GROUND REINFORCEMENT METHOD USING A MICROPILE INCLIDING MULTI-EXPANSION ANCHOR
The present invention relates to a ground reinforcement method using a micro-pile grafted with a multi-expansion body, capable of increasing a pressing area and force of a wedge piece pressed around a drilled hole. According to the present invention, the ground reinforcement method using a micro-pile grafted with a multi-expansion body comprises: a step of drilling a drilled hole (H1) to a predetermined depth in the ground; a step of inserting the multi-expansion body (100) mounted on the bottom part of a spiral rebar (200) into the drilled hole (H1) to allow a craw (142) of the multi-expansion body (100) to be driven in the bottom surface of the drilled hole (H1); a step of allowing a moving cone member (110) to outwardly push each wedge piece (120) such that each wedge piece (120) is pressed around the drilled hole (H1); a step of injecting a grouting injection agent (250) into the drilled hole (H1); and a step of arranging a head part of the spiral rebar (200) exposed on the ground and depositing base concrete (260).
본 발명은 나선형 철근의 하단부에 장착된 다단 확장체를 천공홀에 삽입하여, 천공홀의 바닥면에 다단 확장체의 클로우가 박히게 하고, 다단 확장체가 천공홀의 바닥면에 배치된 상태에서, 가동콘 부재가 웨지편을 바깥으로 밀어내어, 각각의 웨지편이 천공홀의 둘레에 압착되도록, 나선형 철근을 돌리는 다단 확장체를 접목한 마이크로 파일을 적용한 지반보강공법에 관한 것이다. 본 발명에 따른 다단 확장체를 접목한 마이크로 파일을 적용한 지반보강공법은 (1) 지반에 천공홀(H1)을 소정의 깊이로 천공하는 단계와, (2) 천공홀(H1)의 바닥면(3)에 다단 확장체(100)의 클로우(142)가 박히도록, 나선형 철근(200)의 하단부에 장착된 다단 확장체(100)를 천공홀(H1)에 삽입하는 단계와, 여기서, 상기 다단 확장체(100)는 가동콘 부재(110)의 둘레에 배치된 복수개의 웨지편(120)이 고무밴드(130)에 의해 묶여짐으로써, 가동콘 부재(110)의 경사부(111)에 웨지편(120)의 경사부(121)가 대응되게 배치되고, 가동콘 부재(11)의 둘레에 복수개의 가이드 덧살부(115)가 상하 길이 방향으로 일자형으로 길게 형성되어, 가이드 덧살부(115)가 웨지편(120) 사이에 배치되며, 가동콘 부재(110)의 중공부(113)의 둘레에 나선 체결부가 형성되어, 나선형 철근(200)의 하단부가 중공부(113)의 나선 체결부에 체결되며, 가동콘 부재(110)의 하단에 웨지 연결판(140)이 배치되고, 각각의 웨지편(120)이 웨지 연결판(140)의 연결편(141)에 각각 연결되고, 웨지 연결판(140)에 복수개의 클로우(142)가 형성되어, 클로우(142)가 웨지 연결판(140)에서 연결편(141)의 반대 방향으로 향하게 되고, (3) 나선형 철근(200)을 돌리면, 나선형 철근(200)에 체결된 가동콘 부재(110)가 웨지편(120)에 대해 상대적으로 상승하게 됨으로써, 가동콘 부재(110)가 각각의 웨지편(120))을 바깥으로 밀어내어, 각각의 웨지편(120)이 천공홀(H1)의 둘레에 압착되는 단계와, (4) 천공홀(H1)에 그라우팅 주입제(250)를 주입하는 단계와, (5) 지면 위로 노출된 나선형 철근(200)의 두부를 정리하고, 기초 콘크리트(260)를 타설하는 단계로 구성되는 것을 특징으로 한다.
