DESIGN METHOD OF PRESTRESS CONCRETE GIRDER
PROBLEM TO BE SOLVED: To design a pretension system precast prestress concrete girder.SOLUTION: In a design method of RC-PC prestress concrete girder, a first anchorage length being the anchorage length of a tension material 2 when introducing tension force and a second anchorage length being the anchorage length of the tension material 2 in long-term load time or the anchorage length of the tension material 2 after an earthquake load acts, are set, and sticking splitting of the tension material 2 when introducing the tension force in the first anchorage length, is tested, and the second anchorage length is formed in a reinforced concrete structure of the tension force regarded as zero, and a beam central part 11 except for it is formed in a prestress concrete structure, and stress and deflection of the precast prestress concrete girder are tested.SELECTED DRAWING: Figure 1
【課題】プレテンション方式のプレキャスト製プレストレストコンクリート大梁を設計する。【解決手段】緊張力導入時の緊張材2の定着長さである第一定着長と、長期荷重時の緊張材2の定着長さまたは地震荷重作用後の緊張材2の定着長さである第二定着長とを設定し、第一定着長において緊張力導入時における緊張材2の付着割裂検定を行い、第二定着長を緊張力をゼロとみなす鉄筋コンクリート構造とするとともに、それ以外の梁中央部11をプレストレストコンクリート構造として、プレキャスト製プレストレストコンクリート大梁の応力・たわみ検定を行うことを特徴とする、RC−PCプレストレストコンクリート大梁の設計方法。【選択図】図1
DESIGN METHOD OF PRESTRESS CONCRETE GIRDER
PROBLEM TO BE SOLVED: To design a pretension system precast prestress concrete girder.SOLUTION: In a design method of RC-PC prestress concrete girder, a first anchorage length being the anchorage length of a tension material 2 when introducing tension force and a second anchorage length being the anchorage length of the tension material 2 in long-term load time or the anchorage length of the tension material 2 after an earthquake load acts, are set, and sticking splitting of the tension material 2 when introducing the tension force in the first anchorage length, is tested, and the second anchorage length is formed in a reinforced concrete structure of the tension force regarded as zero, and a beam central part 11 except for it is formed in a prestress concrete structure, and stress and deflection of the precast prestress concrete girder are tested.SELECTED DRAWING: Figure 1
【課題】プレテンション方式のプレキャスト製プレストレストコンクリート大梁を設計する。【解決手段】緊張力導入時の緊張材2の定着長さである第一定着長と、長期荷重時の緊張材2の定着長さまたは地震荷重作用後の緊張材2の定着長さである第二定着長とを設定し、第一定着長において緊張力導入時における緊張材2の付着割裂検定を行い、第二定着長を緊張力をゼロとみなす鉄筋コンクリート構造とするとともに、それ以外の梁中央部11をプレストレストコンクリート構造として、プレキャスト製プレストレストコンクリート大梁の応力・たわみ検定を行うことを特徴とする、RC−PCプレストレストコンクリート大梁の設計方法。【選択図】図1
DESIGN METHOD OF PRESTRESS CONCRETE GIRDER
プレストレストコンクリート大梁の設計方法
TAKEZAKI SHINICHI (author) / KOMURO TSUTOMU (author) / KAWAMOTO SHINICHIRO (author) / WATANABE YUICHI (author) / KORENAGA TAKEYOSHI (author)
2016-06-02
Patent
Electronic Resource
Japanese
PRESTRESSED CONCRETE GIRDER AND PRESTRESS INTRODUCTION METHOD
European Patent Office | 2020
|Prestress concrete box girder end sealing formwork construction method
European Patent Office | 2015
|Prestress introduction structure of truss girder and prestress introduction method
European Patent Office | 2019
|Construction method of bridge prestress continuous box girder
European Patent Office | 2020
|