Large-area rockfill area rotary digging hole-forming cast-in-place pile construction technology
The invention discloses a large-area rock-filled area rotary excavating hole-forming cast-in-place pile construction technology, and relates to the technical field of building construction, the large-area rock-filled area rotary excavating hole-forming cast-in-place pile construction technology comprises the following steps: 1, selecting a construction position in a rock-filled area; 2, a rotary drilling machine is adopted for hole forming operation; 3, after hole forming is completed, hole cleaning operation is conducted; 4, a cylindrical steel cylinder is placed in the formed hole, and the bottom end of the steel cylinder tightly presses the bottom wall of the formed hole; 5, water-stable mortar is poured into the space between the steel cylinder and the hole wall of the formed hole through high-pressure grouting equipment, and a hole wall reinforcing layer is formed; 6, after the hole wall reinforcing layer is formed, the steel cylinder is dismantled; 7, the bound reinforcement cage is put into the formed hole, and stirred concrete is poured into the hole to form a cast-in-place pile; and 8, after grouting is completed, concrete is subjected to curing operation. The structural strength and stability of the cast-in-place pile under the complex geological condition are ensured, and the construction quality is improved.
本申请公开了一种大面积填石区域旋挖成孔灌注桩施工工艺,涉及建筑施工的技术领域,其包括以下步骤:步骤1、在填石区域选定施工位置;步骤2、采用旋挖机进行成孔作业;步骤3、成孔完成后,进行清孔作业;步骤4、在成孔内放入柱形的钢筒,且使钢筒的底端压紧成孔的底壁;步骤5、采用高压注浆设备向钢筒与成孔孔壁之间的空间内灌注水稳砂浆,形成孔壁加固层;步骤6、待孔壁加固层成型后,将钢筒拆除;步骤7、将绑扎好的钢筋笼放入成孔内,并向孔内灌注搅拌好的混凝土,形成灌注桩;步骤8、灌浆完成后,对混凝土进行养护作业。本申请确保了灌注桩在复杂地质条件下的结构强度和稳定性,提高了施工质量。
Large-area rockfill area rotary digging hole-forming cast-in-place pile construction technology
The invention discloses a large-area rock-filled area rotary excavating hole-forming cast-in-place pile construction technology, and relates to the technical field of building construction, the large-area rock-filled area rotary excavating hole-forming cast-in-place pile construction technology comprises the following steps: 1, selecting a construction position in a rock-filled area; 2, a rotary drilling machine is adopted for hole forming operation; 3, after hole forming is completed, hole cleaning operation is conducted; 4, a cylindrical steel cylinder is placed in the formed hole, and the bottom end of the steel cylinder tightly presses the bottom wall of the formed hole; 5, water-stable mortar is poured into the space between the steel cylinder and the hole wall of the formed hole through high-pressure grouting equipment, and a hole wall reinforcing layer is formed; 6, after the hole wall reinforcing layer is formed, the steel cylinder is dismantled; 7, the bound reinforcement cage is put into the formed hole, and stirred concrete is poured into the hole to form a cast-in-place pile; and 8, after grouting is completed, concrete is subjected to curing operation. The structural strength and stability of the cast-in-place pile under the complex geological condition are ensured, and the construction quality is improved.
本申请公开了一种大面积填石区域旋挖成孔灌注桩施工工艺,涉及建筑施工的技术领域,其包括以下步骤:步骤1、在填石区域选定施工位置;步骤2、采用旋挖机进行成孔作业;步骤3、成孔完成后,进行清孔作业;步骤4、在成孔内放入柱形的钢筒,且使钢筒的底端压紧成孔的底壁;步骤5、采用高压注浆设备向钢筒与成孔孔壁之间的空间内灌注水稳砂浆,形成孔壁加固层;步骤6、待孔壁加固层成型后,将钢筒拆除;步骤7、将绑扎好的钢筋笼放入成孔内,并向孔内灌注搅拌好的混凝土,形成灌注桩;步骤8、灌浆完成后,对混凝土进行养护作业。本申请确保了灌注桩在复杂地质条件下的结构强度和稳定性,提高了施工质量。
Large-area rockfill area rotary digging hole-forming cast-in-place pile construction technology
一种大面积填石区域旋挖成孔灌注桩施工工艺
XIANG XUELIN (author) / HU CHI (author) / ZHOU KAI (author) / SHENG WENJING (author)
2024-12-06
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Construction method and system for rotary digging hole-forming cast-in-place pile
European Patent Office | 2023
|Rotary digging hole-forming cast-in-place pile construction structure and method thereof
European Patent Office | 2024
|Complex geological rotary digging hole-forming cast-in-place pile and construction method
European Patent Office | 2024
|Construction method for manual hole digging cast-in-place pile in karst area
European Patent Office | 2022
|Shaped protection device for rotary digging hole-forming cast-in-place pile hole opening
European Patent Office | 2022
|