CONSTRUCTION METHOD FOR TEMPORARY WATER-PROOFING
To provide a construction method for temporary water-proofing that is superior in workability such that a fireproof coating of an eaves beam is not wetted with rail during construction and it does not need labor to install and take away a temporary waterproof sheet.SOLUTION: The present invention relates to a construction method for temporary water-proofing which is implemented when an eaves beam 4 of a flat roof 1 is coated for fire-proofing. Then the construction method comprises the processes of: hanging a lower edge 3a of a roofing material 3 laid on a roof board 2 of the flat roof down to an upper edge 5a of an outer wall body part 5 arranged up so a position adjoining a lower surface of the eaves beam; coating the eaves beam for fire-proofing; turning up the lower edge of the roofing material onto the roof board to connect an outer wall upper end part covering a side of the eaves beam to the outer wall body part; and cutting a hanging part 31 of the roofing material.SELECTED DRAWING: Figure 1
【課題】施工中に軒梁の耐火被覆を雨で濡らすことがないうえに、仮防水シートの設置と撤去の手間をかける必要がない施工性に優れた仮防水処理を施す施工方法を提供する。【解決手段】陸屋根1の軒梁4に耐火被覆を行う際に行われる仮防水処理を施す施工方法である。そして、陸屋根の野地板2に敷設するルーフィング材3の下縁3aを、軒梁の下面に隣接する位置まで配置された外壁本体部5の上縁5aまで垂らす工程と、軒梁に耐火被覆を行う工程と、ルーフィング材の下縁を野地板上まで捲り上げて、外壁本体部に対して軒梁の側方を覆う外壁上端部を接続する工程と、ルーフィング材の垂下部31をカットする工程とを備えている。【選択図】図1
CONSTRUCTION METHOD FOR TEMPORARY WATER-PROOFING
To provide a construction method for temporary water-proofing that is superior in workability such that a fireproof coating of an eaves beam is not wetted with rail during construction and it does not need labor to install and take away a temporary waterproof sheet.SOLUTION: The present invention relates to a construction method for temporary water-proofing which is implemented when an eaves beam 4 of a flat roof 1 is coated for fire-proofing. Then the construction method comprises the processes of: hanging a lower edge 3a of a roofing material 3 laid on a roof board 2 of the flat roof down to an upper edge 5a of an outer wall body part 5 arranged up so a position adjoining a lower surface of the eaves beam; coating the eaves beam for fire-proofing; turning up the lower edge of the roofing material onto the roof board to connect an outer wall upper end part covering a side of the eaves beam to the outer wall body part; and cutting a hanging part 31 of the roofing material.SELECTED DRAWING: Figure 1
【課題】施工中に軒梁の耐火被覆を雨で濡らすことがないうえに、仮防水シートの設置と撤去の手間をかける必要がない施工性に優れた仮防水処理を施す施工方法を提供する。【解決手段】陸屋根1の軒梁4に耐火被覆を行う際に行われる仮防水処理を施す施工方法である。そして、陸屋根の野地板2に敷設するルーフィング材3の下縁3aを、軒梁の下面に隣接する位置まで配置された外壁本体部5の上縁5aまで垂らす工程と、軒梁に耐火被覆を行う工程と、ルーフィング材の下縁を野地板上まで捲り上げて、外壁本体部に対して軒梁の側方を覆う外壁上端部を接続する工程と、ルーフィング材の垂下部31をカットする工程とを備えている。【選択図】図1
CONSTRUCTION METHOD FOR TEMPORARY WATER-PROOFING
仮防水処理を施す施工方法
TSUE NAOMI (author)
2020-08-31
Patent
Electronic Resource
Japanese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
CONSTRUCTION METHOD OF STRUCTURE FOR WATER PROOFING AND ROOT PROOFING