Construction method of foundation pit slope pre-stressed anchor cable
The invention relates to a construction method of a foundation pit slope pre-stressed anchor cable, which belongs to the technical field of building construction, and comprises the following steps: S1, drilling: positioning a geological drilling machine on a first row of anchor cable operating platform by using a crane, adjusting and measuring the drilling position and the inclination angle of the drilling machine, fixing the drilling machine on the operating platform and a rock surface by using a fastener, and constructing from bottom to top, an upper layer of operation platform is erected in time along with the drilling progress; s2, anchor cable installation is conducted, specifically, a plurality of reinforced anchor cable structures are installed on the slope structure at equal intervals, a baffle is erected near each reinforced anchor cable structure, and the reinforced anchor cable structures are protected; hole bottom grouting construction is adopted for anchor cable grouting, mortar is injected from the hole bottom, air is exhausted from an exhaust hole, and a mortar position indicator is adopted for controlling the grouting position; and S4, anchor cable tensioning is conducted, specifically, anchor cable tensioning is conducted after grouting and anchor beam concrete reach 70% of the design strength, tensioning equipment is calibrated before anchor cable tensioning, and stress errors are avoided. The effect of improving the structural stability of the anchor cable is achieved.
本申请涉及一种基坑边坡预应力锚索的施工方法,属于建筑施工的技术领域,其包括以下步骤:S1、钻孔:利用吊车将地质钻机就位于第一排锚索操作平台,调整测量钻孔位置及钻机倾角,利用紧固件固定于操作平台及岩面上,自下而上施工,随钻孔的进度,及时架立上一层操作平台;S2、安装锚索:将多个加强型锚索结构等间距安装在边坡结构上,每个加强型锚索结构附近搭设挡板,对加强型锚索结构进行保护;S3、注浆:锚索注浆采用孔底注浆施工,砂浆由孔底注入,空气由排气孔排出,采用砂浆位置指示器控制注浆位置;S4、锚索的张拉:锚索张拉在注浆及锚梁砼达到设计强度70%后进行,张拉锚索前对张拉设备进标定,避免出现应力误差。本申请具有提高锚索结构稳定的效果。
Construction method of foundation pit slope pre-stressed anchor cable
The invention relates to a construction method of a foundation pit slope pre-stressed anchor cable, which belongs to the technical field of building construction, and comprises the following steps: S1, drilling: positioning a geological drilling machine on a first row of anchor cable operating platform by using a crane, adjusting and measuring the drilling position and the inclination angle of the drilling machine, fixing the drilling machine on the operating platform and a rock surface by using a fastener, and constructing from bottom to top, an upper layer of operation platform is erected in time along with the drilling progress; s2, anchor cable installation is conducted, specifically, a plurality of reinforced anchor cable structures are installed on the slope structure at equal intervals, a baffle is erected near each reinforced anchor cable structure, and the reinforced anchor cable structures are protected; hole bottom grouting construction is adopted for anchor cable grouting, mortar is injected from the hole bottom, air is exhausted from an exhaust hole, and a mortar position indicator is adopted for controlling the grouting position; and S4, anchor cable tensioning is conducted, specifically, anchor cable tensioning is conducted after grouting and anchor beam concrete reach 70% of the design strength, tensioning equipment is calibrated before anchor cable tensioning, and stress errors are avoided. The effect of improving the structural stability of the anchor cable is achieved.
本申请涉及一种基坑边坡预应力锚索的施工方法,属于建筑施工的技术领域,其包括以下步骤:S1、钻孔:利用吊车将地质钻机就位于第一排锚索操作平台,调整测量钻孔位置及钻机倾角,利用紧固件固定于操作平台及岩面上,自下而上施工,随钻孔的进度,及时架立上一层操作平台;S2、安装锚索:将多个加强型锚索结构等间距安装在边坡结构上,每个加强型锚索结构附近搭设挡板,对加强型锚索结构进行保护;S3、注浆:锚索注浆采用孔底注浆施工,砂浆由孔底注入,空气由排气孔排出,采用砂浆位置指示器控制注浆位置;S4、锚索的张拉:锚索张拉在注浆及锚梁砼达到设计强度70%后进行,张拉锚索前对张拉设备进标定,避免出现应力误差。本申请具有提高锚索结构稳定的效果。
Construction method of foundation pit slope pre-stressed anchor cable
一种基坑边坡预应力锚索的施工方法
LIU FEI (author) / XU RENHAO (author) / WANG DUOXUAN (author) / GAO QIAN (author) / ZHOU CHENGWEN (author) / YANG YAGUANG (author) / CHEN BIN (author) / QIN DUZHEN (author) / GONG SHAOWU (author) / MEI SHAN (author)
2024-09-13
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
European Patent Office | 2023
|Pre-stressed anchor cable device and installation construction method of pre-stressed anchor cable
European Patent Office | 2023
|Lattice beam pre-stressed anchor cable slope supporting structure
European Patent Office | 2022
|