SLURRY WALL TRENCHING COMPREHENSIVE CONSTRUCTION METHOD FOR PIPELINES
The present invention relates to the technical field of slurry wall construction. Disclosed is a slurry wall trenching comprehensive construction method for pipelines, comprising the following steps: S10, detecting positions of the pipelines, and performing reinforcement protection; S20, constructing guide walls on both sides of the top of a trench hole; S30, performing soil grabbing trenching on both sides of the pipelines; S40, performing soil grabbing trenching under the pipelines; S50, performing impact trenching on a rock stratum at the bottom of the trench hole; S60, placing a reinforcement cage into the trench hole; and S70, pouring concrete into the trench hole to form a trench. The slurry wall trenching comprehensive construction method for the pipelines provided in the technical solution of the present invention is high in construction efficiency, low in safety risk, and low in comprehensive costs.
La présente invention concerne le domaine technique de la construction de paroi moulée. Est divulgué un procédé de construction complète de tranchée de paroi moulée pour des pipelines, comprenant les étapes suivantes : S10, la détection de positions des pipelines et la réalisation d'une protection de renforcement; S20, la construction de parois de guidage des deux côtés du sommet d'un trou de tranchée; S30, la réalisation d'une tranchée de préhension de sol des deux côtés des pipelines; S40, la réalisation d'une tranchée de préhension de sol sous les pipelines; S50, la réalisation d'une tranchée d'impact sur une strate de roche au fond du trou de tranchée; S60, le placement d'une cage de renforcement dans le trou de tranchée; et S70, la coulée de béton dans le trou de tranchée pour former une tranchée. Le procédé de construction complète de tranchée de paroi moulée pour les pipelines décrit dans la solution technique de la présente invention présente un rendement de construction élevé, un faible risque de sécurité et un faible coût global.
本发明涉及地下连续墙施工的技术领域,公开了一种管线地下连续墙成槽综合施工方法,包括以下步骤:S10,探明管线的位置,并进行加固保护;S20,在槽孔顶部的两侧施工导墙;S30,在所述管线两侧抓土成槽;S40,对所述管线正下方抓土成槽;S50,对所述槽孔底部的岩层进行冲击成槽;S60,在所述槽孔内安放钢筋笼;S70,在所述槽孔内浇筑混凝土成槽。本发明技术方案给出的管线地下连续墙成槽综合施工方法,施工效率高、安全风险小且综合成本低。
SLURRY WALL TRENCHING COMPREHENSIVE CONSTRUCTION METHOD FOR PIPELINES
The present invention relates to the technical field of slurry wall construction. Disclosed is a slurry wall trenching comprehensive construction method for pipelines, comprising the following steps: S10, detecting positions of the pipelines, and performing reinforcement protection; S20, constructing guide walls on both sides of the top of a trench hole; S30, performing soil grabbing trenching on both sides of the pipelines; S40, performing soil grabbing trenching under the pipelines; S50, performing impact trenching on a rock stratum at the bottom of the trench hole; S60, placing a reinforcement cage into the trench hole; and S70, pouring concrete into the trench hole to form a trench. The slurry wall trenching comprehensive construction method for the pipelines provided in the technical solution of the present invention is high in construction efficiency, low in safety risk, and low in comprehensive costs.
La présente invention concerne le domaine technique de la construction de paroi moulée. Est divulgué un procédé de construction complète de tranchée de paroi moulée pour des pipelines, comprenant les étapes suivantes : S10, la détection de positions des pipelines et la réalisation d'une protection de renforcement; S20, la construction de parois de guidage des deux côtés du sommet d'un trou de tranchée; S30, la réalisation d'une tranchée de préhension de sol des deux côtés des pipelines; S40, la réalisation d'une tranchée de préhension de sol sous les pipelines; S50, la réalisation d'une tranchée d'impact sur une strate de roche au fond du trou de tranchée; S60, le placement d'une cage de renforcement dans le trou de tranchée; et S70, la coulée de béton dans le trou de tranchée pour former une tranchée. Le procédé de construction complète de tranchée de paroi moulée pour les pipelines décrit dans la solution technique de la présente invention présente un rendement de construction élevé, un faible risque de sécurité et un faible coût global.
本发明涉及地下连续墙施工的技术领域,公开了一种管线地下连续墙成槽综合施工方法,包括以下步骤:S10,探明管线的位置,并进行加固保护;S20,在槽孔顶部的两侧施工导墙;S30,在所述管线两侧抓土成槽;S40,对所述管线正下方抓土成槽;S50,对所述槽孔底部的岩层进行冲击成槽;S60,在所述槽孔内安放钢筋笼;S70,在所述槽孔内浇筑混凝土成槽。本发明技术方案给出的管线地下连续墙成槽综合施工方法,施工效率高、安全风险小且综合成本低。
SLURRY WALL TRENCHING COMPREHENSIVE CONSTRUCTION METHOD FOR PIPELINES
PROCÉDÉ DE CONSTRUCTION COMPLÈTE DE TRANCHÉE DE PAROI MOULÉE POUR PIPELINES
管线地下连续墙成槽综合施工方法
HUANG KAI (author) / LEI BIN (author) / TONG XIN (author) / SHEN XIAOPING (author) / HOU LEI (author) / LI BO (author) / WU ZENGGUI (author)
2021-10-14
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
British Library Online Contents | 2017
|Underground diaphragm wall trenching machine and construction method thereof
European Patent Office | 2023
|Hole collapse preventive trenching construction method of underground diaphragm wall
European Patent Office | 2015
|