DEMOLITION METHOD OF CONCRETE SLAB
PROBLEM TO BE SOLVED: To provide a demolition method of a concrete slab which can demolish the concrete slab without exerting an influence on a passenger who passes below.SOLUTION: In a demolition method of a concrete slab which demolishes the concrete slab by splitting it into blocks, an accommodation implement is attached to a lower face of a preceding demolishing part in a slab so as to cover the preceding demolishing part, an external force is imparted to the demolishing part, the preceding demolishing part is demolished, a temporary beam is arranged so as to straddle an opened space of the preceding demolishing part, the accommodation implement is attached to the lower face of an adjacent demolishing part so as to be supported by the temporary beam, and a lower face other than a demolition-scheduled range of the adjacent demolishing part adjoining the preceding demolishing part, an external force is imparted to the adjacent demolishing part from an upper face, and thus the concrete slab is demolished.SELECTED DRAWING: Figure 1
【課題】コンクリートスラブを、下を通る通行人に影響を与えることなく解体することができる方法を提供する。【解決手段】コンクリート製のスラブをブロックに分けて解体する、コンクリートスラブの解体方法であって、前記スラブ中の先行解体部の下面に該先行解体部を覆うように収容具を取り付け、前記先行解体部に上面から外力を与えて、該先行解体部を解体し、前記先行解体部の開放空間を跨ぐように仮設梁を設置し、前記仮設梁と、前記先行解体部に隣接する隣接解体部の解体予定範囲外の下面とで支持するように、前記収容具を前記隣接解体部の下面に取付け、前記隣接解体部に上面から外力を与えて解体することを特徴とする。【選択図】図1
DEMOLITION METHOD OF CONCRETE SLAB
PROBLEM TO BE SOLVED: To provide a demolition method of a concrete slab which can demolish the concrete slab without exerting an influence on a passenger who passes below.SOLUTION: In a demolition method of a concrete slab which demolishes the concrete slab by splitting it into blocks, an accommodation implement is attached to a lower face of a preceding demolishing part in a slab so as to cover the preceding demolishing part, an external force is imparted to the demolishing part, the preceding demolishing part is demolished, a temporary beam is arranged so as to straddle an opened space of the preceding demolishing part, the accommodation implement is attached to the lower face of an adjacent demolishing part so as to be supported by the temporary beam, and a lower face other than a demolition-scheduled range of the adjacent demolishing part adjoining the preceding demolishing part, an external force is imparted to the adjacent demolishing part from an upper face, and thus the concrete slab is demolished.SELECTED DRAWING: Figure 1
【課題】コンクリートスラブを、下を通る通行人に影響を与えることなく解体することができる方法を提供する。【解決手段】コンクリート製のスラブをブロックに分けて解体する、コンクリートスラブの解体方法であって、前記スラブ中の先行解体部の下面に該先行解体部を覆うように収容具を取り付け、前記先行解体部に上面から外力を与えて、該先行解体部を解体し、前記先行解体部の開放空間を跨ぐように仮設梁を設置し、前記仮設梁と、前記先行解体部に隣接する隣接解体部の解体予定範囲外の下面とで支持するように、前記収容具を前記隣接解体部の下面に取付け、前記隣接解体部に上面から外力を与えて解体することを特徴とする。【選択図】図1
DEMOLITION METHOD OF CONCRETE SLAB
コンクリートスラブの解体方法
YAMAZAKI HIDEYUKI (author) / KUSANO HIROMITSU (author) / ITO MASAHIRO (author) / HAMAKAWA KOJI (author)
2016-05-26
Patent
Electronic Resource
Japanese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
DEMOLITION SYSTEM AND DEMOLITION METHOD OF CONCRETE SLAB
European Patent Office | 2018
|DEMOLITION METHOD OF REINFORCEMENT CONCRETE AND DEMOLITION DEVICE THEREOF