GROUND REINFORCEMENT METHOD USING A MICROPILE INCLIDING MULTI-EXPANSION ANCHOR
The present invention relates to a ground reinforcement method using a micro-pile grafted with a multi-expansion body, capable of increasing a pressing area and force of a wedge piece pressed around a drilled hole. According to the present invention, the ground reinforcement method using a micro-pile grafted with a multi-expansion body comprises: a step of drilling a drilled hole (H1) to a predetermined depth in the ground; a step of inserting the multi-expansion body (100) mounted on the bottom part of a spiral rebar (200) into the drilled hole (H1) to allow a craw (142) of the multi-expansion body (100) to be driven in the bottom surface of the drilled hole (H1); a step of allowing a moving cone member (110) to outwardly push each wedge piece (120) such that each wedge piece (120) is pressed around the drilled hole (H1); a step of injecting a grouting injection agent (250) into the drilled hole (H1); and a step of arranging a head part of the spiral rebar (200) exposed on the ground and depositing base concrete (260).
본 발명은 나선형 철근의 하단부에 장착된 다단 확장체를 천공홀에 삽입하여, 천공홀의 바닥면에 다단 확장체의 클로우가 박히게 하고, 다단 확장체가 천공홀의 바닥면에 배치된 상태에서, 가동콘 부재가 웨지편을 바깥으로 밀어내어, 각각의 웨지편이 천공홀의 둘레에 압착되도록, 나선형 철근을 돌리는 다단 확장체를 접목한 마이크로 파일을 적용한 지반보강공법에 관한 것이다. 본 발명에 따른 다단 확장체를 접목한 마이크로 파일을 적용한 지반보강공법은 (1) 지반에 천공홀(H1)을 소정의 깊이로 천공하는 단계와, (2) 천공홀(H1)의 바닥면(3)에 다단 확장체(100)의 클로우(142)가 박히도록, 나선형 철근(200)의 하단부에 장착된 다단 확장체(100)를 천공홀(H1)에 삽입하는 단계와, 여기서, 상기 다단 확장체(100)는 가동콘 부재(110)의 둘레에 배치된 복수개의 웨지편(120)이 고무밴드(130)에 의해 묶여짐으로써, 가동콘 부재(110)의 경사부(111)에 웨지편(120)의 경사부(121)가 대응되게 배치되고, 가동콘 부재(11)의 둘레에 복수개의 가이드 덧살부(115)가 상하 길이 방향으로 일자형으로 길게 형성되어, 가이드 덧살부(115)가 웨지편(120) 사이에 배치되며, 가동콘 부재(110)의 중공부(113)의 둘레에 나선 체결부가 형성되어, 나선형 철근(200)의 하단부가 중공부(113)의 나선 체결부에 체결되며, 가동콘 부재(110)의 하단에 웨지 연결판(140)이 배치되고, 각각의 웨지편(120)이 웨지 연결판(140)의 연결편(141)에 각각 연결되고, 웨지 연결판(140)에 복수개의 클로우(142)가 형성되어, 클로우(142)가 웨지 연결판(140)에서 연결편(141)의 반대 방향으로 향하게 되고, (3) 나선형 철근(200)을 돌리면, 나선형 철근(200)에 체결된 가동콘 부재(110)가 웨지편(120)에 대해 상대적으로 상승하게 됨으로써, 가동콘 부재(110)가 각각의 웨지편(120))을 바깥으로 밀어내어, 각각의 웨지편(120)이 천공홀(H1)의 둘레에 압착되는 단계와, (4) 천공홀(H1)에 그라우팅 주입제(250)를 주입하는 단계와, (5) 지면 위로 노출된 나선형 철근(200)의 두부를 정리하고, 기초 콘크리트(260)를 타설하는 단계로 구성되는 것을 특징으로 한다.
GROUND REINFORCEMENT METHOD USING A MICROPILE INCLIDING MULTI-EXPANSION ANCHOR
다단 확장체를 접목한 마이크로 파일을 적용한 지반보강공법
NO IN HWAN (author)
2018-06-26
Patent
Electronic Resource
Korean
IPC:
E02D
FOUNDATIONS
,
Gründungen
Slope stabilization by micropile reinforcement
British Library Conference Proceedings | 1996
|REINFORCEMENT STRUCTURE AND REINFORCEMENT METHOD OF FOUNDATION STRUCTURE USING MICROPILE
European Patent Office | 2024
Micropile and micropile molding method for earthquake-proof and strengthening ground
European Patent Office | 2018
|Micropile foundation structure and construction method of micropile foundation
European Patent Office | 2018
|