Tower crane foundation and water-collecting well integrated construction method
The invention relates to the technical field of building construction, in particular to a tower crane foundation and water-collecting well integrated construction method, which comprises the following steps: before site construction, planning arrangement of a tower crane and construction of a tower crane foundation are firstly carried out to meet the hoisting of site materials and machines and tools; the tower crane foundation can replace foundation raft concrete, the secondary pouring amount is reduced, and cost reduction and efficiency improvement are facilitated; the selection of the position of the tower crane is more flexible, and when the tower crane foundation is constructed, part of the main body foundation is constructed in advance, so that the whole construction progress can be accelerated; through the integrated construction technology of the tower crane foundation and other areas, facility construction joints are reserved in reasonable positions, the construction progress of the tower crane foundation is guaranteed, meanwhile, the influence on later construction of other areas is reduced, and potential quality hazards of the construction joints are reduced.
本发明涉及建筑施工技术领域,具体是一种塔吊基础与集水井一体化施工方法,在现场施工前,先进行塔吊的策划布置,塔吊基础施工,以满足现场材料及机具的吊装;塔吊基础能够代替基础筏板混凝土,减少二次浇筑量,有利于降本增效;对塔吊位置的选择具有较大灵活性,在施工塔吊基础时,提前施工部分主体基础,有利于加快整体施工进度;通过将塔吊基础与其他区域一体化施工技术,在合理位置留设施工缝,保证塔吊基础的施工进度,同时也减少对后期其他区域施工的影响,减少施工缝的质量隐患。
Tower crane foundation and water-collecting well integrated construction method
The invention relates to the technical field of building construction, in particular to a tower crane foundation and water-collecting well integrated construction method, which comprises the following steps: before site construction, planning arrangement of a tower crane and construction of a tower crane foundation are firstly carried out to meet the hoisting of site materials and machines and tools; the tower crane foundation can replace foundation raft concrete, the secondary pouring amount is reduced, and cost reduction and efficiency improvement are facilitated; the selection of the position of the tower crane is more flexible, and when the tower crane foundation is constructed, part of the main body foundation is constructed in advance, so that the whole construction progress can be accelerated; through the integrated construction technology of the tower crane foundation and other areas, facility construction joints are reserved in reasonable positions, the construction progress of the tower crane foundation is guaranteed, meanwhile, the influence on later construction of other areas is reduced, and potential quality hazards of the construction joints are reduced.
本发明涉及建筑施工技术领域,具体是一种塔吊基础与集水井一体化施工方法,在现场施工前,先进行塔吊的策划布置,塔吊基础施工,以满足现场材料及机具的吊装;塔吊基础能够代替基础筏板混凝土,减少二次浇筑量,有利于降本增效;对塔吊位置的选择具有较大灵活性,在施工塔吊基础时,提前施工部分主体基础,有利于加快整体施工进度;通过将塔吊基础与其他区域一体化施工技术,在合理位置留设施工缝,保证塔吊基础的施工进度,同时也减少对后期其他区域施工的影响,减少施工缝的质量隐患。
Tower crane foundation and water-collecting well integrated construction method
一种塔吊基础与集水井一体化施工方法
TANG JIANHONG (author) / WEN YIZHU (author) / WANG CHENGLONG (author) / WANG GANG (author) / ZHANG JING (author)
2024-09-17
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Tower crane foundation for foundation pit and construction method of tower crane foundation