METHOD OF ERECTING PREFABRICATED PRESTRESSED REINFORCED CONCRETE FRAMEWORK OF MULTI-SECTION BUILDING
FIELD: construction.SUBSTANCE: method of erecting prefabricated prestressed framework includes erecting columns with through openings, laying flooring slabs in the building framework spans and cable reinforcement for the entire length of the building between the slab rows, passed through the column openings, tensioning the reinforcement and anchoring it on the extreme framework columns with the subsequent monolithing joints between the slabs and the columns with concrete. Between the sections of the building, paired columns are erected with forming expansion joints between them. Between the paired columns in the expansion joints, temporary spacers are installed, and anchor devices with thrust plates are installed on the cable reinforcement, and the reinforcement is tensioned with anchoring it, with the abutment on the extreme and paired columns. Then the cable reinforcement in the expansion joints is cut, and the temporary spacers are dismantled.EFFECT: technology simplification.7 dwg
Изобретение относится к области строительства, в частности к способу возведения сборного предварительно напряженного железобетонного каркаса многосекционного здания. Технический результат изобретения заключается в упрощении технологии возведения каркаса. Способ возведения сборного предварительно напряженного каркаса включает возведение колонн со сквозными отверстиями, укладку в пролетах каркаса здания плит перекрытия и канатной арматуры на всю длину здания между рядами плит и пропущенной сквозь отверстия колонн, натяжение арматуры и заанкеривание ее на крайних колоннах каркаса с последующим замоноличиванием бетоном швов между плитами и колоннами. Между секциями здания возводят спаренные колонны с образованием между ними деформационных швов. Между спаренными колоннами в деформационных швах устанавливают временные распорки, а на канатную арматуру устанавливают анкерные устройства с упорными пластинами и производят натяжение арматуры с заанкериванием ее с упором на крайние и спаренные колонны. Затем канатную арматуру в деформационных швах разрезают и демонтируют временные распорки. 7 ил.
METHOD OF ERECTING PREFABRICATED PRESTRESSED REINFORCED CONCRETE FRAMEWORK OF MULTI-SECTION BUILDING
FIELD: construction.SUBSTANCE: method of erecting prefabricated prestressed framework includes erecting columns with through openings, laying flooring slabs in the building framework spans and cable reinforcement for the entire length of the building between the slab rows, passed through the column openings, tensioning the reinforcement and anchoring it on the extreme framework columns with the subsequent monolithing joints between the slabs and the columns with concrete. Between the sections of the building, paired columns are erected with forming expansion joints between them. Between the paired columns in the expansion joints, temporary spacers are installed, and anchor devices with thrust plates are installed on the cable reinforcement, and the reinforcement is tensioned with anchoring it, with the abutment on the extreme and paired columns. Then the cable reinforcement in the expansion joints is cut, and the temporary spacers are dismantled.EFFECT: technology simplification.7 dwg
Изобретение относится к области строительства, в частности к способу возведения сборного предварительно напряженного железобетонного каркаса многосекционного здания. Технический результат изобретения заключается в упрощении технологии возведения каркаса. Способ возведения сборного предварительно напряженного каркаса включает возведение колонн со сквозными отверстиями, укладку в пролетах каркаса здания плит перекрытия и канатной арматуры на всю длину здания между рядами плит и пропущенной сквозь отверстия колонн, натяжение арматуры и заанкеривание ее на крайних колоннах каркаса с последующим замоноличиванием бетоном швов между плитами и колоннами. Между секциями здания возводят спаренные колонны с образованием между ними деформационных швов. Между спаренными колоннами в деформационных швах устанавливают временные распорки, а на канатную арматуру устанавливают анкерные устройства с упорными пластинами и производят натяжение арматуры с заанкериванием ее с упором на крайние и спаренные колонны. Затем канатную арматуру в деформационных швах разрезают и демонтируют временные распорки. 7 ил.
METHOD OF ERECTING PREFABRICATED PRESTRESSED REINFORCED CONCRETE FRAMEWORK OF MULTI-SECTION BUILDING
СПОСОБ ВОЗВЕДЕНИЯ СБОРНОГО ПРЕДВАРИТЕЛЬНО НАПРЯЖЕННОГО ЖЕЛЕЗОБЕТОННОГО КАРКАСА МНОГОСЕКЦИОННОГО ЗДАНИЯ
GULADZE TEJMURIZ ILICH (author)
2017-10-10
Patent
Electronic Resource
Russian
IPC:
E04B
Allgemeine Baukonstruktionen
,
GENERAL BUILDING CONSTRUCTIONS
METHOD OF ERECTING MONOLITHIC PRESTRESSED REINFORCED CONCRETE FRAMEWORK OF MULTI-SECTION BUILDING
European Patent Office | 2017
|Ribbed prestressed reinforced concrete prefabricated member plate
European Patent Office | 2015
|Prefabricated prestressed strip-shaped reinforced concrete foundation
European Patent Office | 2021
|European Patent Office | 2022
|Prestressed prefabricated reinforced concrete road plate and preparation method thereof
European Patent Office | 2025
|