SLIDE CONSTRUCTION METHOD FOR RIGID-FRAME STRUCTURE
To provide a slide construction method for a rigid-frame structure having high safety without generating horizontal force of a column base part by the dead weight of the rigid-frame structure.SOLUTION: Working platforms 2, 2 for assembling a partial frame 3 are installed at a specific position S so as to be movable on slide rails 1, 1. The girder G of the partial frame 3 is supported by the working platforms 2, 2, and is transported to a prescribed position on the slide rails 1, 1 with the lower end of the column in a lifted state. In the transported partial frame 3, the support of the girder G is released by jack-down, and the column base part is anchored on predetermined foundation columns f, f,.. and stands by itself. Before the column base part is placed on the foundation columns f, f,., a deviation from an accurate installation position of the column base part is corrected. The self-standing partial frame 3 and the previously installed partial frame 3 are connected. The working platforms 2, 2 are moved back on the slide rails 1, 1 to the specific position S for assembling the next partial frame 3.SELECTED DRAWING: Figure 1
【課題】ラーメン構造物の自重による柱脚部水平力が発生せず、安全性の高いラーメン構造物のスライド工法を提供する。【解決手段】部分架構3を組立てる構台2、2がスライドレール1、1上を移動可能に、特定位置Sに設置される。部分架構3は、その大梁Gが構台2、2によって支持され、柱の下端が宙に浮いた状態で、スライドレール1、1上を所定位置まで運搬される。運搬された部分架構3は、ジャッキダウンにより大梁Gの支持が解除され、前記柱脚部が所定の基礎柱f、f、…上に定着されて自立する。前記柱脚部が基礎柱f、f、…上に載置される前に、前記柱脚部の正確な据付位置とのずれが修正される。自立した部分架構3と先行して設置済みの部分架構3とが連結される。構台2、2が、次の部分架構3を組立てる特定位置Sまで、スライドレール1、1上を移動して戻される。【選択図】図1
SLIDE CONSTRUCTION METHOD FOR RIGID-FRAME STRUCTURE
To provide a slide construction method for a rigid-frame structure having high safety without generating horizontal force of a column base part by the dead weight of the rigid-frame structure.SOLUTION: Working platforms 2, 2 for assembling a partial frame 3 are installed at a specific position S so as to be movable on slide rails 1, 1. The girder G of the partial frame 3 is supported by the working platforms 2, 2, and is transported to a prescribed position on the slide rails 1, 1 with the lower end of the column in a lifted state. In the transported partial frame 3, the support of the girder G is released by jack-down, and the column base part is anchored on predetermined foundation columns f, f,.. and stands by itself. Before the column base part is placed on the foundation columns f, f,., a deviation from an accurate installation position of the column base part is corrected. The self-standing partial frame 3 and the previously installed partial frame 3 are connected. The working platforms 2, 2 are moved back on the slide rails 1, 1 to the specific position S for assembling the next partial frame 3.SELECTED DRAWING: Figure 1
【課題】ラーメン構造物の自重による柱脚部水平力が発生せず、安全性の高いラーメン構造物のスライド工法を提供する。【解決手段】部分架構3を組立てる構台2、2がスライドレール1、1上を移動可能に、特定位置Sに設置される。部分架構3は、その大梁Gが構台2、2によって支持され、柱の下端が宙に浮いた状態で、スライドレール1、1上を所定位置まで運搬される。運搬された部分架構3は、ジャッキダウンにより大梁Gの支持が解除され、前記柱脚部が所定の基礎柱f、f、…上に定着されて自立する。前記柱脚部が基礎柱f、f、…上に載置される前に、前記柱脚部の正確な据付位置とのずれが修正される。自立した部分架構3と先行して設置済みの部分架構3とが連結される。構台2、2が、次の部分架構3を組立てる特定位置Sまで、スライドレール1、1上を移動して戻される。【選択図】図1
SLIDE CONSTRUCTION METHOD FOR RIGID-FRAME STRUCTURE
ラーメン構造物のスライド工法
KAWAZOE TOSHIYUKI (author) / FUJINO TERUMASA (author)
2022-03-04
Patent
Electronic Resource
Japanese
IPC:
E04B
Allgemeine Baukonstruktionen
,
GENERAL BUILDING CONSTRUCTIONS
ELEVATED RIGID FRAME BRIDGE AND ELEVATED RIGID FRAME BRIDGE CONSTRUCTION METHOD
European Patent Office | 2021
|Rigid frame bridge structure and construction method thereof
European Patent Office | 2024
|