CONNECTION STRUCTURE OF PILE HEAD PORTION OF STEEL PIPE PILE, AND CONSTRUCTION METHOD OF STEEL PIPE PILE
To provide a connection structure of pile head portions of steel pipe piles capable of reducing works at a construction site and shortening a construction period in constructing.SOLUTION: In a connection structure of pile head portions of steel pipe piles 1 connecting pile head portions 11 of a plurality of steel pipe piles 1 installed on a sea bottom ground by a connection member 2, the connection member 2 comprises a rod-like insertion member 3 inserted into a pipe body of the steel pipe pile 1, and a connection member 4 connecting the plurality of insertion members 3. A infilled concrete 6 installed in the pipe body of the steel pipe pile 1 and the connection member 2 are integrated via the insertion member 3.SELECTED DRAWING: Figure 1
【課題】施工現場での作業を減らして、施工時の工期短縮化を図ることができる鋼管杭の杭頭部結合構造を提案する。【解決手段】海底地盤に打設された複数の鋼管杭1の杭頭部11を結合部材2により結合する鋼管杭1の杭頭部結合構造であって、結合部材2は、鋼管杭1の管体内に挿入される棒状の挿入部材3と、複数の挿入部材3を連結する連結部材4と、で構成されている。鋼管杭1の管体内に打設される中詰めコンクリート6と結合部材2とを挿入部材3を介して一体化する。【選択図】図1
CONNECTION STRUCTURE OF PILE HEAD PORTION OF STEEL PIPE PILE, AND CONSTRUCTION METHOD OF STEEL PIPE PILE
To provide a connection structure of pile head portions of steel pipe piles capable of reducing works at a construction site and shortening a construction period in constructing.SOLUTION: In a connection structure of pile head portions of steel pipe piles 1 connecting pile head portions 11 of a plurality of steel pipe piles 1 installed on a sea bottom ground by a connection member 2, the connection member 2 comprises a rod-like insertion member 3 inserted into a pipe body of the steel pipe pile 1, and a connection member 4 connecting the plurality of insertion members 3. A infilled concrete 6 installed in the pipe body of the steel pipe pile 1 and the connection member 2 are integrated via the insertion member 3.SELECTED DRAWING: Figure 1
【課題】施工現場での作業を減らして、施工時の工期短縮化を図ることができる鋼管杭の杭頭部結合構造を提案する。【解決手段】海底地盤に打設された複数の鋼管杭1の杭頭部11を結合部材2により結合する鋼管杭1の杭頭部結合構造であって、結合部材2は、鋼管杭1の管体内に挿入される棒状の挿入部材3と、複数の挿入部材3を連結する連結部材4と、で構成されている。鋼管杭1の管体内に打設される中詰めコンクリート6と結合部材2とを挿入部材3を介して一体化する。【選択図】図1
CONNECTION STRUCTURE OF PILE HEAD PORTION OF STEEL PIPE PILE, AND CONSTRUCTION METHOD OF STEEL PIPE PILE
鋼管杭の杭頭部結合構造及び鋼管杭の施工方法
HASHIMOTO TAKAYUKI (author) / HASHIMOTO ATSUSHI (author)
2023-01-10
Patent
Electronic Resource
Japanese
STEEL PIPE PILE CONNECTION STRUCTURE, STEEL PIPE PILE CONNECTION METHOD
European Patent Office | 2022
|STEEL PIPE PILE CONNECTION STRUCTURE, STEEL PIPE PILE BASE, AND CONNECTION METHOD OF STEEL PIPE PILE
European Patent Office | 2023
|European Patent Office | 2018
|STEEL PIPE PILE JOINT, STEEL PIPE PILE, AND CONSTRUCTION METHOD OF STEEL PIPE PILE
European Patent Office | 2021
|