UNDERWATER DRIVEN PILE POSITIONING SYSTEM FOR FOUNDATION STEEL PIPE PILES OF DEEPWATER FOUR-PILE JACKET
Disclosed in the present invention is an underwater driven pile positioning system for foundation steel pipe piles of a deepwater four-pile jacket, comprising a main base, four sets of leveling devices, four sets of pile holding devices, a hydraulic system, a monitoring system and a control system. The main base comprises four vertical pile frames and four connecting beams; a cage opening is formed in the top of each vertical pile frame; and the upper and lower parts of four corners of each vertical pile frame are provided with four upper pile holding supports and four lower pile holding supports. The four connecting beams are connected among the upper parts of the four vertical pile frames; the four sets of leveling devices are mounted at the bottoms of the four vertical pile frames; each set of leveling device comprises an anti-sinking plate and four leveling lifting/lowering mechanisms connected between the lower parts of four upright posts of the vertical pile frame and the top surface of the anti-sinking plate; and the four sets of pile holding devices are mounted in inner cavities of the four vertical pile frames. Each set of pile holding device comprises four upper-layer pile grippers and four lower-layer pile grippers which are arranged on four upper pile holding supports and four lower pile holding supports. The present invention has the remarkable characteristics of automation, visualization, high precision, high efficiency and high integration.
La présente invention concerne un système de positionnement de pile entraînée sous l'eau pour des piles en tube d'acier de fondation d'un treillis à quatre piles en eau profonde, comprenant une base principale, quatre ensembles de dispositifs de mise à niveau, quatre ensembles de dispositifs de maintien de pile, un système hydraulique, un système de surveillance et un système de commande. La base principale comprend quatre cadres de piles verticaux et quatre poutres de liaison ; une ouverture de cage est formée dans la partie supérieure de chaque cadre de pile vertical ; et les parties supérieure et inférieure des quatre coins de chaque cadre de pile vertical comportent quatre supports de maintien de pile supérieurs et quatre supports de maintien de pile inférieurs. Les quatre poutres de liaison sont reliées entre les parties supérieures des quatre cadres de piles verticaux ; les quatre ensembles de dispositifs de mise à niveau sont montés au niveau des parties inférieures des quatre cadres de piles verticaux ; chaque ensemble de dispositifs de mise à niveau comprend une plaque anti-affaissement et quatre mécanismes de levage/abaissement de mise à niveau reliés entre les parties inférieures de quatre montants verticaux du cadre de pile vertical et la surface supérieure de la plaque anti-affaissement ; et les quatre ensembles de dispositifs de maintien de pile sont montés dans des cavités internes des quatre cadres de piles verticaux. Chaque ensemble de dispositifs de maintien de pile comprend quatre dispositifs de préhension de pile de couche supérieure et quatre dispositifs de préhension de pile de couche inférieure qui sont agencés sur quatre supports de maintien de pile supérieurs et quatre supports de maintien de pile inférieurs. La présente invention présente les caractéristiques remarquables d'automatisation, de visualisation, de haute précision, de haute efficacité et de haute intégration.
本发明公开了一种深水四桩导管架的基础钢管桩的水下沉桩定位系统,包括主体基盘、四套调平装置、四套抱桩装置、液压系统、监测系统和控制系统。主体基盘包括四个立式桩架和四根联系梁;每个立式桩架的顶部均设置一个笼口;每个立式桩架的四个角部的上、下部设置四个上、下部抱桩支架;四根联系梁连接在四个立式桩架的上部之间;四套调平装置安装在四个立式桩架的底部;每套调平装置包括一块防沉板和四个连接在立式桩架的四根立柱的下部与防沉板的顶面之间的调平升降机构;四套抱桩装置安装在四个立式桩架的内腔中;每套抱桩装置包括四个设在四个上、下部抱桩支架的上、下层抱桩器。本发明具有自动化、可视化、高精度、高效、高度集成的显著特点。
UNDERWATER DRIVEN PILE POSITIONING SYSTEM FOR FOUNDATION STEEL PIPE PILES OF DEEPWATER FOUR-PILE JACKET
Disclosed in the present invention is an underwater driven pile positioning system for foundation steel pipe piles of a deepwater four-pile jacket, comprising a main base, four sets of leveling devices, four sets of pile holding devices, a hydraulic system, a monitoring system and a control system. The main base comprises four vertical pile frames and four connecting beams; a cage opening is formed in the top of each vertical pile frame; and the upper and lower parts of four corners of each vertical pile frame are provided with four upper pile holding supports and four lower pile holding supports. The four connecting beams are connected among the upper parts of the four vertical pile frames; the four sets of leveling devices are mounted at the bottoms of the four vertical pile frames; each set of leveling device comprises an anti-sinking plate and four leveling lifting/lowering mechanisms connected between the lower parts of four upright posts of the vertical pile frame and the top surface of the anti-sinking plate; and the four sets of pile holding devices are mounted in inner cavities of the four vertical pile frames. Each set of pile holding device comprises four upper-layer pile grippers and four lower-layer pile grippers which are arranged on four upper pile holding supports and four lower pile holding supports. The present invention has the remarkable characteristics of automation, visualization, high precision, high efficiency and high integration.
