METHOD FOR CONSTRUCTING OIL RETAINING WALL AND OIL RETAINING WALL STRUCTURE
To provide a construction method of an oil retaining wall 1 of reinforced concrete construction provided to surround an oil storage tank 100 and having a straight line part and a corner part in plan view.SOLUTION: Precast concrete pieces (PCa pieces) 10 having inverted T-shaped or L-shaped cross-sections are arranged at intervals, and a cast-in-place concrete 50 is placed between the PCa pieces 10, 10. Here, between the PCa pieces 10, 10 of straight parts, a construction joint part SM is formed in which lateral reinforcing bars protruding from end surfaces of the PCa pieces 10, 10 on both sides are connected by a lap joint by placing the cast-in-place concrete 50. A cast-in-place concrete 50 is placed between a PCa piece 10K of a corner part and the PCa piece 10 of the straight part in a state that the lateral reinforcing bars does not project from the end face of the PCa piece 10K of the corner part, and forms a structural joint part KM not connected by the lateral reinforcing bars.SELECTED DRAWING: Figure 1
【課題】 貯油タンク100を囲むように設けられ、平面視で直線部と角部とを有する鉄筋コンクリート造の防油堤1の構築方法を提供する。【解決手段】 断面が逆T字状又はL字状のプレキャストコンクリートピース(PCaピース)10を、間隔をあけて配列し、PCaピース10、10間に場所打ちコンクリート50を打設する。ここにおいて、直線部同士のPCaピース10、10間は、場所打ちコンクリート50の打設により、両側のPCaピース10、10の端面から突出する横方向鉄筋が重ね継手で接続される施工目地部SMをなす。角部のPCaピース10Kと直線部のPCaピース10との間は、角部のPCaピース10Kの端面から横方向鉄筋が突出していない状態で場所打ちコンクリート50が打設されて、前記横方向鉄筋によりつながらない構造目地部KMをなす。【選択図】 図1
METHOD FOR CONSTRUCTING OIL RETAINING WALL AND OIL RETAINING WALL STRUCTURE
To provide a construction method of an oil retaining wall 1 of reinforced concrete construction provided to surround an oil storage tank 100 and having a straight line part and a corner part in plan view.SOLUTION: Precast concrete pieces (PCa pieces) 10 having inverted T-shaped or L-shaped cross-sections are arranged at intervals, and a cast-in-place concrete 50 is placed between the PCa pieces 10, 10. Here, between the PCa pieces 10, 10 of straight parts, a construction joint part SM is formed in which lateral reinforcing bars protruding from end surfaces of the PCa pieces 10, 10 on both sides are connected by a lap joint by placing the cast-in-place concrete 50. A cast-in-place concrete 50 is placed between a PCa piece 10K of a corner part and the PCa piece 10 of the straight part in a state that the lateral reinforcing bars does not project from the end face of the PCa piece 10K of the corner part, and forms a structural joint part KM not connected by the lateral reinforcing bars.SELECTED DRAWING: Figure 1
【課題】 貯油タンク100を囲むように設けられ、平面視で直線部と角部とを有する鉄筋コンクリート造の防油堤1の構築方法を提供する。【解決手段】 断面が逆T字状又はL字状のプレキャストコンクリートピース(PCaピース)10を、間隔をあけて配列し、PCaピース10、10間に場所打ちコンクリート50を打設する。ここにおいて、直線部同士のPCaピース10、10間は、場所打ちコンクリート50の打設により、両側のPCaピース10、10の端面から突出する横方向鉄筋が重ね継手で接続される施工目地部SMをなす。角部のPCaピース10Kと直線部のPCaピース10との間は、角部のPCaピース10Kの端面から横方向鉄筋が突出していない状態で場所打ちコンクリート50が打設されて、前記横方向鉄筋によりつながらない構造目地部KMをなす。【選択図】 図1
METHOD FOR CONSTRUCTING OIL RETAINING WALL AND OIL RETAINING WALL STRUCTURE
防油堤の構築方法、及び、防油堤構造
YASUNAGA MASAMICHI (author)
2021-08-19
Patent
Electronic Resource
Japanese
RETAINING WALL STRUCTURE AND METHOD FOR CONSTRUCTING RETAINING WALL
European Patent Office | 2023
|RETAINING WALL BLOCK, RETAINING WALL MEMBER AND METHOD FOR CONSTRUCTING RETAINING WALL BLOCK
European Patent Office | 2021
|retaining wall structure and the method of constructing retaining wall structure
European Patent Office | 2021
|PREFABRICATED RETAINING WALL BLOCK AND METHOD FOR CONSTRUCTING RETAINING WALL
European Patent Office | 2018
|