SCAFFOLD FOR CHIMNEY DEMOLITION, AND CHIMNEY DEMOLITION METHOD
PROBLEM TO BE SOLVED: To provide a scaffold for chimney demolition, which enables inspection and the like to be simply performed during the chimney demolition, and a chimney demolition method.SOLUTION: A scaffold 1 for chimney demolition includes: a pair of masts 3 and 3 that are erected to face each other across a chimney 2; a work floor 4 that is circumferentially provided around the chimney 2; and a work floor 5 for inspection, which is arranged below the work floor 4. The work floor 4 is lifted/lowered by using the pair of masts 3 and 3 as guide rails. The work floor 5 for inspection is lifted/lowered independently of the work floor 4 by using mast 3 that is one of the pair of masts 3 and 3 as a guide rail.SELECTED DRAWING: Figure 1
【課題】煙突解体時の点検等を簡易に行うことが可能な煙突解体用足場および煙突解体工法を提案する。【解決手段】煙突2を挟んで対向するように立設された一対のマスト3,3と、煙突2に周設された作業床4と、作業床4の下方に配設された点検用作業床5とを備える煙突解体用足場1であって、作業床4は一対のマスト3,3をガイドレールとして昇降し、点検用作業床5は一対のマスト3,3のうちのいずれか一方のマスト3をガイドレールとして作業床4とは独立して昇降する。【選択図】図1
SCAFFOLD FOR CHIMNEY DEMOLITION, AND CHIMNEY DEMOLITION METHOD
PROBLEM TO BE SOLVED: To provide a scaffold for chimney demolition, which enables inspection and the like to be simply performed during the chimney demolition, and a chimney demolition method.SOLUTION: A scaffold 1 for chimney demolition includes: a pair of masts 3 and 3 that are erected to face each other across a chimney 2; a work floor 4 that is circumferentially provided around the chimney 2; and a work floor 5 for inspection, which is arranged below the work floor 4. The work floor 4 is lifted/lowered by using the pair of masts 3 and 3 as guide rails. The work floor 5 for inspection is lifted/lowered independently of the work floor 4 by using mast 3 that is one of the pair of masts 3 and 3 as a guide rail.SELECTED DRAWING: Figure 1
【課題】煙突解体時の点検等を簡易に行うことが可能な煙突解体用足場および煙突解体工法を提案する。【解決手段】煙突2を挟んで対向するように立設された一対のマスト3,3と、煙突2に周設された作業床4と、作業床4の下方に配設された点検用作業床5とを備える煙突解体用足場1であって、作業床4は一対のマスト3,3をガイドレールとして昇降し、点検用作業床5は一対のマスト3,3のうちのいずれか一方のマスト3をガイドレールとして作業床4とは独立して昇降する。【選択図】図1
SCAFFOLD FOR CHIMNEY DEMOLITION, AND CHIMNEY DEMOLITION METHOD
煙突解体用足場および煙突解体工法
MARUYAMA TAKASHI (author) / MIYAO MASAAKI (author) / MACHIDA ETSUKO (author) / HAGIWARA JUNICHI (author)
2017-02-09
Patent
Electronic Resource
Japanese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
SCAFFOLD FOR CHIMNEY FORMATION DEMOLITION AND CHIMNEY FORMATION DEMOLISHING METHOD
European Patent Office | 2022
|SCAFFOLD FOR CHIMNEY FORMATION DEMOLITION AND CHIMNEY FORMATION DEMOLISHING METHOD
European Patent Office | 2022
|