MANUFACTURING METHOD OF PRE-FLEX INTRODUCTION TYPE CASING COMPOSITE GIRDER USING FORMWORK WEIGHT
The present invention relates to a method for manufacturing a composite girder in which a reinforcing concrete casing is installed in a lower part of the steel girder. The method comprises the steps of: a) installing a multiproduction table on both sides of the floor of a workshop and fixing a steel girder so that both ends of the steel girder are placed on the multiproduction table, then placing reinforcing bars; b) installing a formwork under the steel girder, wherein point formworks and a span formwork are separately installed so that the weight of the point formworks at both ends of the formwork is supported by the multiproduction table, the weight of the span formwork between the multiproduction tables on both sides is supported by the steel girder, and a preflex load is applied to the steel girder by the weight of the span formwork; c) constructing a concrete casing by pouring concrete for casing construction inside the formwork and curing the concrete; and d) removing the span formwork from the steel girder so that the preflex load applied to the steel girder is released.
본 발명은 강재거더의 하부에 보강용 콘크리트 케이싱이 설치되는 합성거더의 제작방법에 관한 것으로서, 이는 a) 작업장의 바닥 양측에 멀티제작대를 설치하고 강재거더의 양 단부가 상기 멀티제작대에 놓여지도록 고정시킨 후 철근을 배근하는 단계; b) 상기 강재거더의 하부에 거푸집을 설치하되, 상기 거푸집 중 양 단부의 지점거푸집은 멀티제작대에 의해 자중이 지지되도록 하고, 양측 멀티제작대 사이의 경간거푸집은 상기 강재거더에 의해 자중이 지지되도록 지점거푸집과 경간거푸집을 구분하여 설치함으로써, 경간거푸집의 자중에 의해 강재거더에 프리플렉션 하중이 재하되도록 하는 단계; c) 상기 거푸집 내부에 케이싱 구축용 콘크리트를 타설하고 이를 양생하여 콘크리트 케이싱을 구축하는 단계; d) 상기 강재거더로부터 경간거푸집을 제거하여 강재거더에 가해졌던 프리플렉션 하중이 해제되도록 하는 단계;가 포함되는 것을 특징으로 한다.
MANUFACTURING METHOD OF PRE-FLEX INTRODUCTION TYPE CASING COMPOSITE GIRDER USING FORMWORK WEIGHT
The present invention relates to a method for manufacturing a composite girder in which a reinforcing concrete casing is installed in a lower part of the steel girder. The method comprises the steps of: a) installing a multiproduction table on both sides of the floor of a workshop and fixing a steel girder so that both ends of the steel girder are placed on the multiproduction table, then placing reinforcing bars; b) installing a formwork under the steel girder, wherein point formworks and a span formwork are separately installed so that the weight of the point formworks at both ends of the formwork is supported by the multiproduction table, the weight of the span formwork between the multiproduction tables on both sides is supported by the steel girder, and a preflex load is applied to the steel girder by the weight of the span formwork; c) constructing a concrete casing by pouring concrete for casing construction inside the formwork and curing the concrete; and d) removing the span formwork from the steel girder so that the preflex load applied to the steel girder is released.
본 발명은 강재거더의 하부에 보강용 콘크리트 케이싱이 설치되는 합성거더의 제작방법에 관한 것으로서, 이는 a) 작업장의 바닥 양측에 멀티제작대를 설치하고 강재거더의 양 단부가 상기 멀티제작대에 놓여지도록 고정시킨 후 철근을 배근하는 단계; b) 상기 강재거더의 하부에 거푸집을 설치하되, 상기 거푸집 중 양 단부의 지점거푸집은 멀티제작대에 의해 자중이 지지되도록 하고, 양측 멀티제작대 사이의 경간거푸집은 상기 강재거더에 의해 자중이 지지되도록 지점거푸집과 경간거푸집을 구분하여 설치함으로써, 경간거푸집의 자중에 의해 강재거더에 프리플렉션 하중이 재하되도록 하는 단계; c) 상기 거푸집 내부에 케이싱 구축용 콘크리트를 타설하고 이를 양생하여 콘크리트 케이싱을 구축하는 단계; d) 상기 강재거더로부터 경간거푸집을 제거하여 강재거더에 가해졌던 프리플렉션 하중이 해제되도록 하는 단계;가 포함되는 것을 특징으로 한다.
MANUFACTURING METHOD OF PRE-FLEX INTRODUCTION TYPE CASING COMPOSITE GIRDER USING FORMWORK WEIGHT
거푸집 자중을 이용한 프리플렉스 도입형 케이싱 합성거더의 제작방법
2021-11-22
Patent
Electronic Resource
Korean
IPC:
E01D
BRIDGES
,
Brücken
Box girder formwork for bridge construction and use method of box girder formwork
European Patent Office | 2023
|