ULTRA-LONG STEEL STRAND THREADING CONSTRUCTION METHOD FOR CONTINUOUS BEAM
An ultra-long steel strand (6) threading construction method for a continuous beam, comprising the steps of: threading a glass fiber (3) through a continuous beam (1) by means of a glass fiber threading machine; after the glass fiber (3) passes through the continuous beam, connecting the glass fiber (3) and a first steel wire rope (4), manually pulling same after connection, and using the first steel wire rope (4) as a lead; connecting the first steel wire rope (4) and a second steel wire rope (5) in a snap-fit manner, checking a joint, arranging a winch (9) at a small mileage side, using the winch (9) to perform construction, and pulling the second steel wire rope (5) by means of the first steel wire rope (4); and connecting the second steel wire rope (5) and a plurality of steel strands (6) in a snap-fit manner, dragging the plurality of steel strands (6) from the interior of a corrugated pipe by means of the winch (9), and fixing the plurality of steel strands (6) by means of an anchor. The present invention solves the problem in the prior art that during construction of a large-span bridge, it is very difficult to perform steel strand threading construction, the construction equipment is simple and the material is conventional and easily acquired; the construction method is simple and easy to implement, and completes tasks that cannot be completed by the largest threading machine; and the construction speed is high, and the whole threading of steel strands can be completed at one time.
Procédé de construction à filetage de brin d'acier ultra-long (6) pour une poutre continue, comprenant les étapes consistant à : fileter une fibre de verre (3) par le biais d'une poutre continue (1) au moyen d'une machine de filetage de fibre de verre ; après que la fibre de verre (3) passe à travers la poutre continue, relier la fibre de verre (3) et un premier câble d'acier (4), tirer manuellement celui-ci après la liaison, et utiliser le premier câble d'acier (4) en tant que conducteur ; relier le premier câble d'acier (4) et un second câble d'acier (5) par encliquetage, vérifier un joint, disposer un treuil (9) au niveau d'un petit côté de kilométrage, utiliser le treuil (9) pour procéder à la construction, et tirer le second câble d'acier (5) au moyen du premier câble d'acier (4) ; et relier le second câble d'acier (5) et une pluralité de brins d'acier (6) par encliquetage, faire glisser la pluralité de brins d'acier (6) à partir de l'intérieur d'un tuyau ondulé au moyen du treuil (9), et fixer la pluralité de brins d'acier (6) au moyen d'un dispositif d'ancrage. La présente invention résout le problème de l'état de la technique selon lequel, lors de la construction d'un pont à grande portée, il est très difficile de procéder à la construction à filetage de brin d'acier, l'équipement de construction est simple et les matériaux sont traditionnels et facilement acquis ; le procédé de construction est simple et facile à mettre en œuvre, et exécute des tâches qui ne peuvent pas être exécutées par la plus grande machine de filetage ; et la vitesse de construction est élevée, et le filetage de brins d'acier peut être intégralement réalisé en une seule fois.
一种连续梁超长束钢绞线(6)穿束施工方法,包括步骤:将玻璃纤维(3)通过玻璃纤维穿束机在连续梁(1)中穿束;在玻璃纤维(3)通过之后,将玻璃纤维(3)与第一钢丝绳(4)连接,连接后人工拽拉,将第一钢丝绳(4)作为引线;将第一钢丝绳(4)与第二钢丝绳(5)采用卡扣连接,检查接口,在小里程侧布置卷扬机(9),采用卷扬机(9)施工,将第二钢丝绳(5)通过第一钢丝绳(4)拽过来;将第二钢丝绳(5)与多根钢绞线(6)卡扣连接,通过卷扬机(9)将多根钢绞线(6)从波纹管内拖拽,将多根钢绞线(6)用锚具固定。解决现有技术大跨度桥梁施工过程中钢绞线穿束施工难度大的问题,施工设备简单且材料常规,易获取;施工方法简单易实现,完成最大穿束机无法完成的任务;施工速度快,可一次完成钢绞线整体穿束。
ULTRA-LONG STEEL STRAND THREADING CONSTRUCTION METHOD FOR CONTINUOUS BEAM
An ultra-long steel strand (6) threading construction method for a continuous beam, comprising the steps of: threading a glass fiber (3) through a continuous beam (1) by means of a glass fiber threading machine; after the glass fiber (3) passes through the continuous beam, connecting the glass fiber (3) and a first steel wire rope (4), manually pulling same after connection, and using the first steel wire rope (4) as a lead; connecting the first steel wire rope (4) and a second steel wire rope (5) in a snap-fit manner, checking a joint, arranging a winch (9) at a small mileage side, using the winch (9) to perform construction, and pulling the second steel wire rope (5) by means of the first steel wire rope (4); and connecting the second steel wire rope (5) and a plurality of steel strands (6) in a snap-fit manner, dragging the plurality of steel strands (6) from the interior of a corrugated pipe by means of the winch (9), and fixing the plurality of steel strands (6) by means of an anchor. The present invention solves the problem in the prior art that during construction of a large-span bridge, it is very difficult to perform steel strand threading construction, the construction equipment is simple and the material is conventional and easily acquired; the construction method is simple and easy to implement, and completes tasks that cannot be completed by the largest threading machine; and the construction speed is high, and the whole threading of steel strands can be completed at one time.
