Technology of repeated grouting of concrete dams
Conclusions Grouting works during regrouting of high-head concrete dams are carried out by a special technology substantially differing in many parameters from the traditional technology specified for initial grouting of joints.The main purpose of regrouting a dam after several years of its operation under a load is to bring the stress—strain state to the design parameters.The main condition of correct solution of problems of regrouting of dam joints is drawing up a competent professional plan.The basis of the technology of repeated (multiple) grouting of joints having small, supersmall, and nonuniform openings is the use of high-penetrability grouts (HPG technology) in combination (in the case of detected manually uneliminable leaks) with grouts with an adjustable mobility loss time (GAMLT technology). As a consequence of this — the presence of special, quite stringent technological rules of preparing and using such grouts.
Technology of repeated grouting of concrete dams
Conclusions Grouting works during regrouting of high-head concrete dams are carried out by a special technology substantially differing in many parameters from the traditional technology specified for initial grouting of joints.The main purpose of regrouting a dam after several years of its operation under a load is to bring the stress—strain state to the design parameters.The main condition of correct solution of problems of regrouting of dam joints is drawing up a competent professional plan.The basis of the technology of repeated (multiple) grouting of joints having small, supersmall, and nonuniform openings is the use of high-penetrability grouts (HPG technology) in combination (in the case of detected manually uneliminable leaks) with grouts with an adjustable mobility loss time (GAMLT technology). As a consequence of this — the presence of special, quite stringent technological rules of preparing and using such grouts.
Technology of repeated grouting of concrete dams
Pronina, L. É. (author) / Ashikhmen, V. A. (author)
1996
Article (Journal)
English
BKL:
56.30
Wasserbau
Local classification TIB:
770/6550/8000
Technology of Repeated Grouting of Concrete Dams
British Library Online Contents | 1996
|Technology of repeated grouting of concrete dams
Springer Verlag | 1996
|British Library Conference Proceedings | 1991
|Repeated joint-grouting of Roller Compacted Concrete arch dam
British Library Conference Proceedings | 2003
|Grouting of cracks in concrete dams: numerical modelling and structural behaviour