SUSPENSION DEVICE FOR STEEL PIPES, SUSPENSION METHOD OF STEEL PIPES WHEN INSTALLING STEEL PIPES, AND INSTALLATION METHOD OF STEEL PIPES
PROBLEM TO BE SOLVED: To provide a method for preventing a steel pipe pile from hindering movement of a drilling bit while being installed, in installation work for steel pipes using a drilling press-in device that performs drilling and pressing-in of steel pipes simultaneously.SOLUTION: A method is used when installing a steel pipe pile 71 using a drilling press-in device 8 that performs drilling and pressing-in of steel pipes simultaneously. Using a suspension device 1 for steel pipes, either of the steel pipe pile 71 or the drilling press-in device 8 is connected to the other, and the drilling press-in device 8 performs drilling while pressing in the steel pipe pile 71, such that the steel pipe pile 71 installed does not hinder movement of a drilling bit 85 of the drilling press-in device 8. The configuration protects the steel pipe pile 71 so as not to fall by more than a certain length. A bottom end of the steel pipe pile 71 does not reach a top end of the drilling bit 85, no matter how far the steel pipe pile falls. Furthermore, striking press-in force of a down-the-hole hammer 83 and the like is applied on the steel pipe pile 71 for certain.SELECTED DRAWING: Figure 1
【課題】掘削と鋼管類の圧入を同時に行う掘削圧入装置を用いた鋼管類の打設工事において、打設途中の鋼管杭が掘削ビットの動きを妨げることを防止する方法を提供する。【解決手段】掘削と鋼管類の圧入を同時に行う掘削圧入装置8を用いて鋼管杭71を打設する際に利用する方法であって、打設する鋼管杭71によって掘削圧入装置8の掘削ビット85の動きを妨げることがないように、鋼管類吊り下げ装置1によって、鋼管杭71および掘削圧入装置8の一方を他方に連結し、該掘削圧入装置8で掘削するとともに鋼管杭71を圧入する。このような特徴により、一定の長さ以上は鋼管杭71が降下しないように防護される。また、鋼管杭71がどんなに降下しても、その下端は掘削ビット85上端には届かないようになる。しかも、ダウンザホールハンマ83などによる打撃圧入力を、鋼管杭71に対して確実に印加することができる。【選択図】図1
SUSPENSION DEVICE FOR STEEL PIPES, SUSPENSION METHOD OF STEEL PIPES WHEN INSTALLING STEEL PIPES, AND INSTALLATION METHOD OF STEEL PIPES
PROBLEM TO BE SOLVED: To provide a method for preventing a steel pipe pile from hindering movement of a drilling bit while being installed, in installation work for steel pipes using a drilling press-in device that performs drilling and pressing-in of steel pipes simultaneously.SOLUTION: A method is used when installing a steel pipe pile 71 using a drilling press-in device 8 that performs drilling and pressing-in of steel pipes simultaneously. Using a suspension device 1 for steel pipes, either of the steel pipe pile 71 or the drilling press-in device 8 is connected to the other, and the drilling press-in device 8 performs drilling while pressing in the steel pipe pile 71, such that the steel pipe pile 71 installed does not hinder movement of a drilling bit 85 of the drilling press-in device 8. The configuration protects the steel pipe pile 71 so as not to fall by more than a certain length. A bottom end of the steel pipe pile 71 does not reach a top end of the drilling bit 85, no matter how far the steel pipe pile falls. Furthermore, striking press-in force of a down-the-hole hammer 83 and the like is applied on the steel pipe pile 71 for certain.SELECTED DRAWING: Figure 1
【課題】掘削と鋼管類の圧入を同時に行う掘削圧入装置を用いた鋼管類の打設工事において、打設途中の鋼管杭が掘削ビットの動きを妨げることを防止する方法を提供する。【解決手段】掘削と鋼管類の圧入を同時に行う掘削圧入装置8を用いて鋼管杭71を打設する際に利用する方法であって、打設する鋼管杭71によって掘削圧入装置8の掘削ビット85の動きを妨げることがないように、鋼管類吊り下げ装置1によって、鋼管杭71および掘削圧入装置8の一方を他方に連結し、該掘削圧入装置8で掘削するとともに鋼管杭71を圧入する。このような特徴により、一定の長さ以上は鋼管杭71が降下しないように防護される。また、鋼管杭71がどんなに降下しても、その下端は掘削ビット85上端には届かないようになる。しかも、ダウンザホールハンマ83などによる打撃圧入力を、鋼管杭71に対して確実に印加することができる。【選択図】図1
SUSPENSION DEVICE FOR STEEL PIPES, SUSPENSION METHOD OF STEEL PIPES WHEN INSTALLING STEEL PIPES, AND INSTALLATION METHOD OF STEEL PIPES
鋼管類吊り下げ装置、鋼管類打設時における鋼管類の吊設方法、鋼管類の打設方法