Construction method of laminated slab and cast-in-place beam reinforcement cage joint, structural beam slab integrated with laminated slab and construction method of structural beam slab
The invention discloses a construction method of a joint of a laminated slab and a cast-in-place beam reinforcement cage, a structural beam slab integrated with the laminated slab and a construction method of the structural beam slab. The construction method of the joint of the laminated slab and the cast-in-place beam reinforcement cage comprises the steps that a full-cage beam reinforcement cage of a cast-in-place beam is divided into a half-cage beam reinforcement cage constructed in advance and a top main reinforcement constructed in the later period; a half-cage-beam reinforcement cage is bound, the half-cage-beam reinforcement cage comprises bottom main reinforcements, middle waist reinforcements and stirrups, the middle waist reinforcements are connected with the stirrups, and supporting reinforcements are connected between the middle waist reinforcements and the bottom main reinforcements; hoisting a semi-cage beam reinforcement cage; the laminated slab is hoisted, and horizontal reinforcing bars of the laminated slab extend into the semi-cage beam reinforcement cage and are located between the stirrups above the middle waist bars; and the top main reinforcements are connected into the stirrups of the half-cage-beam reinforcement cage in a penetrating mode, so that the bottom main reinforcements, the middle waist reinforcements, the top main reinforcements, the supporting reinforcements and the stirrups form a full-cage-beam reinforcement cage. The binding difficulty of the beam reinforcement cage of the cast-in-place beam is reduced, and the construction efficiency of the beam reinforcement cage is improved.
本发明公开一种叠合板与现浇梁钢筋笼节点的施工方法、集成有叠合板的结构梁板及其施工方法,该叠合板与现浇梁钢筋笼节点的施工方法包括将现浇梁的全笼梁钢筋笼划分为先期施工的半笼梁钢筋笼及后期施工的顶部主筋;绑扎半笼梁钢筋笼,其中半笼梁钢筋笼包括底部主筋、中部腰筋和箍筋,所述中部腰筋与箍筋连接,在中部腰筋与底部主筋之间连接有撑筋;吊装半笼梁钢筋笼;吊装叠合板,将叠合板的胡子筋伸入在半笼梁钢筋笼内且位于中部腰筋上方的箍筋之间;将顶部主筋穿入连接在半笼梁钢筋笼的各道箍筋内,使所述底部主筋、中部腰筋、顶部主筋、撑筋和箍筋形成全笼梁钢筋笼。本发明降低了现浇梁的梁钢筋笼的绑扎难度,提高了梁钢筋笼的施工效率。
Construction method of laminated slab and cast-in-place beam reinforcement cage joint, structural beam slab integrated with laminated slab and construction method of structural beam slab
The invention discloses a construction method of a joint of a laminated slab and a cast-in-place beam reinforcement cage, a structural beam slab integrated with the laminated slab and a construction method of the structural beam slab. The construction method of the joint of the laminated slab and the cast-in-place beam reinforcement cage comprises the steps that a full-cage beam reinforcement cage of a cast-in-place beam is divided into a half-cage beam reinforcement cage constructed in advance and a top main reinforcement constructed in the later period; a half-cage-beam reinforcement cage is bound, the half-cage-beam reinforcement cage comprises bottom main reinforcements, middle waist reinforcements and stirrups, the middle waist reinforcements are connected with the stirrups, and supporting reinforcements are connected between the middle waist reinforcements and the bottom main reinforcements; hoisting a semi-cage beam reinforcement cage; the laminated slab is hoisted, and horizontal reinforcing bars of the laminated slab extend into the semi-cage beam reinforcement cage and are located between the stirrups above the middle waist bars; and the top main reinforcements are connected into the stirrups of the half-cage-beam reinforcement cage in a penetrating mode, so that the bottom main reinforcements, the middle waist reinforcements, the top main reinforcements, the supporting reinforcements and the stirrups form a full-cage-beam reinforcement cage. The binding difficulty of the beam reinforcement cage of the cast-in-place beam is reduced, and the construction efficiency of the beam reinforcement cage is improved.
本发明公开一种叠合板与现浇梁钢筋笼节点的施工方法、集成有叠合板的结构梁板及其施工方法,该叠合板与现浇梁钢筋笼节点的施工方法包括将现浇梁的全笼梁钢筋笼划分为先期施工的半笼梁钢筋笼及后期施工的顶部主筋;绑扎半笼梁钢筋笼,其中半笼梁钢筋笼包括底部主筋、中部腰筋和箍筋,所述中部腰筋与箍筋连接,在中部腰筋与底部主筋之间连接有撑筋;吊装半笼梁钢筋笼;吊装叠合板,将叠合板的胡子筋伸入在半笼梁钢筋笼内且位于中部腰筋上方的箍筋之间;将顶部主筋穿入连接在半笼梁钢筋笼的各道箍筋内,使所述底部主筋、中部腰筋、顶部主筋、撑筋和箍筋形成全笼梁钢筋笼。本发明降低了现浇梁的梁钢筋笼的绑扎难度,提高了梁钢筋笼的施工效率。
Construction method of laminated slab and cast-in-place beam reinforcement cage joint, structural beam slab integrated with laminated slab and construction method of structural beam slab
一种叠合板与现浇梁钢筋笼节点的施工方法、集成有叠合板的结构梁板及其施工方法
TAO YUNHAI (author) / LIAN HAIHONG (author) / WU JUN (author) / ZHU LEIJIE (author) / MAO YUANHAO (author)
2024-09-03
Patent
Electronic Resource
Chinese
Cast-in-place beam and laminated slab installation construction method
European Patent Office | 2023
|Laminated slab, connecting structure of laminated slab and composite beam and construction method
European Patent Office | 2021
|Laminated slab structural beam structure and construction method thereof
European Patent Office | 2023
|Laminated slab composite beam slab structure and composite beam slab system
European Patent Office | 2024
|European Patent Office | 2024
|