CONSTRUCTION METHOD FOR LOWERING GROUNDWATER LEVEL
PROBLEM TO BE SOLVED: To appropriately and efficiently manage a groundwater level by clarifying two-dimensional groundwater distribution and optimally controlling a lift pump.SOLUTION: A construction method for lowering a groundwater level, includes the following steps for: determining a pumping pattern that combines on/off of a lift pump of each pumping well (S1); deriving a parameter set for a pumped water amount at each pumping well by convergence calculation (a simplex method), and calculating current groundwater distribution at each pumping well (S2); calculating estimated groundwater distribution that applies the pumping pattern that has been determined, using a water pumping sensitivity value derived in a pumping test at each pumping well (S3); calculating a total value of an evaluation point that represents a value obtained by subtracting the calculated estimated groundwater distribution from the calculated current groundwater distribution (S4); and controlling the pumped water amount at each pumping well by applying the pumping pattern that maximizes the total value of the calculated evaluation points (S5).SELECTED DRAWING: Figure 1
【課題】 地下水位分布を面的に把握することにより最適な揚水ポンプの制御を実施して、適切かつ効率的に地下水位を管理する。【解決手段】 各揚水井戸における揚水ポンプのオン・オフの組み合わせによる揚水パターンを決定する工程(S1)と、収束計算(シンプレックス法)により各揚水井戸における揚水量のパラメータセットを求めて、各揚水井戸における現状の地下水位分布を算定する工程(S2)と、各揚水井戸における揚水試験から求めた揚水感度値を用いて、決定した各揚水パターンを適用した予測地下水位分布を算定する工程(S3)と、算定した現状の地下水位分布から算定した予測地下水位分布を減算した値を評価ポイントとして、当該評価ポイントの合計値を算定する工程(S4)と、算定した評価ポイントの合計値が最大となる揚水パターンを適用して、各揚水井戸の揚水量を制御する工程(S5)とを含む。【選択図】図1
CONSTRUCTION METHOD FOR LOWERING GROUNDWATER LEVEL
PROBLEM TO BE SOLVED: To appropriately and efficiently manage a groundwater level by clarifying two-dimensional groundwater distribution and optimally controlling a lift pump.SOLUTION: A construction method for lowering a groundwater level, includes the following steps for: determining a pumping pattern that combines on/off of a lift pump of each pumping well (S1); deriving a parameter set for a pumped water amount at each pumping well by convergence calculation (a simplex method), and calculating current groundwater distribution at each pumping well (S2); calculating estimated groundwater distribution that applies the pumping pattern that has been determined, using a water pumping sensitivity value derived in a pumping test at each pumping well (S3); calculating a total value of an evaluation point that represents a value obtained by subtracting the calculated estimated groundwater distribution from the calculated current groundwater distribution (S4); and controlling the pumped water amount at each pumping well by applying the pumping pattern that maximizes the total value of the calculated evaluation points (S5).SELECTED DRAWING: Figure 1
【課題】 地下水位分布を面的に把握することにより最適な揚水ポンプの制御を実施して、適切かつ効率的に地下水位を管理する。【解決手段】 各揚水井戸における揚水ポンプのオン・オフの組み合わせによる揚水パターンを決定する工程(S1)と、収束計算(シンプレックス法)により各揚水井戸における揚水量のパラメータセットを求めて、各揚水井戸における現状の地下水位分布を算定する工程(S2)と、各揚水井戸における揚水試験から求めた揚水感度値を用いて、決定した各揚水パターンを適用した予測地下水位分布を算定する工程(S3)と、算定した現状の地下水位分布から算定した予測地下水位分布を減算した値を評価ポイントとして、当該評価ポイントの合計値を算定する工程(S4)と、算定した評価ポイントの合計値が最大となる揚水パターンを適用して、各揚水井戸の揚水量を制御する工程(S5)とを含む。【選択図】図1
CONSTRUCTION METHOD FOR LOWERING GROUNDWATER LEVEL
地下水位低下工法
HAYASHI MIKIAKI (author) / NAKAI MIKIO (author) / OKADA NAOHITO (author) / SAKAFUJI YUTA (author)
2017-12-28
Patent
Electronic Resource
Japanese
IPC:
E02D
FOUNDATIONS
,
Gründungen
European Patent Office | 2023
|European Patent Office | 2023
|Groundwater lowering in construction : a practical guide
TIBKAT | 2001
|Lowering the groundwater level in construction of flaesheim locks of wesel-datteln ship canal
Engineering Index Backfile | 1929
|