Procédé de construction à filetage de brin d'acier ultra-long (6) pour une poutre continue, comprenant les étapes consistant à : fileter une fibre de verre (3) par le biais d'une poutre continue (1) au moyen d'une machine de filetage de fibre de verre ; après que la fibre de verre (3) passe à travers la poutre continue, relier la fibre de verre (3) et un premier câble d'acier (4), tirer manuellement celui-ci après la liaison, et utiliser le premier câble d'acier (4) en tant que conducteur ; relier le premier câble d'acier (4) et un second câble d'acier (5) par encliquetage, vérifier un joint, disposer un treuil (9) au niveau d'un petit côté de kilométrage, utiliser le treuil (9) pour procéder à la construction, et tirer le second câble d'acier (5) au moyen du premier câble d'acier (4) ; et relier le second câble d'acier (5) et une pluralité de brins d'acier (6) par encliquetage, faire glisser la pluralité de brins d'acier (6) à partir de l'intérieur d'un tuyau ondulé au moyen du treuil (9), et fixer la pluralité de brins d'acier (6) au moyen d'un dispositif d'ancrage. La présente invention résout le problème de l'état de la technique selon lequel, lors de la construction d'un pont à grande portée, il est très difficile de procéder à la construction à filetage de brin d'acier, l'équipement de construction est simple et les matériaux sont traditionnels et facilement acquis ; le procédé de construction est simple et facile à mettre en œuvre, et exécute des tâches qui ne peuvent pas être exécutées par la plus grande machine de filetage ; et la vitesse de construction est élevée, et le filetage de brins d'acier peut être intégralement réalisé en une seule fois.
一种连续梁超长束钢绞线(6)穿束施工方法,包括步骤:将玻璃纤维(3)通过玻璃纤维穿束机在连续梁(1)中穿束;在玻璃纤维(3)通过之后,将玻璃纤维(3)与第一钢丝绳(4)连接,连接后人工拽拉,将第一钢丝绳(4)作为引线;将第一钢丝绳(4)与第二钢丝绳(5)采用卡扣连接,检查接口,在小里程侧布置卷扬机(9),采用卷扬机(9)施工,将第二钢丝绳(5)通过第一钢丝绳(4)拽过来;将第二钢丝绳(5)与多根钢绞线(6)卡扣连接,通过卷扬机(9)将多根钢绞线(6)从波纹管内拖拽,将多根钢绞线(6)用锚具固定。解决现有技术大跨度桥梁施工过程中钢绞线穿束施工难度大的问题,施工设备简单且材料常规,易获取;施工方法简单易实现,完成最大穿束机无法完成的任务;施工速度快,可一次完成钢绞线整体穿束。
ULTRA-LONG STEEL STRAND THREADING CONSTRUCTION METHOD FOR CONTINUOUS BEAM
PROCÉDÉ DE CONSTRUCTION À FILETAGE DE BRIN D'ACIER ULTRA-LONG POUR UNE POUTRE CONTINUE
一种连续梁超长束钢绞线穿束施工方法
YANG YUPING (author) / DU XIANWU (author) / ZHOU JIANJUN (author) / DENG ZONGREN (author) / AN YOULI (author) / WANG HAIBO (author) / WANG JING (author) / WANG JIE (author) / LI XIAOLEI (author) / ZHANG BIN (author)
2021-07-22
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
Strand pulling construction method for ultra-long steel strand of continuous beam