Immersed tube anchor block construction method
The invention discloses a construction method of an immersed tube anchor block. The construction method comprises the following steps: driving a steel sheet pile: driving and arranging the steel sheet pile on the shore to support a foundation pit; foundation pit excavation, wherein anchor block foundation pits are excavated according to design; a broken stone hardcore layer is laid, wherein the broken stone hardcore layer is thrown and filled after the foundation pit is excavated; cofferdam construction is conducted, specifically, membrane bag sand cofferdam construction is conducted; water pumping in the cofferdam: pumping out accumulated water in the cofferdam; reinforcing steel bars are bound, wherein anchor block reinforcing steel bars are bound after the pipe joint is installed and is in butt joint with a shore pipeline; formwork installation, wherein a formwork for anchor block pouring is installed; concrete pouring: pouring a concrete anchor block by using a template support; after the anchor blocks reach the strength, the formworks are dismantled; and backfilling the foundation pit and removing the cofferdam. And the immersed tube anchor block construction can be quickly and efficiently completed.
本发明公开了一种沉管镇墩施工方法,包括钢板桩施打:在岸上施打布置钢板桩进行基坑支护;基坑开挖:按照设计开挖镇墩基坑;碎石垫层铺设:基坑开挖好后抛填碎石垫层;围堰施工:进行膜袋砂围堰施工;围堰内抽水:抽出围堰内的积水;钢筋绑扎:待管节安装完成并与岸上管线对接完后,进行镇墩钢筋绑扎;模板安装:安装镇墩浇筑用的模板;混凝土浇筑:利用模板支撑浇筑混凝土镇墩;模板拆除:镇墩达到强度后,拆除模板;基坑回填并拆除围堰。能够快速高效的完成沉管镇墩施工。
Immersed tube anchor block construction method
The invention discloses a construction method of an immersed tube anchor block. The construction method comprises the following steps: driving a steel sheet pile: driving and arranging the steel sheet pile on the shore to support a foundation pit; foundation pit excavation, wherein anchor block foundation pits are excavated according to design; a broken stone hardcore layer is laid, wherein the broken stone hardcore layer is thrown and filled after the foundation pit is excavated; cofferdam construction is conducted, specifically, membrane bag sand cofferdam construction is conducted; water pumping in the cofferdam: pumping out accumulated water in the cofferdam; reinforcing steel bars are bound, wherein anchor block reinforcing steel bars are bound after the pipe joint is installed and is in butt joint with a shore pipeline; formwork installation, wherein a formwork for anchor block pouring is installed; concrete pouring: pouring a concrete anchor block by using a template support; after the anchor blocks reach the strength, the formworks are dismantled; and backfilling the foundation pit and removing the cofferdam. And the immersed tube anchor block construction can be quickly and efficiently completed.
本发明公开了一种沉管镇墩施工方法,包括钢板桩施打:在岸上施打布置钢板桩进行基坑支护;基坑开挖:按照设计开挖镇墩基坑;碎石垫层铺设:基坑开挖好后抛填碎石垫层;围堰施工:进行膜袋砂围堰施工;围堰内抽水:抽出围堰内的积水;钢筋绑扎:待管节安装完成并与岸上管线对接完后,进行镇墩钢筋绑扎;模板安装:安装镇墩浇筑用的模板;混凝土浇筑:利用模板支撑浇筑混凝土镇墩;模板拆除:镇墩达到强度后,拆除模板;基坑回填并拆除围堰。能够快速高效的完成沉管镇墩施工。
Immersed tube anchor block construction method
一种沉管镇墩施工方法
ZHOU YUE (author) / WAN LIANG (author) / HU TIANXIANG (author) / YE CONG (author) / WU CHAO (author) / WU LEI (author) / TANG XIAOFENG (author) / ZHOU CHENGYAO (author)
2024-10-29
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Construction method of immersed tube joint in immersed tube tunnel and immersed tube joint structure
European Patent Office | 2021
|Combined immersed tube joint for immersed tube tunnel and construction method
European Patent Office | 2023
|Immersed tube and cast-in-place pile construction method of immersed tube
European Patent Office | 2024
|