INSTALLATION METHOD FOR FINAL JOINT OF IMMERSED TUBE TUNNEL
The present application belongs to the field of final joint construction and relates to an installation method for a final joint of an immersed tube tunnel. The installation method comprises steps such as: establishing a first coordinate system; arranging feature points; installing an N+2 tube segment; installing an N+1 tube segment;, and pushing out an abutting section; wherein the first coordinate system is established at the tail end of an N+3 tube segment; passage points N+1S, N+1W are separately arranged at the head and tail ends of the N+1 tube segment, passage points DS and DW are arranged at the abutment section, and passage points N+2S and N+2W are separately arranged at the head and tail ends of the N+2 tube segment; and coordinates of the passage points DS, DW, N+1S, N+1W, N+2S, N+2W are calculated in the first coordinate system. The installation method can increase the installation precision of a final joint, and has easy operations.
La présente demande appartient au domaine de la construction de joint final et concerne un procédé d'installation pour un joint final d'un tunnel tubulaire immergé. Le procédé d'installation comprend les étapes consistant à : établir un premier système de coordonnées ; agencer des points caractéristiques ; installer un segment de tube N+2 ; installer un segment de tube N+1 ; et pousser vers l'extérieur une section de butée ; le premier système de coordonnées étant établi à l'extrémité de queue d'un segment de tube N+3 ; des points de passage N+1S, N+1W étant agencés séparément au niveau des extrémités de tête et de queue du segment de tube N+1, des points de passage DS et DW étant agencés au niveau de la section de butée, et des points de passage N+2S et N+2W étant agencés séparément au niveau des extrémités de tête et de queue du segment de tube N+2 ; et des coordonnées des points de passage DS, DW, N+1S, N+1W, N+2S, N+2W étant calculées dans le premier système de coordonnées. Le procédé d'installation peut augmenter la précision d'installation d'un joint final, et présente des opérations faciles.
本申请涉及一种沉管隧道最终接头的安装方法,属于最终接头施工领域,该安装方法包括建立第一坐标系、布设特征点、安装N+2管节、安装N+1管节和推出顶进节段等步骤;其中第一坐标系建立于N+3管节的尾端;在N+1管节的首尾端分别布设贯通点N+1S、N+1W,在顶进节段布设贯通点DS、DW,在N+2管节的首尾端分别布设贯通点N+2S、N+2W;并分别计算贯通点DS、DW、N+1S、N+1W、N+2S、N+2W在第一坐标系的坐标;该安装方法可以增加最终接头的安装精度并且易操作。
INSTALLATION METHOD FOR FINAL JOINT OF IMMERSED TUBE TUNNEL
The present application belongs to the field of final joint construction and relates to an installation method for a final joint of an immersed tube tunnel. The installation method comprises steps such as: establishing a first coordinate system; arranging feature points; installing an N+2 tube segment; installing an N+1 tube segment;, and pushing out an abutting section; wherein the first coordinate system is established at the tail end of an N+3 tube segment; passage points N+1S, N+1W are separately arranged at the head and tail ends of the N+1 tube segment, passage points DS and DW are arranged at the abutment section, and passage points N+2S and N+2W are separately arranged at the head and tail ends of the N+2 tube segment; and coordinates of the passage points DS, DW, N+1S, N+1W, N+2S, N+2W are calculated in the first coordinate system. The installation method can increase the installation precision of a final joint, and has easy operations.
La présente demande appartient au domaine de la construction de joint final et concerne un procédé d'installation pour un joint final d'un tunnel tubulaire immergé. Le procédé d'installation comprend les étapes consistant à : établir un premier système de coordonnées ; agencer des points caractéristiques ; installer un segment de tube N+2 ; installer un segment de tube N+1 ; et pousser vers l'extérieur une section de butée ; le premier système de coordonnées étant établi à l'extrémité de queue d'un segment de tube N+3 ; des points de passage N+1S, N+1W étant agencés séparément au niveau des extrémités de tête et de queue du segment de tube N+1, des points de passage DS et DW étant agencés au niveau de la section de butée, et des points de passage N+2S et N+2W étant agencés séparément au niveau des extrémités de tête et de queue du segment de tube N+2 ; et des coordonnées des points de passage DS, DW, N+1S, N+1W, N+2S, N+2W étant calculées dans le premier système de coordonnées. Le procédé d'installation peut augmenter la précision d'installation d'un joint final, et présente des opérations faciles.
本申请涉及一种沉管隧道最终接头的安装方法,属于最终接头施工领域,该安装方法包括建立第一坐标系、布设特征点、安装N+2管节、安装N+1管节和推出顶进节段等步骤;其中第一坐标系建立于N+3管节的尾端;在N+1管节的首尾端分别布设贯通点N+1S、N+1W,在顶进节段布设贯通点DS、DW,在N+2管节的首尾端分别布设贯通点N+2S、N+2W;并分别计算贯通点DS、DW、N+1S、N+1W、N+2S、N+2W在第一坐标系的坐标;该安装方法可以增加最终接头的安装精度并且易操作。
INSTALLATION METHOD FOR FINAL JOINT OF IMMERSED TUBE TUNNEL
PROCÉDÉ D'INSTALLATION POUR JOINT FINAL DE TUNNEL TUBULAIRE IMMERGÉ
沉管隧道最终接头的安装方法
LI YIYONG (author) / ZHANG NAISHOU (author) / CHENG YIPIN (author) / ZHANG CHAO (author) / SUO XUHONG (author) / HAN ZHANWEI (author) / TAO ZHENJIE (author) / ZHU YONGSHUAI (author) / YU BO (author) / DU CHUANG (author)
2024-07-25
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
INSTALLATION METHOD FOR FINAL JOINT OF IMMERSED TUBE TUNNEL
European Patent Office | 2024
|Construction method of immersed tube joint in immersed tube tunnel and immersed tube joint structure
European Patent Office | 2021
|Combined immersed tube joint for immersed tube tunnel and construction method
European Patent Office | 2023
|Final joint of immersed tunnel as well as prefabrication method and installation method
European Patent Office | 2020
|FINAL JOINT OF IMMERSED TUNNEL AS WELL AS PREFABRICATION METHOD AND INSTALLATION METHOD
European Patent Office | 2018
|