ROCK-SOCKETED MONOPILE CONSTRUCTION METHOD BASED ON DOUBLE-CASING PILE STABILIZING PLATFORM
The present invention relates to the field of offshore wind power engineering, and in particular to a rock-socketed monopile construction method based on a double-casing pile stabilizing platform. The method comprises: hoisting a double-casing pile stabilizing platform to a preset place to enter seawater and settle on the seabed; inserting and piling the double-casing pile stabilizing platform, so that an intermediate casing and an outer casing of the double-casing pile stabilizing platform are both piled into a sludge layer; inserting an inner casing into the intermediate casing for piling until the inner casing abuts against a rock stratum; dumping filling an anti-scouring material into a dumping fill space of the double-casing pile stabilizing platform from a dumping fill port of a first platform of the double-casing pile stabilizing platform; drilling a pile hole; putting a monopile into the drilled pile hole to a designed height; and performing grouting reinforcement on the bottom and the outer side of the monopile. According to the present invention, a soil body can be reinforced to improve the safety of offshore wind power rock-socketed monopiles, and by means of the double-casing structure of the present invention, the water flow effect during scour protection construction is reduced, so that the problem of poor construction precision due to the effect of water flow during scour protection and dumping filling operations is solved.
La présente invention se rapporte au domaine de l'ingénierie de l'énergie éolienne en mer, et concerne en particulier un procédé de construction de monopieu à ancrage rocheux basé sur une plate-forme de stabilisation de pieu à double enveloppe. Le procédé comprend : le levage d'une plate-forme de stabilisation de pieu à double enveloppe à un endroit prédéfini pour qu'elle pénètre dans l'eau de mer et s'installe sur le fond marin ; l'insertion et l'empilement de la plate-forme de stabilisation de pieu à double enveloppe, de sorte qu'une enveloppe intermédiaire et une enveloppe externe de la plate-forme de stabilisation de pieu à double enveloppe sont toutes deux empilées dans une couche de boue ; l'insertion d'une enveloppe interne dans l'enveloppe intermédiaire pour l'empilement jusqu'à ce que l'enveloppe interne vienne en butée contre une strate rocheuse ; le déversement d'un matériau anti-affouillement dans un espace de remplissage de déversement de la plate-forme de stabilisation de pieu à double enveloppe à partir d'un orifice de remplissage de déversement d'une première plate-forme de la plate-forme de stabilisation de pieu à double enveloppe ; le forage d'un trou de pieu ; la mise en place d'un monopieu dans le trou de pieu foré à une hauteur prévue ; et la réalisation d'un renfort par injection de ciment sur le fond et le côté extérieur du monopieu. Selon la présente invention, une masse de sol peut être renforcée pour améliorer la sécurité des monopieux à ancrage rocheux de l'énergie éolienne en mer, et au moyen de la structure à double enveloppe selon la présente invention, l'effet d'écoulement d'eau pendant la construction de protection contre l'affouillement est réduit, de sorte que le problème de mauvaise précision de construction due à l'effet de l'écoulement d'eau pendant des opérations de protection contre l'affouillement et de remplissage de déversement est résolu.
本发明属于海上风电工程领域,具体涉及一种基于双护筒稳桩平台的嵌岩单桩施工方法,包括:将双护筒稳桩平台吊装到预定地点,进行入水着床;对双护筒稳桩平台进行插打,使双护筒稳桩平台的中间护筒和外护筒均打入淤泥层;将内护筒插入中间护筒进行插打,并插打至内护筒与岩层相抵;在双护筒稳桩平台的第一平台的抛填口往双护筒稳桩平台的抛填空间内抛填防冲刷材料;钻桩孔;将单桩放入钻好的桩孔并放至设计高度;在单桩底部及外侧进行灌浆加固。通过本发明可以加固土体以提高海上风电嵌岩单桩安全性,而且本发明通过双护筒结构减少冲刷防护施工时水流作用,进而解决冲刷防护抛填作业时,受水流影响,施工精度差的问题。
ROCK-SOCKETED MONOPILE CONSTRUCTION METHOD BASED ON DOUBLE-CASING PILE STABILIZING PLATFORM
The present invention relates to the field of offshore wind power engineering, and in particular to a rock-socketed monopile construction method based on a double-casing pile stabilizing platform. The method comprises: hoisting a double-casing pile stabilizing platform to a preset place to enter seawater and settle on the seabed; inserting and piling the double-casing pile stabilizing platform, so that an intermediate casing and an outer casing of the double-casing pile stabilizing platform are both piled into a sludge layer; inserting an inner casing into the intermediate casing for piling until the inner casing abuts against a rock stratum; dumping filling an anti-scouring material into a dumping fill space of the double-casing pile stabilizing platform from a dumping fill port of a first platform of the double-casing pile stabilizing platform; drilling a pile hole; putting a monopile into the drilled pile hole to a designed height; and performing grouting reinforcement on the bottom and the outer side of the monopile. According to the present invention, a soil body can be reinforced to improve the safety of offshore wind power rock-socketed monopiles, and by means of the double-casing structure of the present invention, the water flow effect during scour protection construction is reduced, so that the problem of poor construction precision due to the effect of water flow during scour protection and dumping filling operations is solved.
