CONSTRUCTION METHOD FOR IMMERSED TUNNEL AT LOW OVERBURDEN
The present invention relates to a tunnel construction method for an underwater shallow ground section (a) using a slurry type shield construction method. The tunnel construction method for an underwater shallow ground section (a) comprises: a cofferdam installation step of installing a cofferdam (10) on an upper portion of the underwater shallow ground section (a); an excavation step of excavating the internal area of the cofferdam (10) to form an excavation unit (20), and performing excavation up to an upper portion of a construction area of a tunnel; an arch member installation step of installing an arch member (100) through the excavation unit (20) to prevent upward ejection of slurry used in the slurry type shield construction method and prevent elevation of a tunnel segment (110) by buoyancy; a backfilling step of forming a backfilling unit (30) by backfilling the excavation unit (20) to bury the arch member (100); and a tunnel excavation step of excavating lower ground of the arch member (100) by the slurry type shield construction method, and installing the tunnel segment (110). Slurry pressure loss caused by slurry loss can be prevented, and the elevation of the tunnel segment can be prevented.
본 발명은 이수가압식 쉴드공법을 이용한 하저 저토피 지반구간(a)의 터널 시공방법에 관한 것으로서, 상기 저토피 지반구간(a)의 상부에 가물막이(10)를 설치하는 가물막이 설치단계; 상기 가물막이(10)의 내부 영역을 개착하여 개착부(20)를 형성하되, 상기 터널의 시공영역의 상부까지 굴착하는 개착 단계; 상기 이수가압식 쉴드공법에 사용되는 이수의 상부 분출을 방지하고, 부력에 의한 터널 세그먼트(110)의 융기를 방지하도록, 상기 개착부(20)를 통해 아치부재(100)를 설치하는 아치부재 설치단계; 상기 아치부재(100)가 매설되도록, 상기 개착부(20)를 되메움하여 되메움부(30)를 형성하는 되메움 단계; 상기 이수가압식 쉴드공법에 의해 상기 아치부재(100)의 하부지반을 굴착하고, 상기 터널 세그먼트(110)를 설치하는 터널 굴착단계;를 포함하는 것을 특징으로 하는 하저 저토피 지반구간의 터널 시공방법을 제시함으로써, 이수의 유실에 의한 이수압 손실을 방지하고, 터널 세그먼트의 융기를 방지할 수 있도록 한다.
CONSTRUCTION METHOD FOR IMMERSED TUNNEL AT LOW OVERBURDEN
The present invention relates to a tunnel construction method for an underwater shallow ground section (a) using a slurry type shield construction method. The tunnel construction method for an underwater shallow ground section (a) comprises: a cofferdam installation step of installing a cofferdam (10) on an upper portion of the underwater shallow ground section (a); an excavation step of excavating the internal area of the cofferdam (10) to form an excavation unit (20), and performing excavation up to an upper portion of a construction area of a tunnel; an arch member installation step of installing an arch member (100) through the excavation unit (20) to prevent upward ejection of slurry used in the slurry type shield construction method and prevent elevation of a tunnel segment (110) by buoyancy; a backfilling step of forming a backfilling unit (30) by backfilling the excavation unit (20) to bury the arch member (100); and a tunnel excavation step of excavating lower ground of the arch member (100) by the slurry type shield construction method, and installing the tunnel segment (110). Slurry pressure loss caused by slurry loss can be prevented, and the elevation of the tunnel segment can be prevented.
본 발명은 이수가압식 쉴드공법을 이용한 하저 저토피 지반구간(a)의 터널 시공방법에 관한 것으로서, 상기 저토피 지반구간(a)의 상부에 가물막이(10)를 설치하는 가물막이 설치단계; 상기 가물막이(10)의 내부 영역을 개착하여 개착부(20)를 형성하되, 상기 터널의 시공영역의 상부까지 굴착하는 개착 단계; 상기 이수가압식 쉴드공법에 사용되는 이수의 상부 분출을 방지하고, 부력에 의한 터널 세그먼트(110)의 융기를 방지하도록, 상기 개착부(20)를 통해 아치부재(100)를 설치하는 아치부재 설치단계; 상기 아치부재(100)가 매설되도록, 상기 개착부(20)를 되메움하여 되메움부(30)를 형성하는 되메움 단계; 상기 이수가압식 쉴드공법에 의해 상기 아치부재(100)의 하부지반을 굴착하고, 상기 터널 세그먼트(110)를 설치하는 터널 굴착단계;를 포함하는 것을 특징으로 하는 하저 저토피 지반구간의 터널 시공방법을 제시함으로써, 이수의 유실에 의한 이수압 손실을 방지하고, 터널 세그먼트의 융기를 방지할 수 있도록 한다.
CONSTRUCTION METHOD FOR IMMERSED TUNNEL AT LOW OVERBURDEN
하저 저토피 지반구간의 터널 시공방법
CHOI JAE HO (author) / AHN DONG YEOL (author) / JUNG JEE HEE (author) / HAN JUN (author) / KOH SUNG YIL (author) / KIM JUN SEOP (author)
2022-09-14
Patent
Electronic Resource
Korean
NTIS | 1970
|Semi open cut type tunnel construction method at low overburden
European Patent Office | 2020
|Semi open cut type tunnel construction method at low overburden
European Patent Office | 2019
|