Clarence Cannon Dam and Reservoir: Cost, Schedule, and Safety Problems: Corps of Engineers (Civil Functions). Department of the Army
The cost of the Clarence Cannon Dam and Reservoir project has more than tripled since 1962 primarily because of inflation and estimating and design refinements. Scheduled completion has been delayed 8 years. The main dam may not be as safe as originally designed because wet fill material was used in the foundation. Dam safety should be verified by an independent consultant.
Clarence Cannon Dam and Reservoir: Cost, Schedule, and Safety Problems: Corps of Engineers (Civil Functions). Department of the Army
The cost of the Clarence Cannon Dam and Reservoir project has more than tripled since 1962 primarily because of inflation and estimating and design refinements. Scheduled completion has been delayed 8 years. The main dam may not be as safe as originally designed because wet fill material was used in the foundation. Dam safety should be verified by an independent consultant.
Clarence Cannon Dam and Reservoir: Cost, Schedule, and Safety Problems: Corps of Engineers (Civil Functions). Department of the Army
1977
29 pages
Report