A platform for research: civil engineering, architecture and urbanism
.ROLLING METHOD OF GIRDER USING THE SLIDING RAIL
The present invention relates to a bridge construction method to install a girder (100) of a part of span in a multi-span bridge. According to the present invention, a method to withdraw and construct a girder by using a moving rail comprises: a vent installation step of installing a temporary vent (300) in a region of a span (A) in which the girder (100) is installed; a moving rail installation step of installing a moving rail (200) to withdraw the girder (100) on an upper surface of a bottom plate (1) of one side adjacent to the region of the span (A); a first girder installation step of installing the girder (100) in the moving rail (200); a withdrawal device installation step of installing a withdrawal device (400) to withdraw the girder (100) in the opposite side of the bottom plate (1); a withdrawal member installation step of connecting a withdrawal member (410) to the withdrawal device (400) and the girder (100); a second girder installation step of operating the withdrawal device (400) to hold the girder (100) in a holding device (500) installed in both supports (2) of the region of the span (A); a temporary vent removal step of removing the temporary vent (300); and a third girder installation step of lowering the height of the holding device (500) to install the girder (100) in a bridge seat device. According to the present invention, since a part of girders of a continuous bridge in which a crane cannot be used can be constructed by using the moving rail and the withdrawal device, construction can be performed without an expensive temporary installation device. Moreover, since a construction time is short, a construction period can be minimized. Moreover, the moving rail can be applied to all sites irrespective of the length and the size of the bridge.
본 발명은 다경간의 교량 중 일부 경간의 거더(100)를 설치하는 교량 시공방법으로서, 상기 거더(100)가 설치되는 경간(A) 영역에 가설벤트(300)를 설치하는 벤트설치단계, 상기 경간(A) 영역에 인접한 일측 바닥판(1)의 상면에 상기 거더(100)의 견인을 위한 이동레일(200)를 설치하는 이동레일설치단계, 상기 이동레일(200)에 상기 거더(100)를 거치하는 거더거치1단계, 상기 일측 바닥판(1)의 맞은편에 상기 거더(100)를 견인하기 위한 견인장치(400)를 설치하는 견인장치설치단계, 상기 견인장치(400)와 상기 거더(100)에 견인부재(410)를 연결하는 견인부재설치단계, 상기 견인장치(400)를 구동하여 상기 거더(100)를 상기 경간(A) 영역의 양 받침부(2)에 설치된 거치장치(500)에 거치하는 거더거치2단계, 상기 가설벤트(300)를 제거하는 가설벤트제거단계 및 상기 거치장치(500)의 높이가 낮아지도록 구동하여 상기 거더(100)를 교좌장치에 거치하는 거더거치3단계;를 포함하는 것을 특징으로 하는 이동레일을 이용한 교량의 거더견인 시공방법을 제시한다. 본 발명에 따르면 크레인을 사용할 수 없는 연속교량의 일부 거더를 이동레일 및 견인장치를 이용하여 시공하는 방법으로서, 고가의 가설장치 없이 시공할 수 있다. 또한, 시공시간이 짧기 때문에 공사기간을 최소화할 수 있고, 이동레일은 교량의 길이와 크기에 관계없이 모든 현장에 적용 가능하다.
.ROLLING METHOD OF GIRDER USING THE SLIDING RAIL
The present invention relates to a bridge construction method to install a girder (100) of a part of span in a multi-span bridge. According to the present invention, a method to withdraw and construct a girder by using a moving rail comprises: a vent installation step of installing a temporary vent (300) in a region of a span (A) in which the girder (100) is installed; a moving rail installation step of installing a moving rail (200) to withdraw the girder (100) on an upper surface of a bottom plate (1) of one side adjacent to the region of the span (A); a first girder installation step of installing the girder (100) in the moving rail (200); a withdrawal device installation step of installing a withdrawal device (400) to withdraw the girder (100) in the opposite side of the bottom plate (1); a withdrawal member installation step of connecting a withdrawal member (410) to the withdrawal device (400) and the girder (100); a second girder installation step of operating the withdrawal device (400) to hold the girder (100) in a holding device (500) installed in both supports (2) of the region of the span (A); a temporary vent removal step of removing the temporary vent (300); and a third girder installation step of lowering the height of the holding device (500) to install the girder (100) in a bridge seat device. According to the present invention, since a part of girders of a continuous bridge in which a crane cannot be used can be constructed by using the moving rail and the withdrawal device, construction can be performed without an expensive temporary installation device. Moreover, since a construction time is short, a construction period can be minimized. Moreover, the moving rail can be applied to all sites irrespective of the length and the size of the bridge.
본 발명은 다경간의 교량 중 일부 경간의 거더(100)를 설치하는 교량 시공방법으로서, 상기 거더(100)가 설치되는 경간(A) 영역에 가설벤트(300)를 설치하는 벤트설치단계, 상기 경간(A) 영역에 인접한 일측 바닥판(1)의 상면에 상기 거더(100)의 견인을 위한 이동레일(200)를 설치하는 이동레일설치단계, 상기 이동레일(200)에 상기 거더(100)를 거치하는 거더거치1단계, 상기 일측 바닥판(1)의 맞은편에 상기 거더(100)를 견인하기 위한 견인장치(400)를 설치하는 견인장치설치단계, 상기 견인장치(400)와 상기 거더(100)에 견인부재(410)를 연결하는 견인부재설치단계, 상기 견인장치(400)를 구동하여 상기 거더(100)를 상기 경간(A) 영역의 양 받침부(2)에 설치된 거치장치(500)에 거치하는 거더거치2단계, 상기 가설벤트(300)를 제거하는 가설벤트제거단계 및 상기 거치장치(500)의 높이가 낮아지도록 구동하여 상기 거더(100)를 교좌장치에 거치하는 거더거치3단계;를 포함하는 것을 특징으로 하는 이동레일을 이용한 교량의 거더견인 시공방법을 제시한다. 본 발명에 따르면 크레인을 사용할 수 없는 연속교량의 일부 거더를 이동레일 및 견인장치를 이용하여 시공하는 방법으로서, 고가의 가설장치 없이 시공할 수 있다. 또한, 시공시간이 짧기 때문에 공사기간을 최소화할 수 있고, 이동레일은 교량의 길이와 크기에 관계없이 모든 현장에 적용 가능하다.
.ROLLING METHOD OF GIRDER USING THE SLIDING RAIL
이동레일을 이용한 거더견인 시공방법.
WOO DONG IN (author) / SONG TAE EON (author) / BAE MIN HYUK (author) / JEON SEUNG MIN (author) / CHO WOO IL (author) / CHUN SANG UK (author)
2017-04-07
Patent
Electronic Resource
Korean
IPC:
E01D
BRIDGES
,
Brücken
Work developed in rail and girder rolling
Engineering Index Backfile
Sliding rail type steel box girder bottom plate access hole
European Patent Office | 2024
|