PLACING PLAN PREPARATION DEVICE AND PLACING PLAN PREPARATION METHOD
To provide a placing plan preparation device and a placing plan preparation method which enable preparation of a suitable concrete placing plan.SOLUTION: A placing plan preparation device 100 for preparing a placing plan in concrete placing includes: a block group setting part 43 for sequentially setting a candidate brock group that is a set of construction blocks for continuously placing to a construction object; and an in-group order determination part 44 for determining a placing order in the candidate block group. The candidate block group is composed of a placing block adjacent to an attention block and an extension block positioned in the periphery of the placing block, and the block group setting part 43 sets the candidate block group with a construction block in which placing to the adjacent construction block is incompleted and placing completion time is the earliest, as a new attention block.SELECTED DRAWING: Figure 1
【課題】コンクリートの好適な打込み計画を作成することができる打込み計画作成装置および打込み計画作成方法を提供する。【解決手段】コンクリート打設における打込み計画を作成する打込み計画作成装置100であって、連続して打込みを行う施工ブロックのまとまりである候補ブロック群を施工対象物に対して順番に設定するブロック群設定部43と、前記候補ブロック群内の打込み順序を決定する群内順序決定部44と、を備え、前記候補ブロック群は、着目ブロックに隣接する打重ねブロックおよび前記打重ねブロックの周辺に位置する拡張ブロックで構成され、ブロック群設定部43は、隣接する前記施工ブロックに対する打込みが未完了かつ打込み完了時刻が最も早い打込み済みの施工ブロックを新たな前記着目ブロックとして前記候補ブロック群を設定する。【選択図】図1
PLACING PLAN PREPARATION DEVICE AND PLACING PLAN PREPARATION METHOD
To provide a placing plan preparation device and a placing plan preparation method which enable preparation of a suitable concrete placing plan.SOLUTION: A placing plan preparation device 100 for preparing a placing plan in concrete placing includes: a block group setting part 43 for sequentially setting a candidate brock group that is a set of construction blocks for continuously placing to a construction object; and an in-group order determination part 44 for determining a placing order in the candidate block group. The candidate block group is composed of a placing block adjacent to an attention block and an extension block positioned in the periphery of the placing block, and the block group setting part 43 sets the candidate block group with a construction block in which placing to the adjacent construction block is incompleted and placing completion time is the earliest, as a new attention block.SELECTED DRAWING: Figure 1
【課題】コンクリートの好適な打込み計画を作成することができる打込み計画作成装置および打込み計画作成方法を提供する。【解決手段】コンクリート打設における打込み計画を作成する打込み計画作成装置100であって、連続して打込みを行う施工ブロックのまとまりである候補ブロック群を施工対象物に対して順番に設定するブロック群設定部43と、前記候補ブロック群内の打込み順序を決定する群内順序決定部44と、を備え、前記候補ブロック群は、着目ブロックに隣接する打重ねブロックおよび前記打重ねブロックの周辺に位置する拡張ブロックで構成され、ブロック群設定部43は、隣接する前記施工ブロックに対する打込みが未完了かつ打込み完了時刻が最も早い打込み済みの施工ブロックを新たな前記着目ブロックとして前記候補ブロック群を設定する。【選択図】図1
PLACING PLAN PREPARATION DEVICE AND PLACING PLAN PREPARATION METHOD
打込み計画作成装置および打込み計画作成方法
WATABE TAKAHIKO (author) / TAKEDA HITOSHI (author)
2021-12-13
Patent
Electronic Resource
Japanese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
PLACING PLAN PREPARING DEVICE AND PLACING PLAN PREPARING METHOD