Suspended construction method for prefabricated sump of industrial factory building
The invention discloses a suspended construction method for a prefabricated sump of an industrial factory building. The suspended construction method comprises the steps that firstly, the prefabricated sump is prefabricated; 2, a steel structure frame of the industrial factory building is constructed, and the arrangement position of a suspended support is determined; thirdly, a suspended support is welded to the steel structure frame; fourthly, the prefabricated water collecting pit is hoisted; fifthly, the steel bar truss floor plate is hoisted, and the reserved lap joint steel bars of the prefabricated sump are fixedly connected with the surface layer steel bars of the steel bar truss floor plate; and sixthly, a concrete surface layer is poured on site, and the prefabricated water collecting pit and the steel bar truss floor plate are connected into a whole. The prefabricated water collecting pit is arranged on the steel structure frame of the industrial factory building in a suspended mode, so that the prefabricated water collecting pit is located below the cast-in-place concrete surface layer of the industrial factory building in a suspended state, and the influence of industrial wastewater on the soil texture and the surrounding environment can be reduced; and meanwhile, the problem that water collection and drainage are not smooth due to sedimentation of the prefabricated water collection pit can be solved.
本发明公开了一种工业厂房预制集水坑悬空施工方法,包括:一、预制集水坑的预制;二、施工工业厂房的钢结构框架,确定悬空支架的布设位置;三、在钢结构框架上焊接悬空支架;四、吊装预制集水坑;五、吊装钢筋桁架楼层板,并将预制集水坑的预留搭接钢筋与钢筋桁架楼层板的面层钢筋固定连接;六、现场浇筑混凝土面层,使预制集水坑与钢筋桁架楼层板连接为一体。本发明通过将预制集水坑悬空设置在工业厂房的钢结构框架上,使预制集水坑呈悬空状态位于工业厂房的现场浇筑混凝土面层的下方,能够减少工业废水对于土质与周边环境影响,同时能够解决由于预制集水坑的沉降而导致集水、排水不畅的问题。
Suspended construction method for prefabricated sump of industrial factory building
The invention discloses a suspended construction method for a prefabricated sump of an industrial factory building. The suspended construction method comprises the steps that firstly, the prefabricated sump is prefabricated; 2, a steel structure frame of the industrial factory building is constructed, and the arrangement position of a suspended support is determined; thirdly, a suspended support is welded to the steel structure frame; fourthly, the prefabricated water collecting pit is hoisted; fifthly, the steel bar truss floor plate is hoisted, and the reserved lap joint steel bars of the prefabricated sump are fixedly connected with the surface layer steel bars of the steel bar truss floor plate; and sixthly, a concrete surface layer is poured on site, and the prefabricated water collecting pit and the steel bar truss floor plate are connected into a whole. The prefabricated water collecting pit is arranged on the steel structure frame of the industrial factory building in a suspended mode, so that the prefabricated water collecting pit is located below the cast-in-place concrete surface layer of the industrial factory building in a suspended state, and the influence of industrial wastewater on the soil texture and the surrounding environment can be reduced; and meanwhile, the problem that water collection and drainage are not smooth due to sedimentation of the prefabricated water collection pit can be solved.
本发明公开了一种工业厂房预制集水坑悬空施工方法,包括:一、预制集水坑的预制;二、施工工业厂房的钢结构框架,确定悬空支架的布设位置;三、在钢结构框架上焊接悬空支架;四、吊装预制集水坑;五、吊装钢筋桁架楼层板,并将预制集水坑的预留搭接钢筋与钢筋桁架楼层板的面层钢筋固定连接;六、现场浇筑混凝土面层,使预制集水坑与钢筋桁架楼层板连接为一体。本发明通过将预制集水坑悬空设置在工业厂房的钢结构框架上,使预制集水坑呈悬空状态位于工业厂房的现场浇筑混凝土面层的下方,能够减少工业废水对于土质与周边环境影响,同时能够解决由于预制集水坑的沉降而导致集水、排水不畅的问题。
Suspended construction method for prefabricated sump of industrial factory building
一种工业厂房预制集水坑悬空施工方法
ZHANG QING (author) / WANG XIONGXIONG (author) / XIANG YANG (author) / WANG HUI (author) / LIANG WENBO (author)
2024-10-22
Patent
Electronic Resource
Chinese