FULCRUM FIXTURE AND MOUNTING METHOD OF FULCRUM FIXTURE
To provide a fulcrum that can connect a fall arrest device without damaging a building frame where equipment such as water heaters are installed, and to make it possible to safely carry out work such as maintenance and replacement of the relevant equipment.SOLUTION: A fulcrum fixture 10 includes a fulcrum 20 to which a fall arrest device can be connected, a lower fixture 30 with the fulcrum 20, including a lower first mounting portion 31 fixed to a frame wall surface 16 by using an existing stud bolt 22 (lower fixing member) for fixing a mounting portion 21 (lower portion) of a device 18 to a building frame wall surface 16 and a lower second mounting portion 32 to which the mounting portion 21 (lower portion) of the device 18 is fixed, and an upper fixture 40 with the fulcrum, including an upper first mounting portion 41 fixed to a frame wall surface 16 by using an existing stud bolt 28 (upper fixing member) for fixing a mounting portion 26 (upper portion) of the device 18 to the building frame wall surface 16 and an upper second mounting portion 42 to which the mounting portion 26 (upper portion) of the device 18 is fixed.SELECTED DRAWING: Figure 2
【課題】給湯器等の機器が設置された建物の躯体に、躯体の損傷を伴うことなく、墜落制止用器具を接続可能な支点を設け、当該機器のメンテナンス、取替等の作業を安全に行うことを可能にする。【解決手段】支点取付具10は、墜落制止用器具を接続可能な支点20と、機器18の取付部21(下部)を躯体壁面16に固定するための既設のスタッドボルト22(下部固定部材)を利用して躯体壁面16に固定される下部第1取付部31、及び機器18の取付部21(下部)が固定される下部第2取付部32を備え、支点20が設けられた下部取付具30と、機器18の取付部26(上部)を躯体壁面16に固定するための既設のスタッドボルト28(上部固定部材)を利用して躯体壁面16に固定される上部第1取付部41、及び機器18の取付部26(上部)が固定される上部第2取付部42を備え、前記支点が設けられた上部取付具40と、を有する。【選択図】図2
FULCRUM FIXTURE AND MOUNTING METHOD OF FULCRUM FIXTURE
To provide a fulcrum that can connect a fall arrest device without damaging a building frame where equipment such as water heaters are installed, and to make it possible to safely carry out work such as maintenance and replacement of the relevant equipment.SOLUTION: A fulcrum fixture 10 includes a fulcrum 20 to which a fall arrest device can be connected, a lower fixture 30 with the fulcrum 20, including a lower first mounting portion 31 fixed to a frame wall surface 16 by using an existing stud bolt 22 (lower fixing member) for fixing a mounting portion 21 (lower portion) of a device 18 to a building frame wall surface 16 and a lower second mounting portion 32 to which the mounting portion 21 (lower portion) of the device 18 is fixed, and an upper fixture 40 with the fulcrum, including an upper first mounting portion 41 fixed to a frame wall surface 16 by using an existing stud bolt 28 (upper fixing member) for fixing a mounting portion 26 (upper portion) of the device 18 to the building frame wall surface 16 and an upper second mounting portion 42 to which the mounting portion 26 (upper portion) of the device 18 is fixed.SELECTED DRAWING: Figure 2
【課題】給湯器等の機器が設置された建物の躯体に、躯体の損傷を伴うことなく、墜落制止用器具を接続可能な支点を設け、当該機器のメンテナンス、取替等の作業を安全に行うことを可能にする。【解決手段】支点取付具10は、墜落制止用器具を接続可能な支点20と、機器18の取付部21(下部)を躯体壁面16に固定するための既設のスタッドボルト22(下部固定部材)を利用して躯体壁面16に固定される下部第1取付部31、及び機器18の取付部21(下部)が固定される下部第2取付部32を備え、支点20が設けられた下部取付具30と、機器18の取付部26(上部)を躯体壁面16に固定するための既設のスタッドボルト28(上部固定部材)を利用して躯体壁面16に固定される上部第1取付部41、及び機器18の取付部26(上部)が固定される上部第2取付部42を備え、前記支点が設けられた上部取付具40と、を有する。【選択図】図2
FULCRUM FIXTURE AND MOUNTING METHOD OF FULCRUM FIXTURE
支点取付具及び支点取付具の取付方法
NAGANO YUICHI (author) / IWAI KENJI (author) / SUZUKI MITSURU (author) / EBIZUKA KATSUNORI (author)
2022-10-27
Patent
Electronic Resource
Japanese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
/
A62B
DEVICES, APPARATUS OR METHODS FOR LIFE-SAVING
,
Vorrichtungen, Geräte oder Verfahren zur Lebensrettung
/
F16B
DEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES
,
Vorrichtungen zum Befestigen oder Sichern von Konstruktionselementen oder Maschinenteilen, z.B. Nägel, Bolzen, Schrauben, Sprengringe, Klemmen, Klammern oder Keile
European Patent Office | 2017
|Operation fulcrum and the fulcrum concept
British Library Online Contents | 1999
|British Library Online Contents | 2006
V BRACE FULCRUM CONSTRUCTION METHOD AND V BRACE FULCRUM STRUCTURE
European Patent Office | 2018
|