La présente invention se rapporte au domaine de l'ingénierie de l'énergie éolienne en mer, et concerne en particulier un procédé de construction de monopieu à ancrage rocheux basé sur une plate-forme de stabilisation de pieu à double enveloppe. Le procédé comprend : le levage d'une plate-forme de stabilisation de pieu à double enveloppe à un endroit prédéfini pour qu'elle pénètre dans l'eau de mer et s'installe sur le fond marin ; l'insertion et l'empilement de la plate-forme de stabilisation de pieu à double enveloppe, de sorte qu'une enveloppe intermédiaire et une enveloppe externe de la plate-forme de stabilisation de pieu à double enveloppe sont toutes deux empilées dans une couche de boue ; l'insertion d'une enveloppe interne dans l'enveloppe intermédiaire pour l'empilement jusqu'à ce que l'enveloppe interne vienne en butée contre une strate rocheuse ; le déversement d'un matériau anti-affouillement dans un espace de remplissage de déversement de la plate-forme de stabilisation de pieu à double enveloppe à partir d'un orifice de remplissage de déversement d'une première plate-forme de la plate-forme de stabilisation de pieu à double enveloppe ; le forage d'un trou de pieu ; la mise en place d'un monopieu dans le trou de pieu foré à une hauteur prévue ; et la réalisation d'un renfort par injection de ciment sur le fond et le côté extérieur du monopieu. Selon la présente invention, une masse de sol peut être renforcée pour améliorer la sécurité des monopieux à ancrage rocheux de l'énergie éolienne en mer, et au moyen de la structure à double enveloppe selon la présente invention, l'effet d'écoulement d'eau pendant la construction de protection contre l'affouillement est réduit, de sorte que le problème de mauvaise précision de construction due à l'effet de l'écoulement d'eau pendant des opérations de protection contre l'affouillement et de remplissage de déversement est résolu.
本发明属于海上风电工程领域,具体涉及一种基于双护筒稳桩平台的嵌岩单桩施工方法,包括:将双护筒稳桩平台吊装到预定地点,进行入水着床;对双护筒稳桩平台进行插打,使双护筒稳桩平台的中间护筒和外护筒均打入淤泥层;将内护筒插入中间护筒进行插打,并插打至内护筒与岩层相抵;在双护筒稳桩平台的第一平台的抛填口往双护筒稳桩平台的抛填空间内抛填防冲刷材料;钻桩孔;将单桩放入钻好的桩孔并放至设计高度;在单桩底部及外侧进行灌浆加固。通过本发明可以加固土体以提高海上风电嵌岩单桩安全性,而且本发明通过双护筒结构减少冲刷防护施工时水流作用,进而解决冲刷防护抛填作业时,受水流影响,施工精度差的问题。
ROCK-SOCKETED MONOPILE CONSTRUCTION METHOD BASED ON DOUBLE-CASING PILE STABILIZING PLATFORM
PROCÉDÉ DE CONSTRUCTION DE MONOPIEU À ANCRAGE ROCHEUX BASÉ SUR UNE PLATE-FORME DE STABILISATION DE PIEU À DOUBLE COFFRAGE
一种基于双护筒稳桩平台的嵌岩单桩施工方法
ZHU RONGHUA (author) / LUAN FUHAO (author) / LIU HANQIU (author) / ZHANG CAILIANG (author) / TU ZHISHENG (author) / SUN XIANG (author) / XU QINGFU (author)
2024-01-11
Patent
Electronic Resource
Chinese
Pile stabilizing steel casing for pouring type socketed pile
European Patent Office | 2023
|FABRICATED PLATFORM FOR OFFSHORE WIND POWER MONOPILE ROCK-SOCKETED FOUNDATION CONSTRUCTION
European Patent Office | 2023
|Underwater full pile casing rock-socketed cast-in-place pile construction method
European Patent Office | 2023
|Convenient-to-assemble pile stabilizing steel casing for socketed pile
European Patent Office | 2023