Method of demolition of underground exterior walls
The present invention relates to a bottom-up demolition method for an underground external wall. The bottom-up demolition method for an underground external wall enables a user to stably demolish while preventing an underground external wall from being overturned, by demolishing a required section after excavating only the required section while the underground external wall is supported by soil pressure when refilling is performed after the floor of an underground structure is demolished. The bottom-up demolition method for an underground external wall also enables sequential demolition by cutting the underground external wall in a block shape through core work. To achieve the purpose of the present invention, the bottom-up demolition method for underground external wall comprises: a floor demolishing step of demolishing the floor of the underground structure; a refilling step of refilling the inner space of the underground structure in which the floor part is demolished; a grouting step of constructing grouting to prevent dent of sand and earth and cut off water on the outside of the underground external wall; a step of installing a PS wale on the inner surface of the underground external wall; an excavation step of excavating the ground to the bottom of the underground external wall so that the underground external wall to be demolished is exposed; an underground external wall core cutting step of cutting the underground external wall in a block shape by performing continuous core boring work on the underground external wall; a block demolishing step of removing the block which is cut; a demolished section refilling step of refilling sand and earth in the position of the demolished block; and a continuous demolishing step of continuously demolishing the underground external wall in a width direction of the underground external wall by repeating the underground external wall core cutting step, the block demolishing step, and the refilling step.
본 발명은 상향식 지하외벽 철거방법에 관한 것으로, 지하구조물의 바닥을 철거 한 후 되메우기 한 상태에서 지하외벽을 토압으로 지지한 상태에서 필요 구간만 터파기한 후 철거하게 됨으로써 지하외벽의 전도를 방지하면서 안정적으로 철거할 수 있도록 하고, 코어 작업을 통해 지하외벽을 블록형태로 절단하면서 순차적인 철거가 가능하도록 하는 상향식 지하외벽 철거방법을 제공함에 있다. 상기 목적 달성을 위한 본 발명은, 지하구조물의 바닥을 철거하는 바닥 철거단계; 이후 바닥 부분이 철거된 지하구조물의 내측공간을 되메우기 하는 되메우기 단계; 이후 지하외벽의 외측에 차수 및 토사 함몰 방지를 위해 그라우팅을 시공하는 그라우팅 단계; 이후 지하외벽 내면에 PS띠장을 설치하는 단계; 이후 철거하고자 하는 지하외벽이 노출되도록 지하외벽의 바닥까지 터파기하는 터파기 단계; 이후 상기 지하외벽에 연속적인 코어 타공작업을 수행하여 지하외벽을 블록 형태로 절단하는 지하외벽 코어 절단단계; 이후 절단된 블록을 제거하는 블록 철거단계; 이후 상기 철거된 블록위치에 토사를 되메우기 하는 철거구역 되메우기 단계; 이후 지하외벽 코어 절단단계와, 블록 철거단계와, 되메우기 단계를 반복 수행하여 지하외벽의 폭 방향을 따라 지하외벽을 연속적으로 철거하는 연속 철거단계;를 포함하여 구성된 것을 기술적 요지로 한다.
Method of demolition of underground exterior walls
The present invention relates to a bottom-up demolition method for an underground external wall. The bottom-up demolition method for an underground external wall enables a user to stably demolish while preventing an underground external wall from being overturned, by demolishing a required section after excavating only the required section while the underground external wall is supported by soil pressure when refilling is performed after the floor of an underground structure is demolished. The bottom-up demolition method for an underground external wall also enables sequential demolition by cutting the underground external wall in a block shape through core work. To achieve the purpose of the present invention, the bottom-up demolition method for underground external wall comprises: a floor demolishing step of demolishing the floor of the underground structure; a refilling step of refilling the inner space of the underground structure in which the floor part is demolished; a grouting step of constructing grouting to prevent dent of sand and earth and cut off water on the outside of the underground external wall; a step of installing a PS wale on the inner surface of the underground external wall; an excavation step of excavating the ground to the bottom of the underground external wall so that the underground external wall to be demolished is exposed; an underground external wall core cutting step of cutting the underground external wall in a block shape by performing continuous core boring work on the underground external wall; a block demolishing step of removing the block which is cut; a demolished section refilling step of refilling sand and earth in the position of the demolished block; and a continuous demolishing step of continuously demolishing the underground external wall in a width direction of the underground external wall by repeating the underground external wall core cutting step, the block demolishing step, and the refilling step.
본 발명은 상향식 지하외벽 철거방법에 관한 것으로, 지하구조물의 바닥을 철거 한 후 되메우기 한 상태에서 지하외벽을 토압으로 지지한 상태에서 필요 구간만 터파기한 후 철거하게 됨으로써 지하외벽의 전도를 방지하면서 안정적으로 철거할 수 있도록 하고, 코어 작업을 통해 지하외벽을 블록형태로 절단하면서 순차적인 철거가 가능하도록 하는 상향식 지하외벽 철거방법을 제공함에 있다. 상기 목적 달성을 위한 본 발명은, 지하구조물의 바닥을 철거하는 바닥 철거단계; 이후 바닥 부분이 철거된 지하구조물의 내측공간을 되메우기 하는 되메우기 단계; 이후 지하외벽의 외측에 차수 및 토사 함몰 방지를 위해 그라우팅을 시공하는 그라우팅 단계; 이후 지하외벽 내면에 PS띠장을 설치하는 단계; 이후 철거하고자 하는 지하외벽이 노출되도록 지하외벽의 바닥까지 터파기하는 터파기 단계; 이후 상기 지하외벽에 연속적인 코어 타공작업을 수행하여 지하외벽을 블록 형태로 절단하는 지하외벽 코어 절단단계; 이후 절단된 블록을 제거하는 블록 철거단계; 이후 상기 철거된 블록위치에 토사를 되메우기 하는 철거구역 되메우기 단계; 이후 지하외벽 코어 절단단계와, 블록 철거단계와, 되메우기 단계를 반복 수행하여 지하외벽의 폭 방향을 따라 지하외벽을 연속적으로 철거하는 연속 철거단계;를 포함하여 구성된 것을 기술적 요지로 한다.
Method of demolition of underground exterior walls
상향식 지하외벽 철거방법
LEE CHANG IL (author)
2023-08-25
Patent
Electronic Resource
Korean
IPC:
E02D
FOUNDATIONS
,
Gründungen
UNDERGROUND STRUCTURE DEMOLITION METHOD USING EXISTING UNDERGROUND STRUCUTRES