Special-shaped cable bent tower steel bar positioning and mounting method
The invention discloses a special-shaped cable bent tower steel bar positioning and mounting method which comprises the following steps: S1, confirming a cross section graph, namely completing modeling work of a special-shaped cable bent tower by utilizing three-dimensional modeling software, dividing special-shaped cable bent tower modeling according to construction sections, and sectioning every 2 m to obtain the cross section graph at the height; s2, designing and processing a framework; s3, framework installation; s4, binding reinforcing steel bars; s5, framework system conversion; s6, repeated installation is carried out; and S7, a formwork is installed, concrete is poured, and at the moment, pouring of the cable bent tower is completed. According to the positioning and mounting method, the construction efficiency is improved and the construction cost is reduced while accurate positioning of the special-shaped cable bent tower reinforcing steel bars can be guaranteed.
本发明公开了一种异形索塔钢筋定位安装方法,其包括以下步骤:S1、横断面图确认,利用三维建模软件完成异形索塔的建模工作,根据施工节段划分异形索塔建模,每2m进行一次剖切,得到该高度下的横断面图;S2、骨架设计加工;S3、骨架安装;S4、钢筋绑扎;S5、骨架体系转换;S6、重复安装;S7、模板安装,浇筑混凝土,此时索塔浇筑完成。本发明的定位安装方法在能保证异形索塔钢筋定位准确的同时,提高施工效率,降低施工成本。
Special-shaped cable bent tower steel bar positioning and mounting method
The invention discloses a special-shaped cable bent tower steel bar positioning and mounting method which comprises the following steps: S1, confirming a cross section graph, namely completing modeling work of a special-shaped cable bent tower by utilizing three-dimensional modeling software, dividing special-shaped cable bent tower modeling according to construction sections, and sectioning every 2 m to obtain the cross section graph at the height; s2, designing and processing a framework; s3, framework installation; s4, binding reinforcing steel bars; s5, framework system conversion; s6, repeated installation is carried out; and S7, a formwork is installed, concrete is poured, and at the moment, pouring of the cable bent tower is completed. According to the positioning and mounting method, the construction efficiency is improved and the construction cost is reduced while accurate positioning of the special-shaped cable bent tower reinforcing steel bars can be guaranteed.
本发明公开了一种异形索塔钢筋定位安装方法,其包括以下步骤:S1、横断面图确认,利用三维建模软件完成异形索塔的建模工作,根据施工节段划分异形索塔建模,每2m进行一次剖切,得到该高度下的横断面图;S2、骨架设计加工;S3、骨架安装;S4、钢筋绑扎;S5、骨架体系转换;S6、重复安装;S7、模板安装,浇筑混凝土,此时索塔浇筑完成。本发明的定位安装方法在能保证异形索塔钢筋定位准确的同时,提高施工效率,降低施工成本。
Special-shaped cable bent tower steel bar positioning and mounting method
一种异形索塔钢筋定位安装方法
WANG XIAOXIAO (author) / XU HAIYUN (author) / ZHU JINBO (author) / CHEN YONG (author) / XIAO XIONG (author) / LI WENHANG (author) / HUANG BO (author) / LI WEI (author) / LIU JICHAO (author) / LI WANYOU (author)
2024-11-29
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
Special-shaped cable bent tower decorative plate mounting device and construction method
European Patent Office | 2020
|Ultrahigh special-shaped cable bent tower construction technology
European Patent Office | 2023
|Construction method of curved-surface special-shaped cable bent tower
European Patent Office | 2023
|