La présente invention concerne un système de positionnement de pile entraînée sous l'eau pour des piles en tube d'acier de fondation d'un treillis à quatre piles en eau profonde, comprenant une base principale, quatre ensembles de dispositifs de mise à niveau, quatre ensembles de dispositifs de maintien de pile, un système hydraulique, un système de surveillance et un système de commande. La base principale comprend quatre cadres de piles verticaux et quatre poutres de liaison ; une ouverture de cage est formée dans la partie supérieure de chaque cadre de pile vertical ; et les parties supérieure et inférieure des quatre coins de chaque cadre de pile vertical comportent quatre supports de maintien de pile supérieurs et quatre supports de maintien de pile inférieurs. Les quatre poutres de liaison sont reliées entre les parties supérieures des quatre cadres de piles verticaux ; les quatre ensembles de dispositifs de mise à niveau sont montés au niveau des parties inférieures des quatre cadres de piles verticaux ; chaque ensemble de dispositifs de mise à niveau comprend une plaque anti-affaissement et quatre mécanismes de levage/abaissement de mise à niveau reliés entre les parties inférieures de quatre montants verticaux du cadre de pile vertical et la surface supérieure de la plaque anti-affaissement ; et les quatre ensembles de dispositifs de maintien de pile sont montés dans des cavités internes des quatre cadres de piles verticaux. Chaque ensemble de dispositifs de maintien de pile comprend quatre dispositifs de préhension de pile de couche supérieure et quatre dispositifs de préhension de pile de couche inférieure qui sont agencés sur quatre supports de maintien de pile supérieurs et quatre supports de maintien de pile inférieurs. La présente invention présente les caractéristiques remarquables d'automatisation, de visualisation, de haute précision, de haute efficacité et de haute intégration.
本发明公开了一种深水四桩导管架的基础钢管桩的水下沉桩定位系统,包括主体基盘、四套调平装置、四套抱桩装置、液压系统、监测系统和控制系统。主体基盘包括四个立式桩架和四根联系梁;每个立式桩架的顶部均设置一个笼口;每个立式桩架的四个角部的上、下部设置四个上、下部抱桩支架;四根联系梁连接在四个立式桩架的上部之间;四套调平装置安装在四个立式桩架的底部;每套调平装置包括一块防沉板和四个连接在立式桩架的四根立柱的下部与防沉板的顶面之间的调平升降机构;四套抱桩装置安装在四个立式桩架的内腔中;每套抱桩装置包括四个设在四个上、下部抱桩支架的上、下层抱桩器。本发明具有自动化、可视化、高精度、高效、高度集成的显著特点。
UNDERWATER DRIVEN PILE POSITIONING SYSTEM FOR FOUNDATION STEEL PIPE PILES OF DEEPWATER FOUR-PILE JACKET
SYSTÈME DE POSITIONNEMENT DE PILE ENTRAÎNÉE SOUS L'EAU POUR DES PILES EN TUBE D'ACIER DE FONDATION D'UN TREILLIS À QUATRE PILES EN EAU PROFONDE
一种深水四桩导管架的基础钢管桩的水下沉桩定位系统
LIN XIAO (author) / HUANG JIANYANG (author) / LIU YONG (author) / YAN XIAOFENG (author) / GUO XINJIE (author) / WANG QIBIAO (author) / CHEN TIANSHENG (author)
2024-05-02
Patent
Electronic Resource
Chinese
European Patent Office | 2023
|European Patent Office | 2024
|European Patent Office | 2024
|Offshore wind power underwater four-pile jacket foundation construction pile stabilizing platform
European Patent Office | 2024
|Underwater measurement method for steel pipe pile of jacket foundation by adopting pile-first method
European Patent Office | 2024
|