Demolition method of bridge superstructure using temporary through truss
The present invention relates to a method for disassembling an upper structure of a bridge using a temporary through truss, which is able to secure as much lower space as possible, perform the disassembly on the upper side of the bridge to maintain the operation of the space under the bridge, and be also used as a facility to prevent falling objects. According to the present invention, the method comprises: a step (a) of installing a pair of guide rail units crossing an upper structure on the lower side of the upper structure of a bridge to be apart from each other in a bridge axis direction, and installing two or more temporary bents on both sides of the upper structure of the bridge, respectively; a step (b) of installing a transport cart on the upper side of each guide rail unit; a step (c) of holding a pre-manufactured floor support frame on the upper side of the transport cart with the transport cart located on the outer side of the upper structure of the bridge; a step (d) of slide-moving the transport cart to the lower side of the upper structure of the bridge, and locating the floor support frame on the lower side of the upper structure of the bridge; a step (e) of holding a pair of truss main units, which include an upper chord and a lower chord vertically apart from each other and a batter brace connecting the upper chord and the lower chord, respectively, on the upper side of temporary bents on both sides of the upper structure of the bridge, and engaging the lower side of the truss main units with an end side of the floor support frame to form a temporary through truss; a step (f) of cutting and removing the upper structure of the bridge in a state where the temporary through truss supports the lower side of the upper structure of the bridge; and a step (g) of removing the temporary through truss, the transport cart, the guide rail units, and the temporary bents.
본 발명은 교량 상부구조 해체 시 형하공간을 최대한 확보하고, 교량 상부에서 해체 작업이 가능하여 교하공간 운영을 유지할 수 있으며, 낙하물 방지 시설 겸용이 가능한 가설 하로 트러스를 이용한 교량 상부구조 해체 방법에 대한 것이다. 본 발명은 (a) 교량 상부구조의 하부에 상부구조를 가로지르는 한 쌍의 가이드레일부를 교축 방향으로 서로 이격되도록 설치하는 한편, 교량 상부구조의 양측에 각각 2 이상의 가벤트를 설치하는 단계; (b) 각 가이드레일부의 상부에 이송대차를 설치하는 단계; (c) 상기 이송대차를 교량 상부구조의 외측에 위치시킨 상태에서 사전 제작된 바닥지지틀을 이송대차 상부에 거치시키는 단계; (d) 상기 이송대차를 교량 상부구조 하부로 슬라이딩 이동시켜 바닥지지틀을 교량 상부구조 하부에 위치시키는 단계; (e) 상하로 이격되는 상현재와 하현재 및 상현재와 하현재를 연결하는 사재로 구성되는 한 쌍의 트러스 주구를 각각 교량 상부구조 양측의 가벤트 상부에 거치시킨 후 트러스 주구의 하부를 바닥지지틀 단부와 결합하여 가설 하로 트러스를 형성하는 단계; (f) 상기 가설 하로 트러스가 교량 상부구조의 하부를 지지한 상태에서 교량 상부구조를 절단하여 제거하는 단계; 및 (g) 상기 가설 하로 트러스, 이송대차, 가이드레일부 및 가벤트를 제거하는 단계; 로 구성된다.
Demolition method of bridge superstructure using temporary through truss
The present invention relates to a method for disassembling an upper structure of a bridge using a temporary through truss, which is able to secure as much lower space as possible, perform the disassembly on the upper side of the bridge to maintain the operation of the space under the bridge, and be also used as a facility to prevent falling objects. According to the present invention, the method comprises: a step (a) of installing a pair of guide rail units crossing an upper structure on the lower side of the upper structure of a bridge to be apart from each other in a bridge axis direction, and installing two or more temporary bents on both sides of the upper structure of the bridge, respectively; a step (b) of installing a transport cart on the upper side of each guide rail unit; a step (c) of holding a pre-manufactured floor support frame on the upper side of the transport cart with the transport cart located on the outer side of the upper structure of the bridge; a step (d) of slide-moving the transport cart to the lower side of the upper structure of the bridge, and locating the floor support frame on the lower side of the upper structure of the bridge; a step (e) of holding a pair of truss main units, which include an upper chord and a lower chord vertically apart from each other and a batter brace connecting the upper chord and the lower chord, respectively, on the upper side of temporary bents on both sides of the upper structure of the bridge, and engaging the lower side of the truss main units with an end side of the floor support frame to form a temporary through truss; a step (f) of cutting and removing the upper structure of the bridge in a state where the temporary through truss supports the lower side of the upper structure of the bridge; and a step (g) of removing the temporary through truss, the transport cart, the guide rail units, and the temporary bents.
본 발명은 교량 상부구조 해체 시 형하공간을 최대한 확보하고, 교량 상부에서 해체 작업이 가능하여 교하공간 운영을 유지할 수 있으며, 낙하물 방지 시설 겸용이 가능한 가설 하로 트러스를 이용한 교량 상부구조 해체 방법에 대한 것이다. 본 발명은 (a) 교량 상부구조의 하부에 상부구조를 가로지르는 한 쌍의 가이드레일부를 교축 방향으로 서로 이격되도록 설치하는 한편, 교량 상부구조의 양측에 각각 2 이상의 가벤트를 설치하는 단계; (b) 각 가이드레일부의 상부에 이송대차를 설치하는 단계; (c) 상기 이송대차를 교량 상부구조의 외측에 위치시킨 상태에서 사전 제작된 바닥지지틀을 이송대차 상부에 거치시키는 단계; (d) 상기 이송대차를 교량 상부구조 하부로 슬라이딩 이동시켜 바닥지지틀을 교량 상부구조 하부에 위치시키는 단계; (e) 상하로 이격되는 상현재와 하현재 및 상현재와 하현재를 연결하는 사재로 구성되는 한 쌍의 트러스 주구를 각각 교량 상부구조 양측의 가벤트 상부에 거치시킨 후 트러스 주구의 하부를 바닥지지틀 단부와 결합하여 가설 하로 트러스를 형성하는 단계; (f) 상기 가설 하로 트러스가 교량 상부구조의 하부를 지지한 상태에서 교량 상부구조를 절단하여 제거하는 단계; 및 (g) 상기 가설 하로 트러스, 이송대차, 가이드레일부 및 가벤트를 제거하는 단계; 로 구성된다.
Demolition method of bridge superstructure using temporary through truss
가설 하로 트러스를 이용한 교량 상부구조 해체 방법
KIM JUNGHYUN (author) / PARK JEONGCHEON (author)
2023-07-20
Patent
Electronic Resource
Korean
IPC:
E01D
BRIDGES
,
Brücken
/
B66F
HOISTING, LIFTING, HAULING, OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
,
Hub-, Verhol- oder Schubvorrichtungen, soweit nicht anderweitig vorgesehen, z.B. Vorrichtungen mit unmittelbarer Krafteinwirkung auf die Last
/
G05D
SYSTEMS FOR CONTROLLING OR REGULATING NON-ELECTRIC VARIABLES
,
Systeme zum Steuern oder Regeln nichtelektrischer veränderlicher Größen
Installation method of bridge superstructure using temporary through truss
European Patent Office | 2023
|Demolition construction method for bridge superstructure
European Patent Office | 2020
|Demolition of Waterloo temporary bridge
Engineering Index Backfile | 1946
|Demolition of superstructure of bridge in Bern, Switzerland
Engineering Index Backfile | 1942
|Temporary support for bridge superstructure construction
European Patent Office | 2022
|