According to the present invention, a cutting step comprises: a groove formation step for forming a groove part (2) extending, along an outer peripheral section of a cutting region (13), from an upper end section of a mat slab (1) to a middle section thereof in the vertical direction; a core hole formation step for forming first core holes (41) at two different places in the groove part (2) so that the first core holes reach the bottom section (2a) of the groove part (2); a wire saw installation step for installing a pulley (52) in each of the two first core holes (41), installing a wire saw (51) so that a middle portion (51a) thereof in the longitudinal direction surrounds the cutting region (13), winding the wire saw (51) around the two pulleys (52), and pulling both longitudinal end portions (51b) of the wire saw (51) out above the mat slab (1) via the core holes; and a bottom section cutting step for pulling the wire saw (51) upward from the both end portions (51b), moving the wire saw along the bottom section (13a) of the cutting region (13), and cutting the cutting region (13).
Selon la présente invention, dans ledit procédé, une étape de coupe comprend : une étape de formation de rainure pour former une partie de rainure (2) qui s'étend, le long d'une section périphérique extérieure d'une région de coupe (13), depuis une section d'extrémité supérieure d'une dalle de tapis (1) jusqu'à une section médiane de celle-ci dans la direction verticale ; une étape de formation de trou central pour former des premiers trous centraux (41) à deux emplacements différents dans la partie de rainure (2) de telle sorte que les premiers trous centraux atteignent la section inférieure (2a) de la partie de rainure (2) ; une étape d'installation de scie à fil pour installer une poulie (52) dans chacun des deux premiers trous centraux (41), installer une scie à fil (51) de telle sorte qu'une partie médiane (51a) de celle-ci dans la direction longitudinale entoure la région de coupe (13), enrouler la scie à fil (51) autour des deux poulies (52), et tirer les deux parties d'extrémité longitudinales (51b) de la scie à fil (51) au-dessus de la dalle de tapis (1) par l'intermédiaire des trous centraux ; et une étape de coupe de section inférieure pour tirer la scie à fil (51) vers le haut à partir des deux parties d'extrémité (51b), déplacer la scie à fil le long de la section inférieure (13a) de la région de coupe (13), et couper la région de coupe (13).
切断工程では、切断領域(13)の外周部に沿ってマットスラブ(1)の上端部から上下方向の中間部まで達する溝部(2)を形成する溝部形成工程と、溝部(2における異なる2箇所において第1コア孔(41)を溝部2の底部(2a)に達するように形成するコア孔形成工程と、2つの第1コア孔(41)それぞれにプーリ(52)を設置し、ワイヤーソー(51)の長さ方向の中間部分(51a)を切断領域(13)を囲むように設置するとともに、前記ワイヤーソー(51)を2つのプーリ(52)に巻き掛けて、ワイヤーソー(51)の長さ方向の両端部分(51b)をコア孔を通してマットスラブ(1)の上方に引出すワイヤーソー装置設置工程と、ワイヤーソー(51)を両端部分(51b)それぞれから上方に引き上げて切断領域(13)の底部(13a)に沿って移動させ、切断領域(13)を切断する底部切断工程と、を有する。
According to the present invention, a cutting step comprises: a groove formation step for forming a groove part (2) extending, along an outer peripheral section of a cutting region (13), from an upper end section of a mat slab (1) to a middle section thereof in the vertical direction; a core hole formation step for forming first core holes (41) at two different places in the groove part (2) so that the first core holes reach the bottom section (2a) of the groove part (2); a wire saw installation step for installing a pulley (52) in each of the two first core holes (41), installing a wire saw (51) so that a middle portion (51a) thereof in the longitudinal direction surrounds the cutting region (13), winding the wire saw (51) around the two pulleys (52), and pulling both longitudinal end portions (51b) of the wire saw (51) out above the mat slab (1) via the core holes; and a bottom section cutting step for pulling the wire saw (51) upward from the both end portions (51b), moving the wire saw along the bottom section (13a) of the cutting region (13), and cutting the cutting region (13).
Selon la présente invention, dans ledit procédé, une étape de coupe comprend : une étape de formation de rainure pour former une partie de rainure (2) qui s'étend, le long d'une section périphérique extérieure d'une région de coupe (13), depuis une section d'extrémité supérieure d'une dalle de tapis (1) jusqu'à une section médiane de celle-ci dans la direction verticale ; une étape de formation de trou central pour former des premiers trous centraux (41) à deux emplacements différents dans la partie de rainure (2) de telle sorte que les premiers trous centraux atteignent la section inférieure (2a) de la partie de rainure (2) ; une étape d'installation de scie à fil pour installer une poulie (52) dans chacun des deux premiers trous centraux (41), installer une scie à fil (51) de telle sorte qu'une partie médiane (51a) de celle-ci dans la direction longitudinale entoure la région de coupe (13), enrouler la scie à fil (51) autour des deux poulies (52), et tirer les deux parties d'extrémité longitudinales (51b) de la scie à fil (51) au-dessus de la dalle de tapis (1) par l'intermédiaire des trous centraux ; et une étape de coupe de section inférieure pour tirer la scie à fil (51) vers le haut à partir des deux parties d'extrémité (51b), déplacer la scie à fil le long de la section inférieure (13a) de la région de coupe (13), et couper la région de coupe (13).
切断工程では、切断領域(13)の外周部に沿ってマットスラブ(1)の上端部から上下方向の中間部まで達する溝部(2)を形成する溝部形成工程と、溝部(2における異なる2箇所において第1コア孔(41)を溝部2の底部(2a)に達するように形成するコア孔形成工程と、2つの第1コア孔(41)それぞれにプーリ(52)を設置し、ワイヤーソー(51)の長さ方向の中間部分(51a)を切断領域(13)を囲むように設置するとともに、前記ワイヤーソー(51)を2つのプーリ(52)に巻き掛けて、ワイヤーソー(51)の長さ方向の両端部分(51b)をコア孔を通してマットスラブ(1)の上方に引出すワイヤーソー装置設置工程と、ワイヤーソー(51)を両端部分(51b)それぞれから上方に引き上げて切断領域(13)の底部(13a)に沿って移動させ、切断領域(13)を切断する底部切断工程と、を有する。
METHOD FOR DISMANTLING MAT SLAB
PROCÉDÉ DE DÉMONTAGE DE DALLE DE TAPIS
マットスラブの解体方法
OKUYAMA NOBUHIRO (author)
2019-06-27
Patent
Electronic Resource
Japanese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Bottom-up dismantling method using existing building slab