Reinforcing construction method of water-rich quicksand stratum deep-buried pipeline inspection well system
The invention discloses a reinforcement construction method of a water-rich quicksand stratum deep-buried pipeline inspection well system, which comprises the steps of S1, planning and positioning, S2, inspection well sectional type pouring, S3, connecting end head installation, S4, bottom plate foot-lock anchor rod installation, S5, bottom plate reinforcement anchor rod installation, S6, grouting drainage pipe installation, S7, bottom plate pouring, S8, crossing section pipeline installation, S9, jet grouting pile construction, S10, grouting drainage construction and the like. And therefore, the whole deep-buried pipeline inspection well reinforcement construction process of the water-rich quicksand stratum is completed. According to the reinforcement construction method for the water-rich quicksand stratum deep-buried pipeline inspection well system, operation is easy, construction is convenient, the shear strength of a deep-buried sewage pipeline and the sedimentation or floating resistance of an inspection well can be effectively improved, the damage risk of the deep-buried sewage pipeline is reduced, and safety and reliability are achieved.
本发明公开了一种富水流砂地层深埋管道检查井系统的加固施工方法,包括S1、规划定位,S2、检查井分段式浇筑,S3、连接端头安装,S4、底板锁脚锚杆安装,S5、底板加固锚杆安装,S6、注浆排水管安装,S7、底板浇筑,S8、穿越节管道安装,S9、旋喷桩施工,S10、注浆排水施工等步骤,从而完成整个富水流砂地层的深埋管道检查井加固施工过程。本发明一种富水流砂地层深埋管道检查井系统的加固施工方法,操作简单,施工方便,能够有效提高深埋污水管道的抗剪强度以及检查井的抵抗沉降或上浮的能力,降低深埋污水管道的损坏风险,安全可靠。
Reinforcing construction method of water-rich quicksand stratum deep-buried pipeline inspection well system
The invention discloses a reinforcement construction method of a water-rich quicksand stratum deep-buried pipeline inspection well system, which comprises the steps of S1, planning and positioning, S2, inspection well sectional type pouring, S3, connecting end head installation, S4, bottom plate foot-lock anchor rod installation, S5, bottom plate reinforcement anchor rod installation, S6, grouting drainage pipe installation, S7, bottom plate pouring, S8, crossing section pipeline installation, S9, jet grouting pile construction, S10, grouting drainage construction and the like. And therefore, the whole deep-buried pipeline inspection well reinforcement construction process of the water-rich quicksand stratum is completed. According to the reinforcement construction method for the water-rich quicksand stratum deep-buried pipeline inspection well system, operation is easy, construction is convenient, the shear strength of a deep-buried sewage pipeline and the sedimentation or floating resistance of an inspection well can be effectively improved, the damage risk of the deep-buried sewage pipeline is reduced, and safety and reliability are achieved.
本发明公开了一种富水流砂地层深埋管道检查井系统的加固施工方法,包括S1、规划定位,S2、检查井分段式浇筑,S3、连接端头安装,S4、底板锁脚锚杆安装,S5、底板加固锚杆安装,S6、注浆排水管安装,S7、底板浇筑,S8、穿越节管道安装,S9、旋喷桩施工,S10、注浆排水施工等步骤,从而完成整个富水流砂地层的深埋管道检查井加固施工过程。本发明一种富水流砂地层深埋管道检查井系统的加固施工方法,操作简单,施工方便,能够有效提高深埋污水管道的抗剪强度以及检查井的抵抗沉降或上浮的能力,降低深埋污水管道的损坏风险,安全可靠。
Reinforcing construction method of water-rich quicksand stratum deep-buried pipeline inspection well system
一种富水流砂地层深埋管道检查井系统的加固施工方法
SHI XIAOTAO (author) / LIU GUOZHU (author) / YE HONG (author) / WU XIAOLONG (author) / ZHAN SONG (author) / YAN KAICHENG (author) / ZHAO XIAOSHU (author)
2024-12-17
Patent
Electronic Resource
Chinese
European Patent Office | 2022
|Dewatering construction method applicable to tunnel in water-rich quicksand stratum
European Patent Office | 2015
|Water-rich quicksand stratum foundation trench tool type precipitation well device
European Patent Office | 2020
|Quicksand stratum pipe jacking and pulling construction method
European Patent Office | 2024
|