A platform for research: civil engineering, architecture and urbanism
PRECAST FLOOR SLAB JOINT STRUCTURE AND PRECAST FLOOR SLAB
To propose a precast floor slab joint structure and a precast floor slab used for the same to reduce labor and cost during construction.SOLUTION: A precast floor slab joint structure 1 joins precast floor slabs 3 by filling a gap 11 between the precast floor slabs 3 arranged side by side with a filler 4. A step is formed at the end of the precast floor slab 3 in which the end surface of a lower stage (lower end surface 54) protrudes from the end surface of an upper stage (upper end surface 53). An upper reinforcement bar protrudes from the upper end surface 53 and a lower reinforcement bar protrudes from the lower end surface 54. The gap 11 between the lower end surfaces 54 of the precast floor slabs 3 is set to a size that can secure the fixing length of the lower reinforcement bar.SELECTED DRAWING: Figure 1
【課題】施工時の手間および費用の低減化を図るプレキャスト床版継手構造およびこれに使用するプレキャスト床版を提案する。【解決手段】並設されたプレキャスト床版3同士の隙間11に充填材4を充填することによりプレキャスト床版3同士を接合するプレキャスト床版継手構造1であって、プレキャスト床版3の端部には、上段部の端面(上段部端面53)よりも下段部の端面(下段部端面54)が突出する段差が形成されており、上段部端面53からは、上段鉄筋が突出しているとともに、下段部端面54からは下段鉄筋が突出していて、プレキャスト床版3の下段部端面54同士の隙間11は、下段鉄筋の定着長が確保できる大きさに設定されている。【選択図】図1
PRECAST FLOOR SLAB JOINT STRUCTURE AND PRECAST FLOOR SLAB
To propose a precast floor slab joint structure and a precast floor slab used for the same to reduce labor and cost during construction.SOLUTION: A precast floor slab joint structure 1 joins precast floor slabs 3 by filling a gap 11 between the precast floor slabs 3 arranged side by side with a filler 4. A step is formed at the end of the precast floor slab 3 in which the end surface of a lower stage (lower end surface 54) protrudes from the end surface of an upper stage (upper end surface 53). An upper reinforcement bar protrudes from the upper end surface 53 and a lower reinforcement bar protrudes from the lower end surface 54. The gap 11 between the lower end surfaces 54 of the precast floor slabs 3 is set to a size that can secure the fixing length of the lower reinforcement bar.SELECTED DRAWING: Figure 1
【課題】施工時の手間および費用の低減化を図るプレキャスト床版継手構造およびこれに使用するプレキャスト床版を提案する。【解決手段】並設されたプレキャスト床版3同士の隙間11に充填材4を充填することによりプレキャスト床版3同士を接合するプレキャスト床版継手構造1であって、プレキャスト床版3の端部には、上段部の端面(上段部端面53)よりも下段部の端面(下段部端面54)が突出する段差が形成されており、上段部端面53からは、上段鉄筋が突出しているとともに、下段部端面54からは下段鉄筋が突出していて、プレキャスト床版3の下段部端面54同士の隙間11は、下段鉄筋の定着長が確保できる大きさに設定されている。【選択図】図1
PRECAST FLOOR SLAB JOINT STRUCTURE AND PRECAST FLOOR SLAB
プレキャスト床版継手構造およびプレキャスト床版
TAKAHASHI AKIHIKO (author)
2021-08-02
Patent
Electronic Resource
Japanese
IPC:
E01D
BRIDGES
,
Brücken
PRECAST FLOOR SLAB JOINT STRUCTURE AND METHOD FOR JOINING PRECAST FLOOR SLAB JOINT
European Patent Office | 2024
|