A platform for research: civil engineering, architecture and urbanism
Rapid disassembly construction method for large-size high-formwork plate buckle frame
The invention relates to the technical field of supporting buildings, in particular to a large-size high-formwork-erecting plate buckling frame quick dismounting which comprises the following steps that S1, firstly, residual materials on a building are removed through a conveying hook or other tools, and it is ensured that no sundries exist in the building; s2, connecting pieces of the module supports and other structures are dismantled, and fixing devices between the module supports are dismantled; s3, transporting the module brackets out of the building one by one by using a transportation hook or other hoisting equipment; s4, after the module support is dismantled, a guide transportation device including a supporting column and a guide rail is dismantled; and S5, residues, such as bolts, nuts and gaskets, generated in the dismounting process are checked and cleaned, whether all dismounted parts are complete or not is checked, and if damage exists, recording and replacement are needed.
本申请涉及支撑建筑技术领域,尤其是一种大体积高支模盘扣架快速拆卸,包括以下步骤:S1、先使用运输钩或其他工具将建筑上的剩余材料移除,确保建筑内无杂物;S2、拆除模块支架与其他结构的连接件,并拆除模块支架之间的固定装置;S3、使用运输钩或其他吊装设备,将模块支架逐一运输出建筑;S4、模块支架拆除完成后,拆除包括支撑柱以及导轨在内的导运输装置;S5、检查并清理拆卸过程中产生的残留物,如螺栓、螺母、垫片等,检查所有拆卸下来的部件是否完整,如有损坏需进行记录并更换。
Rapid disassembly construction method for large-size high-formwork plate buckle frame
The invention relates to the technical field of supporting buildings, in particular to a large-size high-formwork-erecting plate buckling frame quick dismounting which comprises the following steps that S1, firstly, residual materials on a building are removed through a conveying hook or other tools, and it is ensured that no sundries exist in the building; s2, connecting pieces of the module supports and other structures are dismantled, and fixing devices between the module supports are dismantled; s3, transporting the module brackets out of the building one by one by using a transportation hook or other hoisting equipment; s4, after the module support is dismantled, a guide transportation device including a supporting column and a guide rail is dismantled; and S5, residues, such as bolts, nuts and gaskets, generated in the dismounting process are checked and cleaned, whether all dismounted parts are complete or not is checked, and if damage exists, recording and replacement are needed.
本申请涉及支撑建筑技术领域,尤其是一种大体积高支模盘扣架快速拆卸,包括以下步骤:S1、先使用运输钩或其他工具将建筑上的剩余材料移除,确保建筑内无杂物;S2、拆除模块支架与其他结构的连接件,并拆除模块支架之间的固定装置;S3、使用运输钩或其他吊装设备,将模块支架逐一运输出建筑;S4、模块支架拆除完成后,拆除包括支撑柱以及导轨在内的导运输装置;S5、检查并清理拆卸过程中产生的残留物,如螺栓、螺母、垫片等,检查所有拆卸下来的部件是否完整,如有损坏需进行记录并更换。
Rapid disassembly construction method for large-size high-formwork plate buckle frame
一种大体积高支模盘扣架快速拆卸施工方法
CHENG YI (author) / WU YUXIANG (author) / HUANG BINGNAN (author) / HUA ZHEN (author) / WANG BIN (author) / ZHOU JICHENG (author)
2024-12-10
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Construction method of cantilever structure high-formwork plate buckle frame body
European Patent Office | 2022
|Plate buckle frame beam bottom formwork structure and construction method
European Patent Office | 2021
|European Patent Office | 2022
|Formwork erecting method for plate buckle frame at overhanging position
European Patent Office | 2024
|