process
一种船载引孔施工工艺
LUO YONG (author) / WANG JINGWEN (author) / QIN JIANYU (author) / LU QIAO (author) / LAI ZHENWEI (author) / ZHENG GANG (author) / LIU BAOHE (author) / MA LINGYUN (author)
2024-08-23
Patent
Electronic Resource
Chinese
World standards for shipborne barges
Elsevier | 1987
|Shipborne water-blooming cyanobacteria collecting device
European Patent Office | 2022
|Maintenance platform for shipborne electromechanical equipment
European Patent Office | 2022
|