Construction method for removing old bridge and newly building bridge without interrupting traffic
The invention discloses a construction method for removing an old bridge and newly building bridges without interrupting traffic. The construction method comprises the following steps that a first bridge and a second bridge are newly built on the two sides of an original old bridge correspondingly; two-way traffic on the old bridge is guided to the first bridge firstly, and then the old bridge is dismantled; bridge decks flush with the surface of the second bridge are installed on the two sides of the second bridge, so that bidirectional widening of the second bridge is completed; two-way traffic on the first bridge is guided to the widened second bridge, and the first bridge is closed; bridge decks flush with the surface of the first bridge are installed on the two sides of the first bridge, so that bidirectional widening of the first bridge is completed; and then the traffic flow in one direction is guided to the widened first bridge, and only the one-way traffic flow in the other direction is reserved on the second bridge. According to the method, the transformation mode of double-side bridge building and two-way widening is adopted, the defects of existing single-side widening and double-side widening are overcome, the defects existing after double-width bridges are widened are overcome, and the later maintenance cost is reduced.
本发明公开了一种不中断交通的旧桥拆除并新建桥梁的建造方法,包括以下步骤:在原有旧桥的两侧分别新建一座第一桥梁和第二桥梁;将旧桥上的双向交通均先引导至第一桥梁上,而后拆除旧桥;在第二桥梁的两侧安装与其表面平齐的桥面板,以完成第二桥梁的双向拓宽;将第一桥梁上的双向交通引导至拓宽后的第二桥梁上,封闭第一桥梁;在第一桥梁的两侧安装与其表面平齐的桥面板,以完成第一桥梁的双向拓宽;而后将其中一个方向的车流引导至拓宽后的第一桥梁上,第二桥梁上仅保留另一方向的单向车流。本发明方法采用双侧新建桥梁+双向拓宽的改造方式,避免现有单侧拓宽、双侧拓宽的弊端,并规避了双幅桥拼宽后存在的弊端,减少后期维修养护成本。
Construction method for removing old bridge and newly building bridge without interrupting traffic
The invention discloses a construction method for removing an old bridge and newly building bridges without interrupting traffic. The construction method comprises the following steps that a first bridge and a second bridge are newly built on the two sides of an original old bridge correspondingly; two-way traffic on the old bridge is guided to the first bridge firstly, and then the old bridge is dismantled; bridge decks flush with the surface of the second bridge are installed on the two sides of the second bridge, so that bidirectional widening of the second bridge is completed; two-way traffic on the first bridge is guided to the widened second bridge, and the first bridge is closed; bridge decks flush with the surface of the first bridge are installed on the two sides of the first bridge, so that bidirectional widening of the first bridge is completed; and then the traffic flow in one direction is guided to the widened first bridge, and only the one-way traffic flow in the other direction is reserved on the second bridge. According to the method, the transformation mode of double-side bridge building and two-way widening is adopted, the defects of existing single-side widening and double-side widening are overcome, the defects existing after double-width bridges are widened are overcome, and the later maintenance cost is reduced.
本发明公开了一种不中断交通的旧桥拆除并新建桥梁的建造方法,包括以下步骤:在原有旧桥的两侧分别新建一座第一桥梁和第二桥梁;将旧桥上的双向交通均先引导至第一桥梁上,而后拆除旧桥;在第二桥梁的两侧安装与其表面平齐的桥面板,以完成第二桥梁的双向拓宽;将第一桥梁上的双向交通引导至拓宽后的第二桥梁上,封闭第一桥梁;在第一桥梁的两侧安装与其表面平齐的桥面板,以完成第一桥梁的双向拓宽;而后将其中一个方向的车流引导至拓宽后的第一桥梁上,第二桥梁上仅保留另一方向的单向车流。本发明方法采用双侧新建桥梁+双向拓宽的改造方式,避免现有单侧拓宽、双侧拓宽的弊端,并规避了双幅桥拼宽后存在的弊端,减少后期维修养护成本。
Construction method for removing old bridge and newly building bridge without interrupting traffic
一种不中断交通的旧桥拆除并新建桥梁的建造方法
LIU JIE (author) / LI HONGBIN (author) / TONG KAIMIN (author) / DENG CAN (author) / DENG DELUN (author) / LI XINCHUN (author) / ZHU JUN (author)
2024-12-10
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
Arch bridge reinforcing structure without interrupting traffic and construction method thereof
European Patent Office | 2022
|Method for dismantling under-crossing railway frame bridge without interrupting traffic
European Patent Office | 2023
|European Patent Office | 2023
|European Patent Office | 2022
|Method for repairing hinge joint of hollow slab bridge without interrupting traffic
European Patent Office | 2021
|