ADIABATIC CONCRETE CONNECTING STRUCTURE AND CONSTRUCTING METHOD
The present invention relates to adiabatic concrete connecting structure and method to form a structure by pouring concrete without a form. The adiabatic concrete connecting method comprises: a step of assembling horizontal and vertical wall re-bars on the top of foundation concrete and installing a pair of U-shaped guide supports on the top of the foundation concrete to face each other in a parallel manner; a step of installing a pair of adiabatic concrete forms (300) on the top of the pair of guide supports along the wall line in a symmetrical manner; a step of primarily applying a first stage of adiabatic concrete form (300) wherein a pair of unit adiabatic concrete forms (300) is fixated and fastened to each other over the entire section; a step of forming a pair of second stage unit adiabatic concrete forms (300) along the wall line and installing a second stage of adiabatic concrete form (300); a step of installing a final stage of adiabatic concrete form (300) as designed by repeating the above steps: and a step of forming an adiabatic concrete wall by pouring and curing concrete into a space between the adiabatic concrete form (300) and an adiabatic panel.
본 발명은 단열콘크리트 구조 및 시공방법에 관한 것으로서, 더욱 상세하게는 단열콘크리트폼을 부품화하고, 공사현장에서 연결고정부재를 통해 단열콘크리트폼을 연결시킴으로서 별도의 거푸집 없이 콘크리트를 타설하여 구조체를 형성할 수 있도록 한 단열콘크리트 구조 및 시공방법에 관한 것으로, 구조물의 벽체를 시공함에 있어서 구조물의 기초바닥이 콘크리트로 형성되고 그 상부에는 수직·수평의 벽체철근이 조립되며 기초바닥 콘크리트 상면에는 단열콘크리트 폼(300)을 고정 해주는 U형 형상의 가이드 받침 1쌍이 평행하게 마주보고 위치하게 설치하는 단계. 1쌍의 가이드 받침위에 상면은 볼록한 원형 돌기 및 T형 홈이 일정간격으로 형성되고 하면은 오목한 원형 홈 및 T형 홈이 일정간격으로 형성된 단열콘크리트 폼(300)을 대칭으로 벽체 라인에 따라 설치하는 단계. 벽체 라인에 따라 설치·구성된 단위 단열콘크리트 폼(300) 상면에 형성된 T자형 홈에 연결 고정핀(400)을 일정간격으로 삽입·설치하여 1쌍의 단위 단열콘크리트 폼(300)을 전 구간에 걸쳐 상호 고정·결속한 1단 단열콘크리트 폼(300)을 첫째로 구성하는 단계. 제 1단 단열콘크리트의 단위 단열콘크리트 폼(300) 상면에 형성되어 있는 원형의 볼록 돌기와 T형 홈에 삽입된 연결 고정핀(400)의 상향으로 돌출된 부분을 제 2단 단열콘크리트 폼(300)의 단위 단열콘크리트 폼(300)의 하면부에 있는 원형의 오목홈과 T형 홈에 삽입하여 1쌍의 제2단 단위 단열콘크리트 폼(300)을 벽체 라인에 따라 형성하고 2단 단위 단열콘크리트 폼(300) 상면에 형성되어 있는 T형 홈에 연결 고정핀(400)을 삽입·고정하여 제 2단 단열콘크리트 폼(300)을 설치하는 단계. 상기 과정을 되풀이하여 설계된 최종 단계의 단열콘크리트 폼(300)을 설치하는 단계. 최종단계의 단위 단열콘크리트 폼(300)이 적층 시공되어 최종단계의 단열콘크리트 폼(300)이 완성된 후에 단열콘크리트 폼(300)의 단열판넬 사이에 콘크리트를 타설·양생하여 단열콘크리트 벽체를 형성하는 단계를 포함하는 것을 특징으로 하는 단열콘크리트 연결구조 시공방법
ADIABATIC CONCRETE CONNECTING STRUCTURE AND CONSTRUCTING METHOD
The present invention relates to adiabatic concrete connecting structure and method to form a structure by pouring concrete without a form. The adiabatic concrete connecting method comprises: a step of assembling horizontal and vertical wall re-bars on the top of foundation concrete and installing a pair of U-shaped guide supports on the top of the foundation concrete to face each other in a parallel manner; a step of installing a pair of adiabatic concrete forms (300) on the top of the pair of guide supports along the wall line in a symmetrical manner; a step of primarily applying a first stage of adiabatic concrete form (300) wherein a pair of unit adiabatic concrete forms (300) is fixated and fastened to each other over the entire section; a step of forming a pair of second stage unit adiabatic concrete forms (300) along the wall line and installing a second stage of adiabatic concrete form (300); a step of installing a final stage of adiabatic concrete form (300) as designed by repeating the above steps: and a step of forming an adiabatic concrete wall by pouring and curing concrete into a space between the adiabatic concrete form (300) and an adiabatic panel.
