Large-span plant steel structure construction method
The invention relates to the technical field of building engineering, and discloses a large-span plant steel structure construction method which comprises the following steps: S1, a constructor constructs a large-span plant steel structure three-dimensional model according to the overall arrangement of a roof truss; s2, dividing the whole steel roof into all partition boundary lines on the large-span plant three-dimensional model according to the distribution of inner side edge sealing trusses; s3, a constructor determines the construction sequence of the large-span plant steel structure according to the construction site and the construction environment; and S4, a constructor prepares a steel truss of each part according to the structure of the large-span plant three-dimensional model. Through hierarchical classification and information organization coding rules, systematicness and accuracy of the three-dimensional model are ensured, and high-precision measurement equipment is used for positioning; by dividing partition boundary lines and adopting a partition construction method, the efficiency is improved, and the construction period is shortened; the rapid installation and stability of the roof structure are ensured through high-altitude rod supplementing and crawler crane hoisting, and meanwhile the safety of high-altitude operation is improved through a temporary supporting system.
本发明涉及建筑工程技术领域,公开了一种大跨度厂房钢结构施工方法,包括以下步骤:S1、施工人员根据屋盖桁架整体布置构建大跨度厂房钢结构三维模型;S2、在所述大跨度厂房三维模型上将钢屋盖整体按内侧封边桁架的分布划分各分区界线;S3、施工人员根据施工场地、施工环境确定大跨度厂房钢结构的施工顺序;S4、施工人员根据所述大跨度厂房三维模型的结构制备每部分的钢桁架。通过层级分类和信息组织编码规则,确保了三维模型的系统性和精确度,并使用高精度测量设备进行定位;通过划分分区界线和采用分区施工法,提升效率并缩短工期;通过高空补杆和履带吊吊装,确保屋盖结构的快速安装和稳定性,同时使用临时支撑系统提高高空作业的安全性。
Large-span plant steel structure construction method
The invention relates to the technical field of building engineering, and discloses a large-span plant steel structure construction method which comprises the following steps: S1, a constructor constructs a large-span plant steel structure three-dimensional model according to the overall arrangement of a roof truss; s2, dividing the whole steel roof into all partition boundary lines on the large-span plant three-dimensional model according to the distribution of inner side edge sealing trusses; s3, a constructor determines the construction sequence of the large-span plant steel structure according to the construction site and the construction environment; and S4, a constructor prepares a steel truss of each part according to the structure of the large-span plant three-dimensional model. Through hierarchical classification and information organization coding rules, systematicness and accuracy of the three-dimensional model are ensured, and high-precision measurement equipment is used for positioning; by dividing partition boundary lines and adopting a partition construction method, the efficiency is improved, and the construction period is shortened; the rapid installation and stability of the roof structure are ensured through high-altitude rod supplementing and crawler crane hoisting, and meanwhile the safety of high-altitude operation is improved through a temporary supporting system.
本发明涉及建筑工程技术领域,公开了一种大跨度厂房钢结构施工方法,包括以下步骤:S1、施工人员根据屋盖桁架整体布置构建大跨度厂房钢结构三维模型;S2、在所述大跨度厂房三维模型上将钢屋盖整体按内侧封边桁架的分布划分各分区界线;S3、施工人员根据施工场地、施工环境确定大跨度厂房钢结构的施工顺序;S4、施工人员根据所述大跨度厂房三维模型的结构制备每部分的钢桁架。通过层级分类和信息组织编码规则,确保了三维模型的系统性和精确度,并使用高精度测量设备进行定位;通过划分分区界线和采用分区施工法,提升效率并缩短工期;通过高空补杆和履带吊吊装,确保屋盖结构的快速安装和稳定性,同时使用临时支撑系统提高高空作业的安全性。
Large-span plant steel structure construction method
一种大跨度厂房钢结构施工方法
WANG ZHIHONG (author) / LI ZAN (author) / SU HONG (author) / SUN ZE (author) / LIU MIN (author) / WU YIFENG (author) / MENG ZHI (author) / OUYANG XIAN (author) / PENG LONG (author) / KUANG QIANG (author)
2024-11-15
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
/
E04B
Allgemeine Baukonstruktionen
,
GENERAL BUILDING CONSTRUCTIONS
/
E04F
FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
,
Ausbau von Bauwerken, z.B. Treppen, Fußböden
/
E04H
Gebäude oder ähnliche Bauwerke für besondere Zwecke
,
BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES
/
G06F
ELECTRIC DIGITAL DATA PROCESSING
,
Elektrische digitale Datenverarbeitung
/
G06T
Bilddatenverarbeitung oder Bilddatenerzeugung allgemein
,
IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
Large-span cantilever steel structure construction method
European Patent Office | 2024
|Large-span steel structure cantilever construction method
European Patent Office | 2021
|