Sawtooth-shaped glass curtain wall steel keel unit type installation method
The invention provides a zigzag glass curtain wall steel keel unit type installation method. The method comprises the following specific steps that S1, design modeling is conducted; s2, performing factory digital laser cutting on the components; s3, keel units are welded, specifically, a welding platform support is manufactured according to the size of each unit plate, part unit profiles are cut through laser and put into the welding support to be welded and assembled, and after being welded, the keel units are transported to a material storage yard through a hoisting platform to be stacked in a unified mode; s4, hoisting a unit steel keel: transporting a keel unit to an operation floor by adopting a truck crane, carrying out pay-off control on the floor by adopting a vertical keel and an adapter measuring and mounting positioner, controlling the plate keel to assist in positioning through the positioner, controlling the mounting error of the zigzag curtain wall component, and welding in place at one time; and S5, digitally processing and installing the glass. By means of the method, high-precision construction of curtain wall projects with complex shapes is achieved, machining consumption is saved, the construction period is greatly shortened, and good economic and social benefits are achieved.
本发明提供一种锯齿形玻璃幕墙钢龙骨单元式安装方法,包括以下具体步骤:S1、设计建模;S2、构件工厂数字激光切割;S3、龙骨单元焊接:根据各单元板块的尺寸制作焊接平台支架,利用激光切割部件单元型材,将其放入焊接支架内进行焊接拼装,龙骨单元焊接完成后采用吊运平台运输至材料堆场统一堆放;S4、单元钢龙骨吊装:龙骨单元采用汽车吊运输到作业楼层,楼层采用竖向龙骨及转接件测量安装定位器进行放线控制,通过定位器控制板块龙骨辅助定位,控制锯齿状幕墙构件安装误差,并一次性焊接到位;S5、玻璃数字化加工及安装。该方法实现了复杂造型幕墙工程的高精度施工,既节省了加工耗费,又极大的缩短了施工工期,具有良好的经济社会效益。
Sawtooth-shaped glass curtain wall steel keel unit type installation method
The invention provides a zigzag glass curtain wall steel keel unit type installation method. The method comprises the following specific steps that S1, design modeling is conducted; s2, performing factory digital laser cutting on the components; s3, keel units are welded, specifically, a welding platform support is manufactured according to the size of each unit plate, part unit profiles are cut through laser and put into the welding support to be welded and assembled, and after being welded, the keel units are transported to a material storage yard through a hoisting platform to be stacked in a unified mode; s4, hoisting a unit steel keel: transporting a keel unit to an operation floor by adopting a truck crane, carrying out pay-off control on the floor by adopting a vertical keel and an adapter measuring and mounting positioner, controlling the plate keel to assist in positioning through the positioner, controlling the mounting error of the zigzag curtain wall component, and welding in place at one time; and S5, digitally processing and installing the glass. By means of the method, high-precision construction of curtain wall projects with complex shapes is achieved, machining consumption is saved, the construction period is greatly shortened, and good economic and social benefits are achieved.
本发明提供一种锯齿形玻璃幕墙钢龙骨单元式安装方法,包括以下具体步骤:S1、设计建模;S2、构件工厂数字激光切割;S3、龙骨单元焊接:根据各单元板块的尺寸制作焊接平台支架,利用激光切割部件单元型材,将其放入焊接支架内进行焊接拼装,龙骨单元焊接完成后采用吊运平台运输至材料堆场统一堆放;S4、单元钢龙骨吊装:龙骨单元采用汽车吊运输到作业楼层,楼层采用竖向龙骨及转接件测量安装定位器进行放线控制,通过定位器控制板块龙骨辅助定位,控制锯齿状幕墙构件安装误差,并一次性焊接到位;S5、玻璃数字化加工及安装。该方法实现了复杂造型幕墙工程的高精度施工,既节省了加工耗费,又极大的缩短了施工工期,具有良好的经济社会效益。
Sawtooth-shaped glass curtain wall steel keel unit type installation method
一种锯齿形玻璃幕墙钢龙骨单元式安装方法
REN YANG (author) / XU XIAOQIN (author) / WANG HUOHUA (author) / GUO YINGQI (author) / LUO QUN (author) / DU YU (author) / CAI CHAO (author) / LI CHAO (author) / YE SHENGXIN (author) / KE JINHUA (author)
2025-01-10
Patent
Electronic Resource
Chinese
Sawtooth-shaped unit aluminum plate curtain wall installation system
European Patent Office | 2022
|Construction method of glass curtain wall, double-T-shaped keel and glass curtain wall system
European Patent Office | 2024
|