A platform for research: civil engineering, architecture and urbanism
Anti-crack construction method for ALC wallboard
The invention relates to the technical field of constructional engineering, in particular to an ALC wallboard anti-cracking construction method which comprises the following steps: step 1, surveying and setting out, determining the mounting position of an ALC wallboard according to a construction drawing and a field positioning axis, and snapping a line; step 2, arranging wallboards, namely arranging the wallboards from a door opening to two ends respectively when the door opening exists in the inner partition wall body; when the door opening does not exist in the inner partition wall body, the plates are arranged in sequence from one end of the wall body in the wall length direction; 3, wallboard installation is conducted, specifically, PVC hard rubber strips are additionally arranged on the tops of the ALC wallboards, and it is guaranteed that the wallboards abut against the upper structure beam slab; the wedge-shaped hard PVC cushion blocks are used at the bottoms of the wallboards and are not taken out after being installed, and cracks generated by sinking of the wallboards after triangular wooden wedges are taken out can be reduced; after the wallboards are installed and corrected, hammering or vibration is carried out on the side edges of the wallboards, and it is guaranteed that abutted seams of the wallboards are tight.
本发明涉及建筑工程技术领域,具体涉及一种ALC墙板抗裂施工方法,所述方法包括:步骤1、测量放线,根据施工图纸及现场定位轴线,确定ALC墙板安装位置并弹线;步骤2、墙板排设,当内隔墙体存在门洞时,从门洞开始分别向两端排板;当内隔墙体不存在门洞口时,从墙体一端开始沿墙长方向顺序排板;步骤3、墙板安装,在ALC墙板顶部增加PVC硬质胶条,保证墙板与上部结构梁板顶紧;墙板底部使用楔形硬质PVC垫块,安装后不取出,可减少三角木楔取出后墙板下沉产生的裂缝;各墙板安装校正后,在墙板侧边进行锤击或振动,确保墙板拼缝严密。
Anti-crack construction method for ALC wallboard
The invention relates to the technical field of constructional engineering, in particular to an ALC wallboard anti-cracking construction method which comprises the following steps: step 1, surveying and setting out, determining the mounting position of an ALC wallboard according to a construction drawing and a field positioning axis, and snapping a line; step 2, arranging wallboards, namely arranging the wallboards from a door opening to two ends respectively when the door opening exists in the inner partition wall body; when the door opening does not exist in the inner partition wall body, the plates are arranged in sequence from one end of the wall body in the wall length direction; 3, wallboard installation is conducted, specifically, PVC hard rubber strips are additionally arranged on the tops of the ALC wallboards, and it is guaranteed that the wallboards abut against the upper structure beam slab; the wedge-shaped hard PVC cushion blocks are used at the bottoms of the wallboards and are not taken out after being installed, and cracks generated by sinking of the wallboards after triangular wooden wedges are taken out can be reduced; after the wallboards are installed and corrected, hammering or vibration is carried out on the side edges of the wallboards, and it is guaranteed that abutted seams of the wallboards are tight.
本发明涉及建筑工程技术领域,具体涉及一种ALC墙板抗裂施工方法,所述方法包括:步骤1、测量放线,根据施工图纸及现场定位轴线,确定ALC墙板安装位置并弹线;步骤2、墙板排设,当内隔墙体存在门洞时,从门洞开始分别向两端排板;当内隔墙体不存在门洞口时,从墙体一端开始沿墙长方向顺序排板;步骤3、墙板安装,在ALC墙板顶部增加PVC硬质胶条,保证墙板与上部结构梁板顶紧;墙板底部使用楔形硬质PVC垫块,安装后不取出,可减少三角木楔取出后墙板下沉产生的裂缝;各墙板安装校正后,在墙板侧边进行锤击或振动,确保墙板拼缝严密。
Anti-crack construction method for ALC wallboard
一种ALC墙板抗裂施工方法
XU YAFEI (author) / ZHANG ZIYANG (author) / CHEN ZHIQIANG (author) / LIANG ZHIFENG (author) / XU DONG (author) / YIN HUOPING (author) / WANG HONGTAO (author) / LIAO QUANHONG (author) / LI QIANG (author)
2024-12-10
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Building ALC wallboard installation anti-crack structure and construction method thereof
European Patent Office | 2024
|Prefabricated wallboard, wallboard system and construction method of wallboard system
European Patent Office | 2022
|Anti-cracking ALC wallboard fixed installation construction method
European Patent Office | 2022
|