Bulk grain horizontal warehouse construction method
The invention relates to a bulk grain horizontal warehouse construction method. The bulk grain horizontal warehouse construction method comprises the following steps that S1, lofting is conducted on the positions of square grid points; s2, leveling a construction ground panel; s3, a mounting base 11 is positioned; s4, the truss supporting platform is assembled in a bolt connection mode; s5, a rail is installed on the side of the roof formwork supporting platform, and a sliding hanging bracket platform car is installed on the rail; s6, the sliding hanging bracket platform car is limited on the track, a constructor goes on the hanging bracket and binds a first-section reinforcement cage, a formwork is erected through a formwork erecting assembly, and a first-section column and a wall start to be poured; s7, all the jacking oil cylinders are jacked; s8, a tower crane is used for disassembling the sliding hanging bracket platform car and the track; s9, a pitched roof bottom die is erected on the flat roof of the roof; and S10, descending of the roof formwork supporting platform is completed, dismounting is conducted, then the jacking oil cylinder and the base are dismounted, and the foundation bolts are cut off. The hanging bracket and the formwork supporting assembly which can move front and back and ascend and descend up and down can be installed, so that the construction efficiency is improved.
本发明涉及一种散装粮食平房仓施工方法,其包括如下步骤:S1:方形网格点的位置放样;S2:施工地面板找平;S3:定位安装底座11;S4:以螺栓连接方式拼装桁架支撑平台;S5:在屋盖模板支撑平台的边侧安装轨道,在轨道上安装滑动吊架平台车;S6:在轨道上对滑动吊架平台车限位,施工人员上吊架,绑扎首段钢筋笼,并使用支模组件支设模板,开始浇筑首段柱和墙;S7:所有的顶升油缸顶升;S8:用塔吊拆卸滑动吊架平台车和轨道;S9:在屋盖平屋面上支设坡屋面底模;S10:完成屋盖模板支撑平台的下降,进行拆卸,再拆卸顶升油缸和底座,并切断地脚螺栓。本发明能安装可前后移动和上下升降的吊架和支模组件,以提升施工效率。
Bulk grain horizontal warehouse construction method
The invention relates to a bulk grain horizontal warehouse construction method. The bulk grain horizontal warehouse construction method comprises the following steps that S1, lofting is conducted on the positions of square grid points; s2, leveling a construction ground panel; s3, a mounting base 11 is positioned; s4, the truss supporting platform is assembled in a bolt connection mode; s5, a rail is installed on the side of the roof formwork supporting platform, and a sliding hanging bracket platform car is installed on the rail; s6, the sliding hanging bracket platform car is limited on the track, a constructor goes on the hanging bracket and binds a first-section reinforcement cage, a formwork is erected through a formwork erecting assembly, and a first-section column and a wall start to be poured; s7, all the jacking oil cylinders are jacked; s8, a tower crane is used for disassembling the sliding hanging bracket platform car and the track; s9, a pitched roof bottom die is erected on the flat roof of the roof; and S10, descending of the roof formwork supporting platform is completed, dismounting is conducted, then the jacking oil cylinder and the base are dismounted, and the foundation bolts are cut off. The hanging bracket and the formwork supporting assembly which can move front and back and ascend and descend up and down can be installed, so that the construction efficiency is improved.
本发明涉及一种散装粮食平房仓施工方法,其包括如下步骤:S1:方形网格点的位置放样;S2:施工地面板找平;S3:定位安装底座11;S4:以螺栓连接方式拼装桁架支撑平台;S5:在屋盖模板支撑平台的边侧安装轨道,在轨道上安装滑动吊架平台车;S6:在轨道上对滑动吊架平台车限位,施工人员上吊架,绑扎首段钢筋笼,并使用支模组件支设模板,开始浇筑首段柱和墙;S7:所有的顶升油缸顶升;S8:用塔吊拆卸滑动吊架平台车和轨道;S9:在屋盖平屋面上支设坡屋面底模;S10:完成屋盖模板支撑平台的下降,进行拆卸,再拆卸顶升油缸和底座,并切断地脚螺栓。本发明能安装可前后移动和上下升降的吊架和支模组件,以提升施工效率。
Bulk grain horizontal warehouse construction method
一种散装粮食平房仓施工方法
PEI YANJUN (author) / JIN XIAOFEI (author) / FAN CHAO (author) / YAN HAN (author) / ZHU KUNCHENG (author) / ZHANG XIN (author) / ZHANG TAO (author) / WANG YUNLEI (author) / ZHANG WENXUE (author) / WANG GUISHENG (author)
2024-09-13
Patent
Electronic Resource
Chinese