A platform for research: civil engineering, architecture and urbanism
MANHOLE INSTALLATION STRUCTURE AND MANHOLE INSTALLATION METHOD
PROBLEM TO BE SOLVED: To provide a manhole installation structure and a manhole installation method capable of making a backfilling layer between a manhole pipe side surface and the peripheral ground function as a water permeation passage over a long time.SOLUTION: In a manhole installation structure of arranging a manhole pipe 2 in a drilling hole, a backfilling layer 3 of using a coal ash molten slag by-produced by coal gasification compound power generation as a backfilling material, is formed between a manhole pipe 2-side surface and a wall surface of the drilling hole. The coal ash molten slag used as the backfilling material hardly causes the deterioration caused at compaction time and the lapse of time, and water permeability is maintained over a long time. In the manhole pipe 2, a drain hole 21 is formed in an upper position than an underground water level WL, and the backfilling layer 3 is formed in a height range for forming the drain hole 21 from at least the underground water level WL.SELECTED DRAWING: Figure 1
【課題】マンホール管側面と周辺地盤との間の埋め戻し層を長時間にわたって透水経路として機能させることができるマンホール設置構造及びマンホール設置工法を提供する。【解決手段】掘削孔にマンホール管2が配設されてなるマンホール設置構造であって、マンホール管2側面と前記掘削孔の壁面との間には、石炭ガス化複合発電で副産される石炭灰溶融スラグを埋め戻し材とする埋め戻し層3が形成されている。埋め戻し材として用いた石炭灰溶融スラグは、締固め時や時間経過にともなう劣化がほとんどなく、長時間にわたって透水性が維持される。マンホール管2には、地下水位WLより上方位置に水抜き孔21が形成されており、埋め戻し層3は、少なくとも地下水位WLから水抜き孔21が形成されている高さの範囲に形成されている。【選択図】図1
MANHOLE INSTALLATION STRUCTURE AND MANHOLE INSTALLATION METHOD
PROBLEM TO BE SOLVED: To provide a manhole installation structure and a manhole installation method capable of making a backfilling layer between a manhole pipe side surface and the peripheral ground function as a water permeation passage over a long time.SOLUTION: In a manhole installation structure of arranging a manhole pipe 2 in a drilling hole, a backfilling layer 3 of using a coal ash molten slag by-produced by coal gasification compound power generation as a backfilling material, is formed between a manhole pipe 2-side surface and a wall surface of the drilling hole. The coal ash molten slag used as the backfilling material hardly causes the deterioration caused at compaction time and the lapse of time, and water permeability is maintained over a long time. In the manhole pipe 2, a drain hole 21 is formed in an upper position than an underground water level WL, and the backfilling layer 3 is formed in a height range for forming the drain hole 21 from at least the underground water level WL.SELECTED DRAWING: Figure 1
【課題】マンホール管側面と周辺地盤との間の埋め戻し層を長時間にわたって透水経路として機能させることができるマンホール設置構造及びマンホール設置工法を提供する。【解決手段】掘削孔にマンホール管2が配設されてなるマンホール設置構造であって、マンホール管2側面と前記掘削孔の壁面との間には、石炭ガス化複合発電で副産される石炭灰溶融スラグを埋め戻し材とする埋め戻し層3が形成されている。埋め戻し材として用いた石炭灰溶融スラグは、締固め時や時間経過にともなう劣化がほとんどなく、長時間にわたって透水性が維持される。マンホール管2には、地下水位WLより上方位置に水抜き孔21が形成されており、埋め戻し層3は、少なくとも地下水位WLから水抜き孔21が形成されている高さの範囲に形成されている。【選択図】図1
MANHOLE INSTALLATION STRUCTURE AND MANHOLE INSTALLATION METHOD
マンホール設置構造及びマンホール設置工法
MATSUMOTO SHIN (author) / SHIGIYA TAKASHI (author) / TAKAHASHI SHINICHI (author)
2017-08-03
Patent
Electronic Resource
Japanese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Manhole inner cover and manhole cover installation structure using the same
European Patent Office | 2021
|