본 발명은 단열콘크리트 구조 및 시공방법에 관한 것으로서, 더욱 상세하게는 단열콘크리트폼을 부품화하고, 공사현장에서 연결고정부재를 통해 단열콘크리트폼을 연결시킴으로서 별도의 거푸집 없이 콘크리트를 타설하여 구조체를 형성할 수 있도록 한 단열콘크리트 구조 및 시공방법에 관한 것으로, 구조물의 벽체를 시공함에 있어서 구조물의 기초바닥이 콘크리트로 형성되고 그 상부에는 수직·수평의 벽체철근이 조립되며 기초바닥 콘크리트 상면에는 단열콘크리트 폼(300)을 고정 해주는 U형 형상의 가이드 받침 1쌍이 평행하게 마주보고 위치하게 설치하는 단계. 1쌍의 가이드 받침위에 상면은 볼록한 원형 돌기 및 T형 홈이 일정간격으로 형성되고 하면은 오목한 원형 홈 및 T형 홈이 일정간격으로 형성된 단열콘크리트 폼(300)을 대칭으로 벽체 라인에 따라 설치하는 단계. 벽체 라인에 따라 설치·구성된 단위 단열콘크리트 폼(300) 상면에 형성된 T자형 홈에 연결 고정핀(400)을 일정간격으로 삽입·설치하여 1쌍의 단위 단열콘크리트 폼(300)을 전 구간에 걸쳐 상호 고정·결속한 1단 단열콘크리트 폼(300)을 첫째로 구성하는 단계. 제 1단 단열콘크리트의 단위 단열콘크리트 폼(300) 상면에 형성되어 있는 원형의 볼록 돌기와 T형 홈에 삽입된 연결 고정핀(400)의 상향으로 돌출된 부분을 제 2단 단열콘크리트 폼(300)의 단위 단열콘크리트 폼(300)의 하면부에 있는 원형의 오목홈과 T형 홈에 삽입하여 1쌍의 제2단 단위 단열콘크리트 폼(300)을 벽체 라인에 따라 형성하고 2단 단위 단열콘크리트 폼(300) 상면에 형성되어 있는 T형 홈에 연결 고정핀(400)을 삽입·고정하여 제 2단 단열콘크리트 폼(300)을 설치하는 단계. 상기 과정을 되풀이하여 설계된 최종 단계의 단열콘크리트 폼(300)을 설치하는 단계. 최종단계의 단위 단열콘크리트 폼(300)이 적층 시공되어 최종단계의 단열콘크리트 폼(300)이 완성된 후에 단열콘크리트 폼(300)의 단열판넬 사이에 콘크리트를 타설·양생하여 단열콘크리트 벽체를 형성하는 단계를 포함하는 것을 특징으로 하는 단열콘크리트 연결구조 시공방법
ADIABATIC CONCRETE CONNECTING STRUCTURE AND CONSTRUCTING METHOD
단열콘크리트 구조 및 시공방법
ROH KYUNG BEOM (author) / ROH U HYEON (author)
2015-06-03
Patent
Electronic Resource
Korean
IPC:
E04B
Allgemeine Baukonstruktionen
,
GENERAL BUILDING CONSTRUCTIONS
Adiabatic concrete connecting structure and constructing method
European Patent Office | 2015
PC PCPrecast concrete connecting structure and a constructing method thereof
European Patent Office | 2019
|STRUCTURE FOR CONNECTING CONCRETE AND METHOD FOR CONSTRUCTING THE SAME
European Patent Office | 2019
|Prestressed assembled concrete frame-joint connecting structure and constructing method thereof
European Patent Office | 2020
|