SOIL RETENTION STRUCTURE AND CONSTRUCTION METHOD THEREOF
To provide a soil retention structure allowing the posture of sheet piles to be stabilized when installing the sheet piles between adjacent steel pipe piles.SOLUTION: A soil retention structure 10 is provided with; a plurality of steel pipe piles 101 aligned at intervals along a wall surface W of the ground foundation; sheet piles 301 placed between adjacent steel pipe piles 101; abutment pieces 201b extending in an axial direction of the steel pipe pile 101 and connected on each of side surfaces of the steel pipe piles 101 to limit motion of the sheet piles 301 in a direction along the wall surface W; and hook pieces extending in the direction along the wall surface W from each of the abutment pieces 201b to abut a surface of a side end part of the sheet pile 301 which is an opposite side surface to the wall surface W.SELECTED DRAWING: Figure 2
【課題】隣り合う鋼管杭の間に矢板を設ける際の矢板の姿勢を安定させる。【解決手段】土留め構造10は、地盤の壁面Wに沿って間隔を置いて配列された複数の鋼管杭101と、隣り合う鋼管杭101の間に設けられる矢板301と、鋼管杭101の軸方向に延在して、鋼管杭101のそれぞれの側面に接合されて、矢板301の壁面Wに沿った方向への動きを規制する当たり片201bと、当たり片201bのそれぞれから壁面Wに沿う方向に延出し、矢板301の側端部の壁面Wとは反対側の面に当接する引掛片と、を備える。【選択図】図2
SOIL RETENTION STRUCTURE AND CONSTRUCTION METHOD THEREOF
To provide a soil retention structure allowing the posture of sheet piles to be stabilized when installing the sheet piles between adjacent steel pipe piles.SOLUTION: A soil retention structure 10 is provided with; a plurality of steel pipe piles 101 aligned at intervals along a wall surface W of the ground foundation; sheet piles 301 placed between adjacent steel pipe piles 101; abutment pieces 201b extending in an axial direction of the steel pipe pile 101 and connected on each of side surfaces of the steel pipe piles 101 to limit motion of the sheet piles 301 in a direction along the wall surface W; and hook pieces extending in the direction along the wall surface W from each of the abutment pieces 201b to abut a surface of a side end part of the sheet pile 301 which is an opposite side surface to the wall surface W.SELECTED DRAWING: Figure 2
【課題】隣り合う鋼管杭の間に矢板を設ける際の矢板の姿勢を安定させる。【解決手段】土留め構造10は、地盤の壁面Wに沿って間隔を置いて配列された複数の鋼管杭101と、隣り合う鋼管杭101の間に設けられる矢板301と、鋼管杭101の軸方向に延在して、鋼管杭101のそれぞれの側面に接合されて、矢板301の壁面Wに沿った方向への動きを規制する当たり片201bと、当たり片201bのそれぞれから壁面Wに沿う方向に延出し、矢板301の側端部の壁面Wとは反対側の面に当接する引掛片と、を備える。【選択図】図2
SOIL RETENTION STRUCTURE AND CONSTRUCTION METHOD THEREOF
土留め構造及びその構築方法
KASUYA YUKI (author)
2021-12-13
Patent
Electronic Resource
Japanese
IPC:
E02D
FOUNDATIONS
,
Gründungen
SOIL RETENTION WALL AND CONSTRUCTION METHOD FOR SOIL RETENTION WALL