Bridge pile reinforcing and repairing method
The invention relates to a bridge pile reinforcing and repairing method, a bridge comprises a plurality of rows of bridge piles, and the method is completed through the following steps that firstly, temporary bearing piles are constructed; secondly, reinforcing piles are constructed, and the reinforcing piles and the bridge piles in the row where the to-be-repaired bridge piles are located are arranged at intervals; thirdly, a bearing platform is constructed, specifically, the to-be-repaired bridge piles are repaired till the height meets the requirement, then the reinforced concrete bearing platform is poured, and the reinforcing piles and the bridge piles in the row where the to-be-repaired bridge piles are located are poured together; and fourthly, the bridge deck slab section is reset, specifically, the temporary bearing pile upper section is driven by the lifting mechanism to descend so that the bridge deck slab section can be supported on the cover beam, and the temporary bearing pile upper section is dismantled. According to the bridge pile reinforcing method, repairing is convenient, passing on the bridge is not affected during repairing, and the problems that an existing bridge pile repairing method is inconvenient to repair, and passing of the bridge is affected are solved.
本发明涉及一种桥桩加固修复方法,桥包括若干排桥桩,通过以下步骤来完成,第一步、施工临时承托桩;第二步、施工加固桩,加固桩同待修复的桥桩所在排的桥桩间隔设置;第三步、施工承台:将待修复的桥桩进行修复到高度符合要求,然后浇筑钢筋混凝土承台将加固桩和待修复的桥桩所在排的桥桩浇筑在一起;第四步、桥面板段复位:通过升降机构驱动临时承托桩上段下降而使得桥面板段支撑在盖梁上,拆除临时承托桩上段。本发明旨在提供一种修复方便且修复时不影响桥上通行的桥桩加固方法,解决了现有的桥桩修复方法修复不便而且影响桥的通行问题。
Bridge pile reinforcing and repairing method
The invention relates to a bridge pile reinforcing and repairing method, a bridge comprises a plurality of rows of bridge piles, and the method is completed through the following steps that firstly, temporary bearing piles are constructed; secondly, reinforcing piles are constructed, and the reinforcing piles and the bridge piles in the row where the to-be-repaired bridge piles are located are arranged at intervals; thirdly, a bearing platform is constructed, specifically, the to-be-repaired bridge piles are repaired till the height meets the requirement, then the reinforced concrete bearing platform is poured, and the reinforcing piles and the bridge piles in the row where the to-be-repaired bridge piles are located are poured together; and fourthly, the bridge deck slab section is reset, specifically, the temporary bearing pile upper section is driven by the lifting mechanism to descend so that the bridge deck slab section can be supported on the cover beam, and the temporary bearing pile upper section is dismantled. According to the bridge pile reinforcing method, repairing is convenient, passing on the bridge is not affected during repairing, and the problems that an existing bridge pile repairing method is inconvenient to repair, and passing of the bridge is affected are solved.
本发明涉及一种桥桩加固修复方法,桥包括若干排桥桩,通过以下步骤来完成,第一步、施工临时承托桩;第二步、施工加固桩,加固桩同待修复的桥桩所在排的桥桩间隔设置;第三步、施工承台:将待修复的桥桩进行修复到高度符合要求,然后浇筑钢筋混凝土承台将加固桩和待修复的桥桩所在排的桥桩浇筑在一起;第四步、桥面板段复位:通过升降机构驱动临时承托桩上段下降而使得桥面板段支撑在盖梁上,拆除临时承托桩上段。本发明旨在提供一种修复方便且修复时不影响桥上通行的桥桩加固方法,解决了现有的桥桩修复方法修复不便而且影响桥的通行问题。
Bridge pile reinforcing and repairing method
一种桥桩加固修复方法
CHEN HAIBING (author) / YU FENG (author) / YANG JUN (author)
2024-12-17
Patent
Electronic Resource
Chinese
Bridge pier repairing and reinforcing construction method
European Patent Office | 2021
|Road bridge crack repairing and reinforcing structure and reinforcing method
European Patent Office | 2021
|European Patent Office | 2023
|Pile anchor wall reinforcing method for repairing mine overhaul road
European Patent Office | 2022
|